Session 2015-16
Internet Publications
Other Bills before Parliament


 
 

551

 

SUPPLEMENT TO THE VOTES AND PROCEEDINGS

 
 

Monday 14 March 2016

 

Report Stage Proceedings

 

Energy Bill [Lords], As Amended


 

[First Sitting]


 

New Clauses relating to wind power; amendments to part 5

 

Callum McCaig

 

Withdrawn  NC2

 

To move the following Clause—

 

         

“Onshore wind power: renewables obligation

 

The power to make a renewables obligation closure order in respect of electricity

 

generated by an onshore wind generating station in Scotland may only be

 

exercised by Scottish Ministers.”

 

 


 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Negatived on division  24

 

Clause  79,  page  46,  line  20,  leave out “31 March 2016” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  25

 

Clause  79,  page  46,  line  25,  leave out “31 March 2016” and insert “1 March 2017”

 



 
 

Report Stage Proceedings: 14 March 2016                  

552

 

Energy Bill-[Lords], continued

 
 

Mr Alistair Carmichael

 

Not called  22

 

Page  47,  line  22,  leave out Clause 80

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  26

 

Clause  80,  page  47,  line  27,  leave out “31 March 2016” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  27

 

Clause  80,  page  47,  line  30,  leave out “31 March 2016” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  28

 

Clause  80,  page  47,  line  36,  leave out “31 March 2017” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  29

 

Clause  80,  page  47,  line  42,  leave out “31 March 2017” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  30

 

Clause  80,  page  48,  line  3,  leave out “31 March 2016” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  31

 

Clause  80,  page  48,  line  6,  leave out “31 March 2017” and insert “1 March 2017”


 
 

Report Stage Proceedings: 14 March 2016                  

553

 

Energy Bill-[Lords], continued

 
 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  32

 

Clause  80,  page  48,  line  20,  leave out “31 March 2016” and insert “1 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  33

 

Clause  80,  page  48,  line  33,  leave out “1 April 2017” and insert “2 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  34

 

Clause  80,  page  48,  line  43,  leave out “1 April 2017” and insert “2 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  35

 

Clause  80,  page  49,  line  8,  leave out “1 April 2017” and insert “2 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  36

 

Clause  80,  page  49,  line  17,  leave out “1 April 2017” and insert “2 March 2017”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  37

 

Clause  80,  page  50,  line  13,  leave out “18 June 2015” and insert “18 May 2016”

 

Philip Boswell

 

Not called  1

 

Clause  80,  page  50,  line  18,  leave out “planning permission” and insert “an

 

application for 1990 Act permission or 1997 Act permission”


 
 

Report Stage Proceedings: 14 March 2016                  

554

 

Energy Bill-[Lords], continued

 
 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  38

 

Clause  80,  page  50,  line  19,  leave out “18 June 2015” and insert “18 May 2016”

 

Philip Boswell

 

Not called  2

 

Clause  80,  page  50,  line  20,  leave out “or judicial review”

 

Philip Boswell

 

Not called  3

 

Clause  80,  page  50,  line  30,  after “Act” insert “(excluding an extension agreed for

 

the purposes of section 78(2) of the 1990 Act or section 47(2) of the 1997 Act)”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  52

 

Clause  80,  page  50,  line  34,  after “application”, insert “(provided that this period

 

does not include any extension agreed for the purposes of section 78(2) of the 1990 Act

 

or section 47(2) of the 1997 Act”

 

Philip Boswell

 

Not called  4

 

Clause  80,  page  50,  line  35,  leave out paragraph (iii)

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  39

 

Clause  80,  page  50,  line  40,  leave out “18 June 2015” and insert “18 May 2016”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  53

 

Clause  80,  page  50,  line  40,  after “18th June 2015”, insert “whether”

 

Philip Boswell

 

Not called  6

 

Clause  80,  page  50,  line  40,  leave out “following an appeal”


 
 

Report Stage Proceedings: 14 March 2016                  

555

 

Energy Bill-[Lords], continued

 
 

Philip Boswell

 

Not called  5

 

Clause  80,  page  50,  line  40,  after “following an appeal” insert—

 

“or a decision made by the Secretary of State, Welsh Ministers or Scottish

 

Ministers following directions given under section 77 of the 1990 Act or

 

section 46 of the 1997 Act, and”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Not called  54

 

Clause  80,  page  50,  line  40,  after “appeal”, insert “or otherwise”

 

Lisa Nandy

 

Dr Alan Whitehead

 

Barry Gardiner

 

Clive Lewis

 

Caroline Lucas

 

Not called  23

 

Clause  80,  page  50,  line  46,  at end insert “, or

 

(e)    

evidence that—

 

(i)    

an application for 1990 Act permission or 1997 Act permission

 

was made on or before 18th June 2015 for the station or for

 

additional capacity,

 

(ii)    

a grant of planning permission was resolved by the relevant

 

planning authority on or before 18th June 2015,

 

(iii)    

planning permission was granted after 18th June 2015, and

 

(iv)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  7

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

an application for 1990 Act permission or 1997 Act permission

 

was made on or before 18 June 2015 for the station or additional

 

capacity,

 

(ii)    

the period allowed under section 78(2) of the 1990 Act or (as the

 

case may be) section 47(2) of the 1997 Act (excluding an

 

extension agreed for the purposes of section 78(2) of the 1990

 

Act or section 47(2) of the 1997 Act) ended on or before 18 June

 

2015 without the things mentioned in section 78(2)(a) or (aa) of

 

the 1990 Act or section 47(2)(a) or (b) of the 1997 Act being

 

done in respect of the application,

 

(iii)    

the application was referred to the Secretary of State, Welsh

 

Ministers or Scottish Ministers in accordance with directions

 

given under section 77 of the 1990 Act or section 46 of the 1997

 

Act,

 

(iv)    

1990 Act permission or 1997 Act permission was granted after

 

18 June 2015, and


 
 

Report Stage Proceedings: 14 March 2016                  

556

 

Energy Bill-[Lords], continued

 
 

(v)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Negatived on division  8

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

an application for 1990 Act permission or 1997 Act permission

 

was made on or before 18 June 2015 for the station or for

 

additional capacity,

 

(ii)    

the relevant planning authority resolved to grant 1990 Act

 

permission or 1997 Act permission on or before 18 June 2015,

 

(iii)    

1990 Act permission or 1997 Act permission was granted after

 

18 June 2015, and

 

(iv)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  9

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

an application for consent for the station or for additional

 

capacity was made under section 36 of this Act,

 

(ii)    

the consultation period prescribed by Regulations made under

 

paragraphs 2(3) or 3(1)(c) of Schedule 8 to this Act had expired

 

on or before 18 June 2015,

 

(iii)    

the Secretary of State caused a public inquiry to be held under

 

paragraph 2(2) or 3(3) of Schedule 8 to this Act or decided that a

 

public inquiry need not be held,

 

(iv)    

consent was granted by the Secretary of State after 18 June 2015,

 

and

 

(v)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  10

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

an application for development consent for the station or for

 

additional capacity was made under section 37 of the Planning

 

Act 2008,

 

(ii)    

the deadline for receipt of representations under section 56(4) of

 

the Planning Act 2008 had expired on or before 18 June 2015,

 

(iii)    

consent was granted by the Secretary of State after 18 June 2015,

 

and

 

(iv)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”


 
 

Report Stage Proceedings: 14 March 2016                  

557

 

Energy Bill-[Lords], continued

 
 

Philip Boswell

 

Not called  11

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

planning permission for the station or additional capacity was

 

granted on or before 18 June 2015,

 

(ii)    

planning permission under sections 73, 90(2), 90(2ZA) or 96A

 

of the 1990 Act or sections 42, 57(2), 57(2ZA) or 64 of the 1997

 

Act, a consent under section 36C of this Act, or an order under

 

section 153 of, and paragraph 2 or 3 of Schedule 6 to, the

 

Planning Act 2008 varying the planning permission under clause

 

32LJ(4)(i)(i) was granted after 18 June 2015, and

 

(iii)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  12

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

1990 Act permission or 1997 Act permission for the station or

 

additional capacity was granted on or before 18 June 2015,

 

(ii)    

consent under section 36 of this Act that permits a greater

 

capacity for the station than that permitted by the planning

 

permission under clause 32LJ(4)(j)(i) was granted after 18 June

 

2015, and

 

(iii)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  13

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

planning permission for the station or additional capacity was

 

granted on or before 18 June 2015,

 

(ii)    

planning permission under clause 32LJ(4)(k)(i) was superseded

 

by a subsequent planning permission granted after 18 June 2015

 

permitting a station with the same or a lower capacity than that

 

granted under the planning permission referred to in clause

 

32LJ(4)(k)(i), and

 

(iii)    

any conditions as to the time period within which the

 

development to which the permission relates must be begun have

 

not been breached.”

 

Philip Boswell

 

Not called  14

 

Clause  80,  page  50,  line  46,  at end insert—

 

“( )    

evidence that—

 

(i)    

planning permission for the station or additional capacity was

 

granted or refused on or before 18 June 2015, and was

 

subsequently confirmed or granted after that date following a

 

statutory challenge under section 288 of the 1990 Act, section


 
Back to StartNext
 

Revised 15 March 2016