Select Committee on Public Accounts Minutes of Evidence


APPENDIX 2

CONTINGENT LIABILITIES IN THE DEPENDENT TERRITORIES (PAC 1997-98/119)

Memorandum by the Department for International Development

Note on Question 27: Completion of Capital Aid Projects

  1.  The question relates to paragraph 2.14 of the NAO Report, which states that ten of the twenty projects requiring completion reports were completed between two months and three years late and four did not show completion dates.

  2.  Of the ten projects which overran, four had delays of six months or less. With regard to the six projects which were shown as having significant delays, the background is as follows:

Turks and Caicos IslandsEstimated Actual
Completion Date Completion Date
2.1
Fisheries Development:March 1993 March 1995
Purchase of Vessel and
Equipment


  The project involved the purchase of a fishing vessel and gear in the UK and installation of an ice plant in the TCI together with vessel running costs for one year. The vessel and gear were procured by the Crown Agents and delivered on time (sea trials February 1989). The ice plant was due to be delivered in October 1989, but there was a delay with the supplier and a problem during installation which meant that plant did not become operational until March 1990. This project was later subsumed into the TCI fisheries development programme and additional funding was provided to meet running costs for a further three years together with some supplementary items of equipment. In effect the delay was much less than might be inferred from the project completion report.

2.2
Resurfacing SecondaryAugust 1990 June 1992
Roads


  This project was approved in August 1989 and ran on schedule until the spring of 1990 when the Public Works Department shifted their limited road building plant to higher priority construction of new roads. Work resumed twelve months later and the project went slowly due to a number of mechanical breakdowns with key items of equipment. As a result of these delays the project costs were 7% above target.

2.3
Fisheries ResourceDecember 1993 March 1995
Management


  This project was approved for biological research into the lobster and conch resources of the TCI. Lobster and conch are the main export from the islands, and stock conservation is therefore a key issue. The main project input was a British fisheries biologist.

  The project started approximately ten months late because the British researcher was not available until he had completed his research programme at Imperial College London. The particular research skills and experience required meant that there was only a limited field of possible candidates, and it was decided to wait for the preferred one.

2.4
Water ExtractionOctober 1990 July 1992
Treatment and Storage


  The project provided a 100,000 gallon water plant on the main tourist island of Providenciales. Approved in January 1990, work did not start until June 1991 due to problems with land acquisition (funded by the TCI Government). Due to this delay some engineering re-design was the then required to avoid cost escalation. The project was completed within the original budget.

AnguillaEstimated Actual
Completion Date Completion Date
2.5
Princess AlexandraDecember 1988 June 1993
Hospital


  Construction of this new hospital was originally planned to commence in February 1987 for a December 1988 completion date. An experienced firm of hospital architects were appointed by ODA, after competitive tender, to design the building and supervise construction. The British Development Division in the Caribbean also recommended to the Anguilla Government that they should appoint an experienced Clerk of Works to deal with day-to-day management issues on site. Due to the relatively small size of the contract, which would have made it uneconomic for a British contractor to mobilise on Anguilla, the project went out to local tender and work began in January 1988, some eleven months behind schedule. The contractor seemingly incorrectly priced elements of his bid and he ran into cashflow problems with regard to the purchase of materials and also, possibly, with regard to his ability to pay competitive rates for skilled labour from the limited pool available on the island. The contractor's difficulties were compounded by problems with the excavation of hard rock on site and delays in the delivery of some building materials from the UK and provision of the electricity supply and telephones by the utility companies.

British Virgin IslandsEstimated Actual
Completion Date Completion Date
2.6
All Weather Road LinkDecember 1990 February 1992


  The project involved the construction of 2.5 kilometres of concrete all- weather road to complete the road link on the island of Tortola. We have been unable to locate earlier papers on this project but it would appear that at least part of the problem with this project was due to the difficult and steep terrain when heavy rain caused major landslips.

  3.  With regard to the four projects apparently lacking completion dates, we can report that all of these projects were completed as shown below:

Turks & Caicos IslandsEstimated Actual
Completion Date Completion Date
Government OfficesNot known- December 1992
Renovationearly records
destroyed
Classroom ConstructionDecember 1994 October 1994
Mechanical WorkshopNot known- January 1991
Reconstitutionearly records
destroyed


Anguilla
Primary SchoolMarch 1995 March 1995
Rehabilitation


Department for International Development

January 1998


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 21 May 1998