PROJECT
FUNDING AND
PROCUREMENT
Background
5.1 Each flood defence region is allocated
a fixed amount of MAFF grant each year. The MAFF grant covers
a fixed percentage of a scheme's total cost. The portion funded
by MAFF varies between the regions, sparsely populated areas with
large expenditure requirements receive a higher percentage grant
for capital projects. The balance of the funding for projects
is obtained from the Local Authority Levy.
5.2 The significant features of this funding
method described above are:
There is a finite amount of funds
for each region each period particularly as levy funds can only
be committed within the committee area in which it is received;
Funding is awarded annually;
Although MAFF do have a priority
scoring system the application of funds may still be influenced
by the availability of local funding.
5.3 These features have hitherto prevented
The Environment Agency awarding long term contracts spanning several
funding periods with the result that:
Schemes progress can be inhibited
by the need to carry out construction over several years in line
with the availability of funds;
The contracts awarded are smaller
and can result in several contracts for a single scheme creating
inefficiencies as contracts are wound up and down;
The need for The Agency to retain
funds for emergency work in each region throughout the year results
in each region being put under pressure to use up its budget towards
the end of the financial year in February and March when bad weather
conditions can make working less effective.
Observations on Funding
5.4 The above constraining features of the
funding arrangements and the issues raised earlier in respect
of management and control combine to produce micro rather than
macro solutions to flood defence needs. This is because:
the geographical authority limits
of the RFDCs and LFDCs necessarily suggest projects within those
geographical limits; and
time limitations created by financial
years dictate the size of individual contracts in respect of project
works and the timetable in which construction takes place.
5.5 In the previous section of this submission,
reference was made to the likelihood of an escalating long term
liability for flood defences in England and Wales. One of the
ways in which to address this liability would be to ensure the
total flood defence funds available for England and Wales are
committed in the most effective manner for the countries as a
whole. This is only likely to be achieved if:
a single entity is responsible for
the management of flood defences, not including drainage, in England
and Wales and for the allocation of funding associated with the
provision and maintenance of flood defences;
a greater freedom is provided to
permit the entity responsible for flood defences to enter into
term contracts which involve on-going commitments across an extended
number of Government financial years;
more innovative procurement methods
are explored and exploited where appropriate.
Procurement Issues
5.6 Typically, flood defences have normally
been procured through a conventional process of requiring contractors
to bid competitively for works which have been specified by independent
consulting engineers acting on terms of reference provided by
the Environment Agency.
5.7 Currently, two flood defence schemes
are being tendered with a view to their being awarded on the basis
of a PFI/Partnering relationship. The discussions that have taken
place within the market generally and bidders in particular suggest
that:
an even stronger private sector involvement
would be forthcoming if flood defence schemes were larger in scale
and offered greater opportunity for design innovation, particularly
if this were allowed to evolve over the concession period;
there is considerable scepticism
as to whether or not the Government will actually commit to long
term Partnering contracts in view of the long term funding commitments.
5.8 Ernst & Young suggest that it is
important that greater private sector participation is harnessed
in order to promote design, construction and operational efficiency
in the provision and maintenance of flood defences. This could
perhaps be most effectively provided by creating a number of concession
areas and requiring the successful bidder to provide flood defence
management for the duration of the concession period. It would
be for the contractor to determine the appropriate means of providing
such flood defences subject to guidance concerning minimum standards
by the responsible Government authority. This minimum level need
not correspond to the current levels that would be indicated by
PAGN.
5.9 Further, it should be noted that many
new and innovative financial products are now being developed
in assist to develop business in managing risks. Such products
are emerging in respect of flood defences and may offer a more
cost effective mechanism than physical defence works in addressing
certain areas of risk.
7 April 1998