Select Committee on Trade and Industry First Report



The review period

  56. The DGGS has set a 5 year price control for British Gas TransCo,[107] while the DGES has opted for a 4 year duration for transmission and 5 years for the distribution price controls of electricity. The DGES believes that a price control period has to be sufficiently long to give the company a period of relative certainty within which it can work to reduce costs, and undertake investment, with the knowledge that the cost savings are not going to be taken away from it, but not "so long that conditions can change, so the control can turn out to be far too lax or far too tight".[108] In his opinion "a period of 4 to 5 years is about the sort of time".[109]

  57. Companies generally disagreed with this, claiming that they need a longer period to improve efficiency and undertake investments. The only persuasive argument for a longer price review period was that put forward by the NGC. NGC claimed that the "periodic reviews of prices which the company is allowed to charge for use of its system are on a far shorter time-scale than the asset lives".[110] "Accordingly, significant change by the regulator from one review period to the next of one or more key financial variables which determine the final RPI-X price control can considerably undermine the capacity to ensure a stable background for continuing investment".[111] We are not convinced. NGC's argument appears to be based essentially on the lack of consistency in the regulatory framework, particularly with regard to the calculation of the asset base and the cost of capital which determines allowed revenue. If the regulator were to adopt a more consistent approach to calculating NGC's valuation of assets and allowable revenues (see paras 67 onwards), then there would be no reason for extending the price control period beyond 4 or 5 years. In any case there is a risk that, if the review period were to be extended, there would be greater temptation to revisit it in between the reviews if any of the variables or assumptions were to change significantly.

  58. NGC argued very strongly for a 5 rather than a 4 year price review period, during the recent transmission price control review. After consideration and consultation, the DGES rejected their proposal and concluded that a 4 year price review period should remain. His arguments were based on the fact that there was scope for considerable change in the transmission business, and there was uncertainty about the level of new competition entering the market and the level of NGC's non-controllable operating costs and that he took developments further ahead than 4 years into account in his price control review.[112]

  59. The length of the review period chosen depends very much on the circumstances within the industry. For example, with further liberalisation of the gas and electricity markets, the regulators may think it appropriate to review some sectors more frequently until the markets settle. There are nonetheless strong arguments for 5 years in transmission, particularly as experience is gained with the passage of time and forecasts improve and the amount of inefficiency remaining is reduced.

  60. There has only been one occasion when an energy regulator has reconsidered a price review. The DGES, in March 1995, decided to reconsider distribution prices less than 12 months after completing the first review but before the new regime was formally in place. This occurred because the DGES came to the view that the price control he had proposed in August 1994 was no longer appropriate, as circumstances had changed sufficiently since setting the original controls. He argued that essential new information had come to light concerning share price movements and the terms of the Trafalgar House bid for Northern Electric.[113] The DGES believed that "although re-examining the proposed controls might increase uncertainty in the short term, I considered that this was preferable to the risk that, if I did nothing, the implemented controls might need to be re-opened before the end of their five year term."[114] We examined the DGES's decision to re-open the price control review at length in our report Aspects of the Electricity Supply Industry, July 1995 (HC 481-I) in which we were critical about the rigour with which the DGES had scrutinised distribution and transmission revenue and costs. We concluded that, on balance, the DGES was right to re-open the review, mainly because "the review was reopened before the revised price control had come into effect and during the period allowed for representations or objections, and the very idea of inviting representations or objections must indicate that a reconsideration is possible".[115] We then recommended that "such a procedure be avoided in the future", so as not to create regulatory uncertainty and undermine the credibility of the regulatory system.[116]

  61. Several witnesses argued that, if the regulators were to re-open a review as a matter of course, price regulation would deteriorate into a complicated form of rate of return regulation,[117] it would undermine the regulatory contract, affect investors' legitimate expectations and "will tend to increase the cost of capital, to the ultimate detriment of customers".[118] The DGES told us that the circumstances have to be "pretty exceptional" before a price review can be re-opened and he does not see "major events occurring over the next few years that would necessitate re-opening a price control".[119] We recognise that revisiting a price review can cause instability, which could be detrimental to the industry given the need for long-term investments; however, no one reported to us any significant adverse affects resulting from the re-opening of the electricity distribution review. Our conclusion remains the same as before. We believe that regulators should not in general re-open price reviews, for reasons of consistency, equity and the maintenance of incentives, although we cannot rule it out completely where there have been significant and exceptional changes in circumstances.


107  OFGAS press notice, 21.7.96. Back

108  Q.1013. Back

109  Q.1013. Back

110  Ev. p.44. Back

111  Ev. p.41. Back

112  OFFER, The Transmission Price Control Review of the National Grid Company: Proposals, 1996, pp.6-7. Back

113  OFFER, Annual Report 1995 pp.28-29. Back

114  OFFER, Annual Report 1995 p.7. Back

115  Eleventh Report from the Trade and Industry Committee, Session 1994-95, on Aspects of the Electricity Supply Industry, HC 481-I, para 94. Back

116  Ibid. Back

117  eg. Mem. p.96. Back

118  Ev. p.209. Back

119  Q.1014. Back


 
previous page contents next page
House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1997
Prepared 18 March 1997