Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 1 - 19)

MONDAY 23 FEBRUARY 1998

MR LAWRIE HAYNES and MR JON SEDDON

Chairman

  1.  This afternoon we welcome Mr Lawrie Haynes to the Committee to discuss the C&AG Report on the First Four Design, Build, Finance and Operate Roads Contracts. Welcome, Mr Haynes. Can I ask you to introduce your colleague to the members of the Committee?
  (Mr Haynes)  My colleague is Mr Jon Seddon, who is the Finance Director of the Highways Agency.

  2.  Thank you very much. Let's get straight into questions. I am going to start with paragraph 1.13 of the report which shows that two of the highest ranked consortia for the two largest projects were not invited to bid for those projects. Might better deals have been obtained if they had been invited to bid for those projects?
  (Mr Haynes)  I think the process we went through in order to establish the companies which could bid was a fairly comprehensive process. We went through a position where we would try and get the quality of each one of the pre-qualification companies high enough so we could choose any of those companies and they would still be of a quality sufficient to put a potentially winning proposal in. At the first stage, the pre- qualification stage, we were not looking to pick winners.

  3.  But you did exclude two potential winners. Others may come back to that, I will move on for the moment. Paragraphs 1.14 and 1.15 and following show that the scope for innovation by the bidders was constrained by the complex core requirements against which they were required to bid. Bidders, as reported in paragraph 1.27(f), say that the Agency appeared to show little enthusiasm, for innovation other than in respect of financing. Why could you not have done more to encourage innovation?
  (Mr Haynes)  In the first instance we were constrained to some degree because the schemes we brought forward, or ministers decided to bring forward, had already gone through the public inquiry process, had gone through orders, and decisions had been made by the Secretary of State. By definition we had made undertakings at the public inquiries and at other meetings and that would, of course, constrain us in the core requirements which we could put to the DBFO bidders.

  4.  Was it the case that you did actually vary some of the requirements after the bidding process had started?
  (Mr Haynes)  We did indeed. We varied some of the requirements subsequently when there has been an obviously demonstrable case for us changing those requirements. Since the contracts had been awarded, we have had about 3,400 claims for variations of standards, for example, and we have elected to pursue about 3,000 of those, or allowed the DBFO companies to pursue about 3,000 of those. In terms of innovation, we have had 372 requests for variations to bring in innovations and we have allowed 94 per cent of those.

  5.  So you do accept it is possible to allow variations post the statutory process?
  (Mr Haynes)  Yes, but in each one of those cases we have kept to the Secretary of State's statutory obligations which we had to keep to in order to sign the orders in the first place.

  6.  Again, others may want to come in on that at some point. Paragraphs 1.11 and 1.28 to 1.33 and Figure 2 show that the procurement process took a long time and cost both the public and private sector players considerable sums of money. Why was this and what steps did the Agency take to improve on these points for current and future projects?
  (Mr Haynes)  Yes, the process was a long one. These were pathfinder schemes, they were experimental schemes, and we had gone through a great deal of consultation with the industry and the city before we commenced them. Their complexity, given that they were 30 year contracts, necessitated us to have extremely clear financial models. We elected to create a model contract with terms and conditions before we went into the competition fully and that did indeed extend the time it took us to complete the deals. I think the time taken was extremely long. We have learnt some lessons from that. We now have our model contract which we are using or will be using for subsequent contracts, we have the direct agreement which is now with the banks, and is now going to be used as a normal document, and indeed we have passed those documents at no cost to local authorities and other authorities who wish to use the DBFO approach. So hopefully for industry we will be reducing the cost and time required for future transactions.

  7.  From memory your adviser costs were pretty high as well, were they not?
  (Mr Haynes)  Yes, they were £8.3 million for the first eight DBFO contracts.

  8.  Why so high for that?
  (Mr Haynes)  There are basically three elements in there. Firstly it was a development of the policy. Ministers had asked advisers to give some advice on the policy generation of whether the schemes were viable or not. Secondly, they were giving us project advice on the first four, which is within the NAO report, and thirdly they gave us project advice on the second tranche, tranche 1A. So those costs were all encompassed in those three elements of the price.

  9.  Paragraph 1.16 states that bidders were required to bid on the basis of shadow tolls. Paragraph 2.9 explains that the private sector is not in a position to manage traffic volume which underpins the use of shadow tolls. Why was this approach chosen? Could bidders have been offered the opportunity to bid on a different basis?
  (Mr Haynes)  This approach was chosen primarily because ministers wished to follow a policy line of getting the industry used to the potential of real tolls. In fact the Chancellor in 1992 had suggested a real motorway tolling system was being considered. It was subsequently followed by the Secretary of State, and the DBFO-design, build, finance and operate-was an opportunity to test the market on that. Linking that policy approach to shadow tolls was a direct connection. It would get the industry familiar with the role of being a network operator, a road operator, and maintain that. So that was one of the primary reasons for using shadow tolls.

  10.  Do you accept that imposed greater risks on the private sector than would otherwise be the case without particularly reducing your risks?
  (Mr Haynes)  I think there were new risks involved here, yes.

  11.  Paragraph 2.21 states that the discount rate you used overstated the net benefits of these projects. Why did you appraise these privately financed projects using a discount rate which the Treasury recommended for publicly financed roads?
  (Mr Haynes)  We used the 8 per cent discount rate on the guidance and instruction of HM Treasury. I believe they gave us that advice because we would be comparing roads with rail at that time, in other words two infrastructure industries would be comparable on a similar basis.

  12.  I will let others provide a flood of questions for you and the Treasury on that subject. Paragraph 2.16 to 2.19 and Figure 14 show that had the correct discount rate of 6 per cent been used, the A69 project was significantly more expensive using private finance, and the A419/417 was marginally more expensive. Would you agree that in the light of these figures these deals do not represent value for money?
  (Mr Haynes)  Well, there are some non-quantifiable benefits which come from these deals as well as the value for money element which is generated by the 8 per cent or 6 per cent, the minus 5 or minus 12 million. Ministers were clearly involved in this and were very much aware of the fact these potentially would not be value for money on an arithmetic basis. We took the view that on a wider basis, in other words generating a road operating industry, it was a reasonable approach to go ahead with these. On the A69, one of the things we wished to do, within assessing the overall industry which would be generated with tranche 1, was to look at the A69 as a maintenance-led contract, in other words a small capital element but a very large maintenance element, and it would give us an opportunity to benchmark that contract in the long-term future.

  13.  That is an interesting answer on qualitative matters, but can you give me a yes or no answer on this, that according to these figures the A69 would have been cheaper to build under public control?
  (Mr Haynes)  Yes.

  14.  Thank you. How far does the experience with these first four contracts confirm the Agency's assessment of the benefits of the private finance approach to road projects?
  (Mr Haynes)  I think we have been very pleased with the way the contracts have gone to date. The A419/417 was delivered early, the A69 was delivered early, so the economic benefits of those projects have come forward earlier than we could have expected. The risks we would have expected under the conventionally procured systems have not come forward. We would normally, as this Committee reviewed some years ago, expect a cost over-run on the contracts. I actually visited the A1(M) about three weeks ago to talk to the chief executive of RMG and he informed me that if we had procured under the normal, traditional contract at this point he would have been putting in a claim for £40 million for unforeseen ground conditions, and indeed would also have been negotiating an extension of time on that contract of one year. So those non- quantifiable benefits have already come forward to date. We have also seen a change in the attitude amongst the companies involved and they are very clearly looking on a whole life costing basis to put long-term maintenance regimes in place and higher standard capital in place. I think that will be beneficial over the life of the contract.

  15.  Paragraphs 3.1 to 3.17 set out the monitoring and legal arrangements in place to ensure service requirements are delivered. Are they working in practice?
  (Mr Haynes)  Yes, they are. We have teams, both at the departmental agent and the departmental representative levels who are working extremely well with the contractors. The systems for monitoring the shadow tolls due to be paid and the auditing systems are working very well. So things are working reasonably well at the moment.

Mr Hope

  16.  Can I begin by raising the fact that the whole of the bidding process and so on relies on the payment of these shadow tolls, as set out on page 15. On page 63, the annex describes the three scenarios-high growth, medium growth and low growth traffic volumes-and then on page 30, paragraph 2.10 says, "If traffic volumes vary significantly ...[this could lead in an extreme case] to financial collapse or .... unexpectedly high profits ...", and that this could alter significantly up or down with all the implications that has. Do we have any actual estimates of what those unexpectedly high profits or unforeseen high costs might be for each scheme rather than theoretical or hypothetical models?
  (Mr Haynes)  Within the document it gives a range of expectation of where we expect the shadow tolls to be paid, a low and high range, and the expected NPV is on the median. One of the things we have done in the banding is to put Band 4 at a zero toll rate, thereby limiting the liability of the Secretary of State to that high peak of growth on traffic.

  17.  So that if we get the maximum growth on, say, the A1-M1 link road or the Alconbury-Peterborough upgrading, there will be a strict limit on the profits which might be gained by the companies and on any cost to the Agency if the reverse were true?
  (Mr Haynes)  Exactly.

  18.  Do we know what these figures are in specific terms over a period?
  (Mr Haynes)  Sorry?

  19.  The cost of the unexpectedly high profit we might see?
  (Mr Haynes)  We do not expect there to be exceedingly high profits because we have capped our liability and therefore the DBFO companies' revenues at a given figure. If the traffic grows beyond Band 4, in other words where the zero toll is payable, in fact the profits for those DBFO companies will come down because they will still be having to maintain the roads although there is a greater traffic flow.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 18 June 1998