7.38 pm
Miss Anne McIntosh (Vale of York): I welcome this opportunity to raise a matter of great concern to my constituents and those of neighbouring hon. Members, including the Leader of the Opposition, my right hon. Friend the Member for Richmond, Yorks (Mr. Hague), and my hon. Friend the Member for Ryedale (Mr. Greenway).
The subject of overhead pylons through the Vale of York was first debated in 1991, and subsequently in 1992 and 1995. The discussions concerned the building of a new gas-fired power station at the ICI Wilton complex on Teesside, which was granted planning permission in 1991 and has subsequently been constructed. Rumours are circulating about a proposal for a new power station to be built in the Newcastle area which would create the totally unacceptable possibility of further transmission implications. The Minister for Science, Energy and Industry may be able to respond to my concerns.
It was only subsequent to the granting of planning permission for the ICI Wilton complex that the National Grid Company proposed to construct new transmission lines running from Lackenby in Cleveland to Pickton in North Yorkshire, and then south to Shipton near York. One point of concern on which I would like the Minister to comment is that these two applications were treated for planning purposes as two separate events. The power stations gained planning permission without any apparent consideration of the environmental impact of the subsequent construction of 60 miles of pylons through some of the most stunningly beautiful countryside in rural England.
My first concern is the impact on the environment. The House will be familiar with the work of REVOLT, which stands for Rural England Versus Overhead Line Transmission. It has 300 active members, stretching to 10,000 signatories of various petitions. That reflects the increasingly vociferous support for the REVOLT campaign throughout north Yorkshire. REVOLT and local residents have consistently argued that the lines were unnecessary, and that is my principal point this evening.
The Teesside complex has been built and, subsequently, there has been no transmission from the plant. The new power station will use apparently spare transmission lines. My constituents, and those of other hon. Members in North Yorkshire, are concerned about that. If there were a proven need, there would not have been the campaign or the strength of feeling against the proposed pylons.
There is also the perceived health hazard, an aspect which has not been investigated fully either by this House or by the public inquiries. The fundamental concern is that the proposal would harm the visual outlook of rural North Yorkshire and would have a negative impact on the prices of housing and other amenities in the immediate residential areas surrounding the pylons.
North Yorkshire county council has lent its full support to the campaign and has consistently spoken against the pylons. The council is unconvinced that the line is required, and believes that the environmental impact of
the construction is too high a price to pay and that the procedures leading to the present situation have been wrong.
I would like to ask the Minister a number of questions. Have the Government actively discharged their duty under the European Union directive on environmental impact assessment--adopted in 1985--specifically article 3 and annexe 3 thereof? Have they undertaken a specific environmental impact assessment to identify, describe and assess the direct, indirect and secondary effects of the proposed line of pylons on the environment? It would be a source of satisfaction to the House if the Minister could report that such an impact assessment has been carried out. We are obliged under the directive and our treaty obligations to pursue such an assessment.
My information is that such an assessment has not taken place, and I would like to report to my constituents that it will. Have the Government considered the negative impact on local amenities and specifically house prices, which would plummet should the pylons be constructed? Are the Government in a position to rule on the inspector's report and recommendations following the last public inquiry? The report has been with the Department of Trade and Industry for approximately two years.
During the recent general election campaign, there was without a shadow of a doubt all-party support for the campaign against the construction of the pylons. The Labour candidate for my constituency promised to deliver a decision in the early days of a Labour Government that that Government would reject the proposals. I asked whether any candidate from any party or any member of any Government could deliver such a pledge, but the Minister has an excellent opportunity to deliver.
If the Minister is unable--or does not have the competence--to reach such a decision, will he agree that the figures placed before the inspector at the last inquiry for the cost of transmission were erroneous? Will the Minister instruct another inquiry to assess the true cost? In my view, the true cost would reflect as a 15 per cent. loss in transmission--representing, at a conservative estimate, a £660 million loss to consumers.
I accept that power stations are competitive, but they obtain a subsidy for long-distance transmission on the grid. They have an artificial incentive to locate near the fuel source and far from the end consumer. Does the Minister agree that the preferred option for industry, the consumer and the environment is to locate the power supply as close to the point of demand as possible? Will the Government therefore consider the option of underground transmission? Has this been considered or costed? Sweden and Australia have ruled that no alternative to underground transmission of electricity and gas supplies will be considered in future.
As Sizewell B is now on line, what need is there for increased electricity in the south? Do not Sizewell A and B together satisfy the demand in the south, with resultant cheaper transmission costs?
If the line were consented to, the door would be open, contractually, to increase Scottish imports to the south of England, which raises a wider national issue. There is no proven need for the pylons. It is my view and that of many of my constituents that erroneous transmission costs were presented to the inquiry. I urge that the true costs be investigated.
Information exists that could show that the previous inquiry was crucially misinformed, and that gives good reasons for an early rejection of the proposed line of pylons. Failing that, I plead for the option of reopening the inquiry so that need, finances and the environment can finally be considered.
I invite the Minister to rule against the construction of these ugly and obscene pylons in the interests of preserving our countryside as we know it and keeping rural England as stunningly beautiful as the Vale of York that we enjoy today. The people of the Vale of York are in the Government's hands and we await with eager anticipation a definitive decision against the construction of the pylons or, at the very least, a decision to open inquiries on the perceived need, the cost, the environmental impact and the knock-on effects on amenities and housing.
Mr. John Austin (Erith and Thamesmead):
I am extremely grateful to the hon. Member for Vale of York (Miss McIntosh) for allowing me to speak in her Adjournment debate. Hon. Members may be wondering why a London Member should be speaking on an issue concerning the Vale of York. I can explain that simply: BICC Cables--one of the few pieces of manufacturing industry left in London, and a world-class business which exports about 60 per cent. of its turnover but is also dependent on its United Kingdom business, as a major supplier to the National Grid Company--is located in my constituency.
I recognise the hon. Lady's strength of feeling and determination to campaign on environmental issues in her constituency, as I have done in mine when it has been threatened by motorways or roads through areas of outstanding natural beauty, but I must state the position as it may affect employees and businesses in my constituency.
The National Grid Company has a statutory obligation, determined not by Labour but by the previous Government, to connect all licensed generators to its transmission system and to transmit power generated by the licence holder to areas of need, no matter how many tens or even hundreds of kilometres away. There is currently excess generating capacity in Scotland and the north-east of England. It has been estimated that restricting the use of power stations in those areas may be costing as much as £50 million a year. I believe that the Department of Trade and Industry has an obligation to avoid that waste.
BICC is also involved with underground cables, and welcomed the decision of the first public inquiry, in 1992, to put part of the link underground. On environmental grounds, I should like as much as possible of any transmission link to be underground; that would be good news for the environment as well as for employees in Erith.
Labour cannot be held responsible for delays. Problems have been created for BICC, which first became aware of the project in 1991. The first public inquiry was in 1992,
and, from 1993 to 1995, BICC did a great deal of preparatory work and detailed engineering study. The public inquiry recommendation published in 1994 gave approval for the link, with the stipulation that the section at Nunthorpe should be underground. The then President of the Board of Trade said that he was minded to accept the inquiry's findings. On that basis, BICC has continued to invest in the project and to keep spare capacity available at its factory in Erith; it has therefore suffered some detriment.