Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 1 - 19)

WEDNESDAY 21 JANUARY 1998

Mr J Mortimer, Treasury Officer of Accounts, further examined.

Chairman

  1.  Good afternoon, everybody. This afternoon we welcome Mr Richard Tilt, the Director General of the Prison Service, to the Committee to discuss the Comptroller and Auditor General's Report and the PFI contracts for the Bridgend and Fazakerley prisons. Welcome again, Mr Tilt. I trust you are at least as well fed today as you were the last time you were here!

   (Mr Tilt)  I hope so.

  2.  Could I ask you to start by introducing your colleagues to the Committee.

   (Mr Tilt)  On my left I have Julian Le Vay who is the Director of Finance at the Prison Service and on my right is Tim Wilson who is the Head of the Contracts and Competition group who has responsibility for negotiating these contracts.

  3.  Thank you. I will start straight in. Figure 10 on page 46 is the first thing I am talking to. It shows in aggregate the two prisons are likely to cost 10 per cent less under PFI than under the traditional procurement. Could you tell us how these savings arise?

   (Mr Tilt)  Well, in embarking on the bidding process we considered that it was necessary to construct a public sector comparator and the details of the public sector comparator are in the report. The contract price for the two places added together was £513 million. That compares with the price that is calculated on the public sector comparator of £567 million. That is how the 10 per cent arises.

  4.  Where were the savings?

   (Mr Tilt)  Oh, I see. Savings arising out of different staffing arrangements, savings arising out of different design arrangements, savings calculated on the basis of risks connected to the history of these sorts of projects which led usually to both cost and time overruns. And time overruns, of course, would cause us considerable problems, apart from the costs associated with them.

  5.  I see. Others may want to come back on that.

   (Mr Tilt)  Yes.

  6.  Figure 10 also shows that while you achieved a £53 million saving at Bridgend compared with traditional procurement, the corresponding saving for Fazakerley was only £1 million. Why were you unable to negotiate a better deal on the Fazakerley contract?

   (Mr Tilt)  I think the principal difference is to do with the designs submitted by the two potential suppliers. The design suggested by Securicor at Bridgend was considerably more innovative. It led to the possibility of lower staffing costs, it had a greater reliance on new technology and IT particularly and it allowed them to put in a lower bid. The construction at Fazakerley by Group 4 Tarmac is a much more conventional one, much closer to the designs which were being used in the public sector, and has some higher staffing costs.

  7.  Paragraph 2.14 says that you estimated the extra cost of not awarding both contracts to one bidder was at least £19 million and there is some suggestion it might even be more than that. Paragraph 2.15 shows that in fact this cost might have been higher but you did not ask any bidder to quantify savings that might have been available if they had been awarded both contracts. Why did you do that?

   (Mr Tilt)  We were clear from the beginning and throughout this process that we would be extraordinarily nervous about awarding both contracts to one supplier, I think on two grounds. One, we were worried that one contractor handling both contracts might increase the risk of delays and we could not afford delays because of the population pressures that we were under so we did not want to take any risks with that at all. In the case of Securicor they had no previous experience of running a prison and we would have been nervous about allowing them to take on two contracts with no previous experience. The same did not apply to Group 4 who had got previous experience. Beyond that we were also keen, given that we were into a programme of DCMF prisons (PFI prisons) to ensure that we were beginning to create a market so that we could subsequently ensure there were enough people bidding to keep the process competitive. That is proving to be the case and is confirmed very much by the Private Finance Panel Report.

  8.  Remind me, Mr Tilt, what was the timing of this contract being let?

   (Mr Tilt)  It was finally signed at the end of 1995 but the process had been going on from 1994.

  9.  At a time when the building industry was suffering a fair amount of competitive pressure.

   (Mr Tilt)  I cannot comment on that.

  10.  Again I am quite sure that others will want to come back on that issue, perhaps in some detail. Paragraph 18 of the Executive Summary, to change the subject briefly, says that you spent £1.6 million on advisers which was more than double your initial estimate of £0.6 million. How did you satisfy yourself that the higher than expected costs of advisers represented value for money? I would like you particularly to address the question of why you let the contract to Lazards without any competition at all?

   (Mr Tilt)  I think it was extraordinarily difficult to estimate what the costs were going to be. This was completely new business for us, as indeed it was for the bidders. The assessment that was made did not take account of all the difficulties that we encountered, indeed as the report makes clear we had to re- tender because the first exercise had to be aborted because we could not persuade the potential bidders that they should accept some of the risks that we were suggesting. We ended up with a very much longer process than we had expected. It is not surprising that the fees were therefore higher. I should say, we have learned I think from the experience in that. In the competition for Lowdham Grange, which has been completed now, we stayed within our budget which was set at a very much lower level than the figure here. That is because by then we were beginning to understand precisely all the ramifications of the contract process. In terms of not having a competition for Lazards, I entirely accept that in retrospect that was wrong, we should have done that. Since then we have always had competitions for advisers and will continue to do so. We did embark, of course, on the contract with Lazards on the basis of the fee rates that arose from an earlier competitive contract but nonetheless I accept that we are open to criticism.

  11.  Again others may want to pursue that. I will come to my last question before I open the questioning up to the Committee. You mentioned the Lowdham Grange contract, paragraph 3.11 says that the Prison Service subsequently let a third PFI contract which was 21 per cent less than Bridgend and 36 per cent less than Fazakerley. What lessons did you learn from the Bridgend and Fazakerley projects that will inform future PFI contracts to achieve these savings in future?

   (Mr Tilt)  Part of the saving comes from the fact that Lowdham Grange is in our terms a simpler contract, a simpler business. It is a single function establishment, Category B training prison. The other two, Altcourse and Park, were both multi-functional local prisons taking in both young offenders and potentially women as well as Category A prisoners. So there would inevitably be a price reduction. It is a much simpler affair. Some of the buildings that we required at Parc and Altcourse are not required at Lowdham Grange but there is no doubt that as one gets experience of the process then we get better at negotiating good contracts. The market is competitive and we have taken some benefit, I think, out of the establishment of the market that came from this first competition.

  12.  Have you done a value engineering analysis for that reason for the 36 per cent difference?

   (Mr Wilson)  We have an understanding in terms of the different construction of the prison. Fazakerley is much closer to the kind of prison that the Prison Service itself would have been building: a large number of separate buildings with considerable additional construction risks and within a much larger area. Now from Bridgend through to Lowdham Grange we have gone for fewer buildings, simpler structures, smaller, tighter perimeters. The first competition gave us a template. Indeed, when briefing contractors at the conclusion of that competition we made it very clear that we were looking for further pressures through competition to reduce the unit costs of the prisons that we were procuring later but maintaining the same level of service.

  Chairman:  I recommend you do look at a value engineering analysis. Let us open the questioning up. Miss Maria Eagle.

Maria Eagle

  13.  Mr Tilt, nice to see you again, although I still cannot quite see you properly. I wonder if you accept my interpretation of the report in respect of Fazakerley Prison in particular that you appear to have accepted a loss to the public purse of up to £65 million-there is a question about how much but up to £65 million-on the basis that you wish to rig up a market in prison construction that did not previously exist. Do you think that is a fair interpretation?

   (Mr Tilt)  No, I do not. I do not wish to rig up any market. I did wish to construct a competitive market.

  14.  Construct a competitive market.

   (Mr Tilt)  But on the figures that you suggest, I do not recognise those figures at all.

  15.  Mr Tilt, do you think it is your job, as an accounting officer of an agency, to pay for constructing a competitive market?

   (Mr Tilt)  No. I think at the time in the context of a policy of delivering new prison places through the PFI it was important to us that we had a good market, that we had a number of people who were prepared to engage in the bidding process.

  16.  You were prepared to expend public money.

   (Mr Tilt)  Can we come back to the question of the money. I do not recognise your figures.

  17.  They are in the National Audit Office report.

   (Mr Tilt)  I do not think they are, I do not see the figure £65 million in the report anywhere. What the report suggests is that if you take the £19 million, which is the difference that we acknowledge exists between the contract prices, if you add to that the five per cent discount that Securicor afterwards, post hoc, said that they might have been prepared to offer, you get to a figure of £44 million. So that is the maximum figure that I am aware of or that I am aware of anywhere in the report.

  18.  You accept it could be up to £44 million?

   (Mr Tilt)  I accept it could be up to £44 million but on the five per cent discount, it is perhaps worth noting that did not appear in the competition.

  19.  You did not ask them?

   (Mr Tilt)  In the subsequent competition --


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 8 April 1998