Select Committee on Health Report


EXPLANATION FOR PROJECTS WITH SIGNIFICANT DIFFERENCES BETWEEN ORIGINAL AND CURRENT ESTIMATE INFORMATION

2.   Bath Redevelopment

  Time Performance—The construction start on site was delayed to April 1998, one year later than originally planned. This delay has resulted in a revised completion date of April 2001, which represents a time overrun of 13.9 per cent on the original completion date.

3.   Royal Cornwall Treliske

  Time Performance—A five month delay to the original completion date is currently forecast, with completion now expected in August 1998. The Trust report that four months of this delay is due to poor contractor/consultant performance, with a further month due to estimating changes.

4.   Warrington

  Time Performance—The estimated completion date slipped because of a delay in awarding the contract due to client variations, plus a predicted 6-8 week slippage in construction works due to inclement weather and ground conditions.

5.   Royal Sussex County Hospital

  Time Performance—This project consists of 16 separate building contracts and the resequencing of a number of these has contributed to the overall completion date being delayed by two years. This represents a time overrun of 75.4 per cent on the original completion date.

6.   Bristol Royal for Sick Children

  Time Performance—The construction start on site was delayed by three months due to inclement weather and statutory authorities. This, along with a delay in the tender process for the main contract works, has resulted in a delay of 14 months to the original completion date.

  Cost Performance—A cost overrun of 16.81 per cent is currently forecast, the original estimate of expenditure of £21.93 million increasing to the current estimate of £25.62 million. The majority of this variation is attributed to design changes and external factors.

7.   Sunderland Scheme 3

  Time Performance—The construction start on site has been delayed, and is now forecast for June 1998, over ten months later than originally planned. This is due to the Architect, who was acting as lead consultant on this project, having their commission terminated. This delay has resulted in a revised completion date of March 2000, representing a time overun of 44.8 per cent on the original completion date.

4.8b  Would the Department provide details of PFI projects with a capital value of £10 million or over approved since 1992, including their current status

  1.  All projects with a capital value of £10 million or over are shown on the table provided in answer to 4.8c. Two projects over £10 million were shown in table C4.2 (HC 297) last year but are not shown this year. Details of these two projects are provided in table 4.8b.1.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 2 November 1998