Select Committee on Public Accounts Thirty-Eighth Report


NORTHERN IRELAND: THE INDUSTRIAL RESEARCH AND TECHNOLOGY UNIT

ASSISTANCE FOR DEVELOPMENT OF MAJOR RESEARCH FACILITIES

21. IRTU provided £4.2 million assistance to a company to undertake research into the development of a new process for the manufacture of a synthetic rubber material. Some 12 months after payment of the final tranche of assistance, the project was terminated due to technical difficulties. The NIAO report raised concerns about the technical appraisal of the case, the non-involvement of IRTU's Casework Committee, the timing of the appraisal and the delay in formal evaluation of the case following termination.[22]

Technical Appraisal

22. The technical appraisal was carried out by the officials in the Technology Division of IRTU who were negotiating with the company. The reasons given by IRTU were the need to respond quickly to the decision deadlines set by the company, the need to handle the project tactfully and the familiarity of one of Technology Division's officials with the company's approach and house style.[23]

23. We asked the Department how they had ensured that their technical appraisers had achieved the necessary objectivity in this case. The Department said that they believed the technical appraisal was best conducted by those who were familiar with IRTU's schemes and objectives, had a thorough knowledge of the company and technical knowledge of the project in question. The Department told us that this was consistent with the practice elsewhere in the Department and in other industrial development agencies. They also considered that the financial appraisal, which had been carried out independently of Technology Division, had represented a safeguard.[24]

Non-involvement of the Casework Committee

24. Contrary to its standard appraisal procedures, IRTU did not submit the project for consideration by their Casework Committee.[25] In reply to our questions, the Department accepted that the procedures should have been followed and that the Casework Committee should have been involved in the process.[26]

Timing of the Appraisal

25. IRTU had exchanged unqualified letters with the company, in June and August 1992, on the scale of assistance. This was before completion of the appraisal in January 1993 and also prior to approval by the Department of Finance and Personnel.[27] While the Department told us that they believed the letters were understood by the company to be indicative offers, they now agreed that the letters should have been qualified and that that lesson had been learned. The Department said that procedures were now in place to ensure that this would not happen again.[28]

Evaluation of the Project

26. In March 1995, the project was terminated, due to technical difficulties. However, 18 months had elapsed, following the project's closure, before IRTU commissioned a formal evaluation of the case.[29] In explanation for the delay the Department said there was an expectation that there might be another project which could follow on from the original project but in fact that did not happen and they now accepted that the evaluation should have been carried out at an earlier stage.[30]

Documentation Standards

27. It was apparent in this case, and also several others which were examined, that IRTU's documentation procedures were deficient.[31] The Department agreed that there was some evidence in this examination that documentation has not always been as good as it

should have been and that it was one of the areas which they were trying to improve. The Department subsequently informed us that comprehensive operating manuals were now in place describing the procedures to be followed with particular emphasis being given to the importance of full documentation of all aspects of appraisal, monitoring and evaluation.[32]

Conclusions

28. We have considered the Department's comments about the technical appraisal very carefully. We appreciate the Department's desire to utilise, to best effect, the skills which exist within the organisation, but this must also take account of the importance of operating procedures which reinforce the objectivity and independence of the appraisal process. It is established good practice in other areas of selective financial assistance that, where the sums involved are large, the appraisal process should not be carried out by the officials who are directly responsible for progressing a project with a client company. In our view, this practice is a sensible safeguard and is as relevant to technical appraisal as it is to financial appraisal.

29. We found it surprising that the largest project which IRTU has supported was one which they failed to submit to the Casework Committee. We note the Department's acceptance that the Committee should have been involved and their assurance that they now have procedures in place to ensure that this does not happen again.

30. It is clear to us that, in failing to spell out the indicative nature of its offer, IRTU had committed themselves to assisting the project before it had been fully appraised. The Department accepted that the letters to the company should have been qualified by reference to the offer being conditional upon the successful completion of appraisal. We note their assurance that they now have procedures in place to ensure that this does not happen again.

31. It is important to ensure that formal evaluations are conducted promptly, following termination of projects, to ensure that any lessons are incorporated into IRTU's procedures at the earliest opportunity.

32. We note the Department's assurance that revised procedures have resolved documentation problems.

33. Overall, we take a very serious view of the series of deficiencies in IRTU's handling of this case. Our concerns have been heightened by the fact that this is the largest project ever assisted by IRTU and it should be clearly understood that the various shortcomings highlighted by the NIAO report are unacceptable. We note the assurances given by the Department that improved procedures are now in place.


22  C&AG (NI)'s Report paragraphs 3.2, 3.8, 3.18-3.19 Back

23  C&AG (NI)'s Report paragraphs 3.4, 3.9-3.12 Back

24  Qs 5-6, 13 Back

25   C&AG (NI)'s Report paragraphs 3.7, 3.13 Back

26  Qs 44-49, 68 Back

27  C&AG (NI)'s Report paragraphs 3.5-3.7, 3.14-3.16 Back

28  Qs 7-8, 68 Back

29  C&AG (NI)'s Report paragraphs 3.18-3.24 Back

30  Qs 14, 72-74 Back

31  C&AG (NI)'s Report paragraphs 2.10-2.12, 3.23 Back

32  Qs 15-18. Evidence, Appendix 1, p 10-11 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 26 May 1998