Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 20 - 39)

WEDNESDAY 21 JANUARY 1998

Mr J Mortimer, Treasury Officer of Accounts, further examined.

  20.  You did not ask them if there were any potential discounts from economies of scale?

   (Mr Tilt)  --in the subsequent competition for Agecroft and Pucklechurch Securicor offered a two per cent discount on an uncompetitive bid[1]. In fact the best discount --

  21.  Can I tell you where my figures come from.

   (Mr Tilt)  Can I just finish the point I was making.

  22.  Quickly please, if you would.

   (Mr Tilt)  The best discount that we were offered on a competitive bid was rather below one per cent.

  23.  If you turn to page 46 of the Report, figure 10, the Chairman has already referred to it, savings at Bridgend of 17 per cent, virtually no savings at Fazakerley. If you achieved similar savings at Fazakerley, that would have been £41 million of additional savings plus up to five per cent discount on economies of scale that Securicor and Costain said to the National Audit Office they could have offered, although you dispute that. We did not ask them but you dispute that. That would have been a further £24 million making £65 million in all.

   (Mr Tilt)  I think it is £25 million not £24 million. I do not dispute that part of it but I do not understand your £41 million. The figure identified in the report is £31 million.

  24.  What is not in dispute though, and you accept you said to the National Audit Office, you thought you may have foregone savings of £19 million?

   (Mr Tilt)  Yes.

  25.  So you accept that?

   (Mr Tilt)  Yes, I do.

  26.  Now I would like to examine your reasons for allowing such losses to go ahead. You have said you want to develop this market in custodial services and on page 28 of the report you make what I find quite an extraordinary statement and that is you say that this strategic decision not to award the two contracts to the same contractor would not have been affected by higher cost savings. Now you accept that cost savings could have been £19 million, you have also mentioned a figure of up to £44 million, I say there is a figure of perhaps up to £65 million. You are an accounting officer, at what point, how many millions of pounds would it have taken before you thought perhaps that ought to affect your strategic decision?

   (Mr Tilt)  I repeat that as far as I am concerned the figure in the report reflects up to £44 million and I do not recognise the other figure. I did in answer to the Chairman at the beginning make two points, not just the future strategic market point but I made first, and in a way probably I think of greater priority, the question of risk attaching to awarding both contracts to one supplier. We took that very seriously indeed and would have been extraordinarily nervous about doing that.

  27.  I am glad you have raised the question of your reasoning because the National Audit Office Report states quite clearly that it was well thought through and indeed it is set out on page 26, paragraph 2.13, there are four concerns. You mentioned two of them but let us just go through them. One is risks placed "... too great a demand on Securicor..." because they were inexperienced, you have mentioned that one. The second one was in relation to the design that they were suggesting. I always thought that PFI was about telling the contractors what services you wanted and leaving the design and their way of delivering to them. I do not see why that would have been such a major concern to you.

   (Mr Tilt)  If I can comment on that?

  28.  We will come back on that. I want to refer to all of them. The third one was that you thought one of the contractors concerned may be experiencing financial difficulties.

   (Mr Tilt)  Yes.

  29.  And therefore you were nervous about giving them two contracts. Would that not be enough to make you nervous about giving them any contracts? It seems to me that out of the four reasons we have had-the fourth one is you wanted to develop a market in custodial services-the only one that is really convincing is the fourth and I wonder whether that is a proper reason for you to have raised given that there has been a significant loss to the public purse as a result?

   (Mr Tilt)  I do not accept that there has been a significant loss to the public purse.

  30.  £19 million is not a significant loss?

   (Mr Tilt)  I am not saying that because I do not think one can regard that as a loss to the public purse necessarily.

  31.  Savings foregone.

   (Mr Tilt)  It is a net present value over 25 years. It is of course based on an assessment that everything would have been delivered precisely on time if they had both been delivered to one contractor. If that had not been the case and we had very substantial worries, we talked about the Costain problem, we had very substantial worries about that.

  32.  That could have been dealt with by financial penalties in the contract.

   (Mr Tilt)  I assume you want to hear the answer which is that if we had suffered a 12 month delay the police cells cost to us of that would have been £65 million[2].

  33.  I can understand that.

   (Mr Tilt)  I have to balance the risk of a single supplier not delivering both on time against those sorts of penalty costs that I would have to pay for police cells.

  34.  It appears from the report you took the view at a very early stage of prison service, it was not you personally, that these contracts would not be let to two different bidders.

   (Mr Tilt)  No, we took the view that they should be let.

  35.  Not to the same bidder?

   (Mr Tilt)  Yes.

  36.  That was in March 1994, you intimated to the bidders. That condition was not in the tendering document, was it?

   (Mr Tilt)  It was not in the second round of tendering documents and that was an omission which we fully acknowledge[3].

  37.  The National Audit Office asked the bidders and they were of the opinion that they could have been awarded both from the tendering documentation. This was a covert view.

   (Mr Tilt)  No, it was not covert. If it had been covert presumably we would not have told them in the first place but we did omit telling them in the context of the second.

  38.  Certainly Securicor and Costain bid for both, did they not?

   (Mr Tilt)  Yes, they did.

  39.  Would they have done that if they had been aware of the fact they could not have been awarded both?

   (Mr Tilt)  No I think you are quite right to say that the bidders believed that there was a possibility of them being awarded both but, as I say, our position was that that would have been a very, very high risk strategy for us and one we were not prepared to take. I note in the report, in fact, that Securicor acknowledge themselves that they understand perfectly well why we did not award both contracts to one bidder.


1   Note by witness: In this context an uncompetitive bid was one more than 4% greater than the lowest bid. Back

2   Note by witness: £65 million would be the cost of holding 600 prisoners in police cells for a year at a cost of £300 per day. These costs are principally comprised of police overtime, and equipment and supplies. Back

3   Note by witness: The Prison Service wrote to bidders in March 1994 to explain that the two contracts would be awarded to two different bidders. Erroneously, this was not included in either of the invitations to tender. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 8 April 1998