Select Committee on Public Accounts Thirty-Ninth Report


PLANNING AND BUDGETING

(a)  Estimates of Eligible Land

21. The Ministry have experienced difficulty in establishing how much land is eligible for the Scheme within each designated area. Errors arose from a variety of causes such as the difficulties of distinguishing between different types of land.[27] The Ministry did not have a complete and accurate record of eligible land before the Scheme was launched in each area. For example the eligible area for arable and ley grassland in Dartmoor had been calculated as 2,000 hectares, whereas take-up amounted to 3,000 hectares.[28] We put it to the Ministry that accurate information on eligible land areas is important for establishing take-up targets, for financial forecasting and for monitoring the Scheme's effectiveness.[29]

22. The Ministry assured the Committee that these shortcomings did not mean they were paying farmers who did not qualify.[30] The initial estimates of the land which would qualify had been based on the best available maps at the time. However these did not distinguish between types of land within the area.[31] The Ministry said that, if they were to map qualifying areas very precisely before each phase of the Scheme was launched, the cost would be enormous and would not be the best way of using their resources.[32]

23. The Committee asked whether using local knowledge and aerial photography could improve accuracy. The Ministry told us that they did use these methods. However aerial photography cannot distinguish between different types of grasses, for example.[33] Their new computerised mapping system will improve the quality of information once it has been collected; but will not address the problem with accuracy of original data. The Ministry said that targets set as a proportion of other figures which were estimates should be avoided if possible.[34]

(b)  Financial Forecasts

24. The Ministry have repeatedly over-estimated the net cost of the Environmentally Sensitive Areas Scheme. For example, in 1995-96 the grants to farmers, net of recoveries from the European Union, amounted to £16 million compared with an estimate of £37 million.[35] We therefore challenged the Ministry on their budgeting record. The Ministry told us that the significant underspend was due to three factors: an over estimate of the level of take-up; the delayed launch of Stages III and IV of the Scheme because of budget pressures elsewhere in the Ministry; and a very cautious approach in deciding when an increase in European Union funding from 25 per cent to 50 per cent would take place.[36]

25. Agri-environment schemes became eligible for the highest level of reimbursement from the European Union on 30 July 1992. However, the regulations required that the existing stages of the Scheme be submitted for approval by the European Committee before claims for reimbursement at the new rate could be approved. The Ministry did not believe that the increased rate of reimbursement would be backdated; but it was, thus reducing their net expenditure. Because of problems within the European Union agriculture budget at the end of 1993, there had been a risk that reimbursement would be reduced to 25 per cent in 1994-95 onwards. The Ministry therefore continued to budget for receipts at less than 50 per cent up to 1996-97.[37]

26. The Ministry assured us that estimated expenditure would match outturn more accurately in the future. However, they said they could never be precise in this sort of scheme, particularly as there had been a dramatic change in the profitability of farming over the past year or so. That might affect take up but the Ministry could not be sure about this.[38]

27. The Committee asked the Ministry what rate of European Union reimbursement other agri-environment schemes attracted and whether the Ministry took the differences into account when deciding which scheme to use to achieve a particular environmental objective. The Ministry could not provide the information on differing rates but agreed that they ought to take these on board in the way suggested by the Committee.[39] The Ministry have told us that, in general, all agri-environmental schemes adopted are eligible for 50 per cent European Union funding.[40]

28. The Committee asked the Treasury what impact such underspending had on the public expenditure survey process and whether over budgeting worked to a department's advantage. The Treasury said that the impact would not be great in this case, given the total size of the Ministry's budget. However, the Treasury would not ignore consistent underspending or indeed some of the other elements mentioned in the Comptroller and Auditor General's Report, such as the ratio of administrative expenditure to grants paid.[41]

(c)  Conclusions

29. We are surprised that the Ministry did not have accurate records of the eligible land before launching the Scheme. As a result, the take-up in relation to eligible grassland in Dartmoor amounted to 50 per cent more hectares than the Ministry had thought would be eligible.

30. We note the Ministry's reservations about the cost-effectiveness of compiling a complete and accurate record of eligible land from the start of the Environmentally Sensitive Areas Scheme; and their assurances that accurate payments to farmers have been soundly based. However, we consider that the Ministry's planning for this Scheme was inadequate. Financial and management control would have been enhanced if payments had been set against a well-founded estimate of the area of land eligible for support by the taxpayer. We look to the Ministry's computerised mapping system to play an effective part in this process.

31. It is unsatisfactory that the Ministry have consistently overestimated the net cost of the Environmentally Sensitive Areas Scheme. And in 1995-96 alone the amount paid out to farmers was £16 million compared with the Supply Estimate put to Parliament of £37 million.

32. The Committee do not expect departments to need to be reminded of the importance of accurate planning and forecasting when presenting Estimates to Parliament, for the purposes of controlling public expenditure, and for monitoring the achievement of their objectives. In doing so they need to take a realistic view on the degree to which European Union financial support will be forthcoming. It is clear to us that the Ministry have been unduly cautious on this issue.


27   C&AG's report (HC 120 of Session 1997-98), para 2.9 Back

28   Q 27 Back

29   Q 76 Back

30   Qs 27, 35 Back

31   Qs 52, 67 Back

32   Qs 27, 75, 99 Back

33   Qs 69-70 Back

34   Qs 67, 71, 76 Back

35   C&AG's report (HC 120 of Session 1997-98), para 4.14, Figure 25 Back

36   Q16 Back

37   Evidence, Appendix 1, p20, paras 29-32 Back

38  Q 20 Back

39  Qs 25-26 Back

40  Evidence, Appendix 1, p19, paras 19-20 Back

41  Qs 145-147 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 3 June 1998