Select Committee on Public Accounts Minutes of Evidence


APPENDIX 4

PRIVATISATION OF BELFAST INTERNATIONAL AIRPORT (PAC 97-98/105)

Supplementary Memoranda from the Department of the Environment (Northern Ireland)

Details of the Capital Expenditure Programme

  1. In December 1990, the Department sought and obtained general guidance from Treasury on how to handle investment proposals from NIAL during the period leading up to the sale of the business. Treasury advised that:

    "there should be a strong presumption against initiating capital investment projects in the run-up to privatisation unless it is absolutely essential to maintain the operations of the business; and projects of a discretionary nature should only be undertaken if, in addition to meeting the usual economic appraisal criteria (in terms of a satisfactory rate of return, etc.), the Accounting Officer of the sponsor department is able to demonstrate if challenged by the Committee of Public Accounts, that the investment had increased disposal proceeds by a sum significantly greater than the costs of carrying the investment forward".

  2. The Treasury guidance also warned of projects that would span the date of privatisation. "Limited experience of such projects has suggested that potential purchasers will use all possible arguments to seek to reduce any beneficial impact on sales proceeds, or even to achieve a discount." DOE sought to have any on-going projects completed before the sale took place.

  3. Of the £25.5 million of expenditure highlighted in the NIAO report at para 5.8, £19 million was spent on schemes which were approved and started before December 1990. £13 million was spent on a cargo centre and an extension to the passenger terminal. Both projects were subject to investment appraisal and met the Treasury requirements on rate of return over 15 years. The cargo centre received DFP approval in principle in December 1987 and the East Terminal Extension was approved in principle by DFP in August 1988. These projects received 50% ERDF funding.

  4. The additional £6 million was approved in the Corporate Plans prior to the announcement that the airport was a candidate for privatisation and was spent in the three year period to March 1991. These schemes included:

Buffet Refurbishment £325k
International Baggage Reclaim £547k
Land Purchases (for security reasons) £875k
Fire vehicles £778k
Clendennings Car park £838k
Police Station extension £170k
BMA Lounge £420k
Computer upgrade £250k
West Pier Accommodation £138k


  5. The NIAO Report states at para 5.19 that, during 1992, NIAL initiated a block of twelve new capital projects costing approximately £5.7 million in total. The Department believes that this reference relates to projects which attracted ERDF grant after September 1991 and cost approximately £5.2 million in total.

  6. On their appointment in July 1992, Touche Ross were immediately asked to review NIAL's capital expenditure plans against Treasury guidelines. On 1 July 1992, the Department wrote to Touche Ross supplying a list of 12 projects which NIAL wished to add to the ERDF Transportation Programme. This list did not include the Choke Point Relief, the Landscape Infrastructure or the Roads and Car Park Rationalisation Schemes which were linked with the on-going scrutiny of the larger Check-in proposal. The Department asked whether the projects were supported within existing, or were likely to be supported within future, corporate plans and, as such, could be eligible for grant. Touche Ross advised that the NIAL investment in the ERDF schemes was consistent with Treasury guidelines.

  7. The Touche Ross assessment of the projects found that they were either in the essential category or were the completion phases of schemes which had been approved in previous corporate plans. This assessment was presented to the Privatisation Committee, which included representatives of DFP and Treasury, on 5 November 1992. The Committee agreed that these projects would be acceptable in the context of privatisation, although without prejudice to the normal process of PE approval within the corporate plan.

  8. It is the Department's view that the schemes all met the Treasury criterion of being essential to maintain operations and, because of the availability of 50% ERDF funding, benefited the sales proceeds.

  9. Details of 11 schemes accounting for £5.45 million are set out below; a twelfth scheme, an extension to the cargo terminal to secure the tenancy of a major cargo handling business, was initiated in February 1991 at a cost of £627k.

9.1 Additions to East Terminal Extension (£1.2m)

  This work involved modifications to the recently constructed East Terminal Extension to cover finishings which were to be undertaken as part of the Check-in project, to take on board new fire safety requirements and the purchase of CCTV to improve terminal security. The last two items of expenditure had been approved by DOE in the 1992 Corporate Plan and the additional expenditure was taken forward as an extension to the East Terminal ERDF grant scheme.

  The East Terminal Extension project had been approved by DOE in August 1988, following a satisfactory investment appraisal. The scheme received ERDF grant of 50%. It was virtually complete by 1991, although there remained some minor works which were pending decisions on the future of the adjacent Check-in project (abandoned in 1992).

9.2 Air Traffic Control Equipment (four projects)

  Four of the projects, relating to Air Traffic Control Equipment, were identified as essential replacements or improvements in the Civil Aviation Authority (CAA) Capital Plan 1991/92-95/96 or as necessary to meet new CAA regulations. In the 1992 Corporate Plan, NIAL proposed expenditure of £5.4 million over 5 years to purchase the equipment necessary to implement the CAA plan. The existing equipment was owned by CAA, who operated ATC at the airport. NIAL proposed to purchase the new equipment and thereby reduce the annual CAA charge by approximately £1 million. In approving the 1992 Corporate Plan, DOE said that each element of expenditure would be subject to an investment appraisal within the terms of the regulatory framework.

  On their appointment as privatisation advisers in July 1992, Touche Ross were asked to assess each of the items in the ATC equipment programme. They confirmed a number of purchases as essential before privatisation and agreed that these should go forward as four separate applications for ERDF grant. These projects and their total costs were:

    - Communications Equipment (£464k);

    - Various items of ATC equipment-Comms Recorder, ADIS and PAPI (£232k);

    - Airfield Lighting Control System and Signage (£234k); and

    - Distance Measuring Equipment (£176k).

9.3 Passenger Segregation

  Modifications to the terminal, costing £25k, were required to meet HM Customs requirements as a result of changes in the status of EC boundaries on 31 December 1992. The scheme was put forward at a projected cost of £250k in the Corporate Plan of 1992, which DOE approved in principle. Later that year, Touche Ross agreed that the project was essential and could be put forward for ERDF grant. The scheme was re-designed and completed in 1993 at a much reduced cost of £25k.

9.4 Flight Management System

  Expenditure on the Flight Management System [19] began in 1990, before the airport was considered suitable for privatisation. By 1992, £528k had been spent and DOE was content that it was essential to complete the project to avoid it spanning the date of privatisation. (Treasury Guidance advises the avoidance of projects which would span the date of privatisation).

  The Flight Management System is a computerised database which contains all the information necessary to enable the efficient management of the airport's resources. The project involved the installation of computer communication lines throughout the airport complex and the development of software to link databases of ATC, Airlines, handling agents, NIAL operations etc. FMS also replaced the Flight Information Display System giving information to passengers on arrivals and departures. The existing FIDS required replacement for technical and operational reasons. This involved the modernisation of supporting hardware and the installation of display monitors.

  This project was first put forward in the 1988 Corporate Plan at an estimated cost of £1 million. Work was started in 1990, before the airport became a candidate for privatisation, and proceeded as a number of stand-alone projects. By mid-1992, NIAL estimated that £528k had been spent and a further £770k was required to complete the project.

  In October 1992, NIAL asked Touche Ross to undertake an investment appraisal before proceeding any further. Touche Ross concluded that an investment of £284k was necessary for implementation and such investment would provide a high internal rate of return. They recommended that the purchase of replacement FIDS monitors, estimated at a cost of £90k, should be subject to separate investment appraisal.

  In November 1992, Touche Ross recommended that the remaining expenditure on the FMS project could be regarded as essential. NIAL applied for ERDF grant for the project at a revised total cost of £999,800.

9.5 Car Park Equipment

  This project costing £220k was essential to replace existing machinery which was 15 years old and unreliable and to introduce a more effective system. The concession agreement with National Car Parks expired in 1992 and NIAL wished to introduce a more cost effective "Pay-on-Foot" system.

  An investment of £750k was put forward in the 1992 Corporate Plan. This was approved by DOE subject to completion of satisfactory investment appraisal under the regulatory framework. Touche Ross in their review of the 1992 Corporate Plan found that the new equipment would deliver cost savings from improved payment methods and categorised the investment as essential.

  The equipment purchase received ERDF grant on a final total cost of £220k. Car Park rationalisation costs were picked up under another contract.

9.6 Choke Point Relief Scheme

  The abandonment of the two-storey Check-in project left the airport with a number of congestion problems within the terminal. Touche Ross tested a range of cheaper alternative designs against investment appraisal criteria and the Treasury privatisation guidelines and concluded that a modest level of expenditure (£975k) was necessary to improve the worst of the operational problems.

  The Choke Point Relief Project [20] was put forward and received approval in the 1993 Corporate Plan.

9.7 Landside Infrastructure and Roads and Car Park Rationalisation

  NIAL also brought forward in the 1993 Corporate Plan an item under the general heading of airport development, to spend £2.18 million on works to relieve congestion problems at the set-down area and on the approach roads, to improve the car parks and to carry out upgrading at various points within the terminal. The works were to be spread over 4 years. After DOE explained the Treasury Guidelines at an NIAL Committee meeting in February 1993, the NIAL Board dropped the terminal upgrading works and brought forward 2 separate projects for discussion with the Department in June and September 1993.

  The Landslide Infrastructure at the set-down/pick-up area [21] to include increased lanes, provided a new canopy at the set-down, security screens at the international exit and fire modifications to the Primary Search Building at a cost of £828k.

  Rationalisation of Road Layout and Car Parks [22] (£862k), brought forward in September, included new roadways to improve traffic flows to and from the set-down area and car parks, additional parking space, lighting and CCTV in the car parks and security fencing and landscaping.

  If any of these projects had been deferred until after privatisation, their essential nature would have necessitated immediate expenditure by the new owner. Such investment may have been without the assistance of the ERDF grant scheme which ended in 1993. It is likely that the full cost of the projects would have been reflected in a compensating reduction in the price bid.

  As para 5.31 of the NIAO Report says, DOE believes that the assumption made by NIAO about the impact of these projects on the cash reserves failed to recognise their potential to generate income or reduce outgoings, as in the case of the ATC equipment which in turn would have had a positive impact on NIAL's sale price. The NIAL Corporate Plan produced in March 1993 clearly identifies the car park equipment and most of the ATC equipment as "Earnings Projects".

Department of the Environment (NI)

5 January 1998


19   Further note not reported (PAC 157B). See also, Evidence, Appendix 6, page 22 (PAC 246) and Appendix 7, page 23 (PAC 157A). Back

20   Further note not reported (PAC 157B). See also, Evidence, Appendix 6, page 22 (PAC 246) and Appendix 7, page 23 (PAC 157A). Back

21   Further note not reported (PAC 157B). See also, Evidence, Appendix 6, page 22 (PAC 246) and Appendix 7, page 23 (PAC 157A). Back

22   Further note not reported (PAC 157B). See also, Evidence, Appendix 6, page 22 (PAC 246) and Appendix 7, page 23 (PAC 157A). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 14 May 1998