Select Committee on Public Accounts Forty-Sixth Report


THE CONTRACT TO DEVELOP AND UPDATE THE REPLACEMENT NATIONAL INSURANCE RECORDING SYSTEM

COMPENSATION

58. The contract with Andersen Consulting allows the Agency to terminate it if Andersen Consulting default on any obligation under the contract and fail to remedy it within 30 days. In such circumstances Andersen Consulting may be required to provide for the provision of facilities and services equivalent to the services covered by the contract by the Agency itself or a third party. The limit on the amount Andersen Consulting might have to pay in such circumstances is £100 million during the development phase and £2 million for each event during the operational phase up to a maximum of £50 million in any 12 month period.[53]

59. The Committee asked the Agency why they considered £100 million compensation adequate when the cost of developing and operating the system in-house had been assessed at more than £300 million. The Agency told us that they did not believe they would have received any bids had the contract provided for unlimited compensation and that the figure of £100 million was more comparable with the expected cost of the contract with Andersen Consulting. The figure of £100 million had been arrived at during the contract negotiations and had been a major sticking point with all three bidders.[54]

60. Following the Agency's agreement with Andersen Consulting on a revised implementation timetable, Andersen Consulting agreed to pay up to £3.1 million in compensation to the Agency toward the estimated £3.8 million additional costs that the Agency expected to incur as a result of the delay.[55] No compensation was to be payable in respect of the estimated lost savings of £4 million and £2 million to the Contributions and Benefits Agencies respectively which the new system would have produced had it been operational on time.[56]

61. We therefore asked the Agency why they believed that compensation for themselves and the Benefits Agency to cover the lost benefit savings was not appropriate. The Agency told us that they had received legal advice that it was unlikely that they would be able to justify seeking compensation for these potential savings. This was because the evidence for them was unlikely to be strong enough to withstand challenge. The Agency told us that had the procurement taken the more orthodox route it is unlikely that any compensation would have been received.[57]

Conclusions

62. Where transfer to the contractor of the risk of failure to deliver is not possible, as in this case, we expect departments to seek to provide in contracts for financial compensation sufficient to pay for an alternative solution should the project fail. In this contract, the levels of compensation provided for would be quite inadequate in the event that Andersen Consulting fail to deliver the required service. We recognise, however, that risks can only be transferred at a cost, and that in any particular case the cost of transferring the risk may be more than the value to the public sector of doing so.

63. While recognising that under the contract the Agency have received £3.1 million compensation for the delayed implementation, we regard it as unsatisfactory that no compensation is payable in respect of a further £6 million representing savings which the Agency would have achieved if the project had not suffered delay.


53   C&AG's Report paragraph 3.16 Back

54   Q112 Back

55   C&AG's Report paragraph 3.26 Back

56   C&AG's Report paragraphs 3.25, 3.27 Back

57   Q52-53 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 1 July 1998