Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 60 - 79)

MONDAY 23 FEBRUARY 1998

MR LAWRIE HAYNES and MR JON SEDDON

  60.  It says in paragraph 2.18 over the page that: "Rationing of total public spending on roads is decided mainly on criteria other than the net present values", which I understand in that there are lots of environmental and other issues related to roads projects and I hope to come back to this question, but is the methodology we are using with net present values robust enough to take decisions relating to whether we should use the PFI route or alternative routes?
  (Mr Haynes)  I think it is a reasonable basis to test the market, yes.

  61.  In paragraph 11 right at the beginning you talk about the comparison with "traditionally procured and conventionally financed projects". Could you just describe to me what are "traditionally procured and conventionally financed projects"?
  (Mr Haynes)  The traditional procurement method is to have the design paid for and contracted with one company, the construction paid for and completed by a second company, the operation and maintenance contracted with a third or more companies and the operation and maintenance contracts are negotiated on a three- or five-year basis.

  62.  Because I wanted to ask you the question that comes out at the end of that sentence whether you made a public comparator with design and build contracts and whether you think it would be appropriate in the circumstances to use that as a comparator?
  (Mr Haynes)  We did actually look at the design and build elements. The transaction teams that made up part of the evaluation team had experience in design and build as well as in the ICE 5th terms of contract, so we did have that basis for comparison in the experience and expertise and professionalism of the transaction team.

  63.  You have not put any of that into the Report. What did that show? Did that show that design and build would be significantly better or worse in terms of being an alternative public comparator?
  (Mr Haynes)  The A1(M) scheme was actually going to be procured under the design and build concept anyway so we had a direct comparison there. The other schemes were going to be contracted under the ICE 5th terms and conditions and therefore we would not have done a direct comparison on design and build.

  64.  Can you tell us what that showed for the A1(M)? What I am really trying to get at is was that closer to the private sector alternative, the PFI alternative, should I say?
  (Mr Haynes)  It is on page 34 in figure 14. The A1(M) shows that using design and build as the basis we generated at eight per cent a £50 million benefit and at six per cent a £30 million benefit to the taxpayer.

  65.  I am sorry, I thought that the figures in figure 14 were for the PFI route as compared with the traditionally procured and conventionally financed.
  (Mr Haynes)  The conventional procurement was £96 million but I think we have to be careful that we compare apples with apples because within here there is also a risk transfer. I made a mistake, it is £167 million, not £96 million.

  66.  The issue I am trying to get at if you look at figure 11 on page 27 my understanding is, forgive me for not being someone who is involved in the construction industry, that the design and build contract would allow you to transfer the risk on numbers 1 and 3 (that is design and construction and delivery and time) to go to the private sector over and above what would be conventional procurement and in those circumstances what I wanted to ask you was how much of the value of risk transfer was associated with those parts of the risk transfer?
  (Mr Haynes)  I do not have that precise information for design and construction or delivery/timing with me.

  67.  Would it be correct that the risk would be transferred in the design and build contract?
  (Mr Haynes)  Yes.

  68.  Do they make up the majority of the risks transferred? Is the majority of those values for risk transfer related to those parts rather than the other risks that you outline in figure 11?
  (Mr Haynes)  Again, I do not have the detail of those two with me.

  69.  Do you think we could have some figures in relation to what the alternatives would be in the design and build contract? [2]
  (Mr Haynes)  Yes, I am sure we can provide them.

  70.  Can I move you on to figure 3.20 which is on pages 42-43. It says: "On the tranche 1 schemes contract costs allow for shadow tolls to be rebased to compensate the operator for the effect of any reduction in traffic." Can you tell me in what circumstances that would come into force?
  (Mr Haynes)  In the event that real tolls were brought on to the DBFO road we would take the shadow toll model from the contractor which was generated at the beginning of the contract and that would be used as the basis for determining if there had been a shift of traffic from that road and the contract then would be rebased so as to ensure the contractor in this case is protected in the event of any change in legislation.

  Mr Love:  Right. Thank you very much, Chairman.

Mr Leslie

  71.  When I am confronted with a barrage of statistics and explanations and numbers and amounts of money, particularly in the way that I read through this Report today, I must admit I start to smell a rat a little bit because I think for anybody trying to read through this document and look at the public sector comparison that you make between the cost of building these road schemes under private finance versus the costs under normal procurement standards to the taxpayer, it is bewildering because by the information I have got at least I have found it very difficult to make that comparison. What I want to know is what is the cost to the taxpayer almost in cash terms if you had built those roads during that 30-year period normally versus how much you are having to pay to these DBFO contractors over that same period and I cannot seem to get it because you skew the public sector comparison in two different ways, first of all, this business about risk transfer and, secondly, this business about the real annual discount rate. Do you not agree that this is a very important thing you should be trying to get and looking at the costs to the taxpayer in cash terms? How can you help clarify this matter for me today?
  (Mr Haynes)  I have tried to explain that they are complex deals. It is important in this to understand that it is not simply a capital cost involved here; there is the capital cost of building the new road, there is the operation and maintenance cost over a 30-year period. It is not considered under the normal simple capital cost of any road construction. There is the risk transfer that was priced by the Highways Agency, it was then audited by a risk consultant and then tested against the market with the bids that were brought in. Bringing in the capital costs with the O&M costs and the risk costs gets us to the public sector comparator.

  72.  I appreciate, of course, that the operation and maintenance costs have to be bundled in and that is why I said that the total cost to the taxpayer over 30 years versus how much cash you are paying out through these shadow tolls to these private developers, and I really have to question some of these risk assumptions you put in here because that takes a lot of those comparisons. If you look, for instance, at the M1-A1 and you are saying that the risk is £106 million, I do not believe it, I find it very difficult. You say there have been delays, but paragraph 2.11 talks about how you skew some of the traffic projection risks in favour of the developer in terms of the M1-A1 and does not this explain a large part of the value of this risk transfer in this case? It is overblown, is it not?
  (Mr Haynes)  No, as I tried to point out to the Chairman at the beginning, the A1(m) was the contract that when I spoke to the Chief Executive of RMG[3] he pointed out a risk that neither he nor I had taken into consideration of £40 million which would have been claimed against the Agency and against the Secretary of State and against the taxpayer if we had gone through traditional procurement.

  73.  That leaves the other £66 million which is the skewing in favour. Compared to the other four schemes you have got here paragraph 2.11 says that in the M1-A1 project involving the sorts of things it does you changed what you call the "sculpting factor" of the shadow toll scheme in their favour.
  (Mr Haynes)  The sculpting factor--

  74.  Just to get the point, the M1-A1 scheme is treated differently in terms of risk analysis from the other schemes.
  (Mr Haynes)  No, they are all treated exactly the same and in each one of these the transaction teams developed a risk model. It was independently verified or checked by a risk consultant and in all cases there was a very close similarity between the Highways Agency's assessment of risk and the consultants' assessment of risk.

  75.  All this risk is very difficult to quantify in cash terms, is it not? I do not see how you can project the specific figures over 30 years and say that this is the risk we have managed to hand over to the private sector. It is a guessing game, is it not?
  (Mr Haynes)  It is a matter of judgement because the transaction teams we had assessing these were both the designers of the original road, they were my staff and their advisers, who had been worked on these roads on an operational and maintenance basis for so many years, are professionally qualified people.

  76.  They are still guessing at it.
  (Mr Haynes)  They are making a judgement.

  77.  Right. Let's go to this other factor that seems to skew the comparator. How much cash are you going to be spending normally and how much are you going to be paying to the DBFO contractors, this business about the real annual discount rate. I have been trying to pin this down. On page 46 there is a glossary of terms. Discount rate: "The percentage rate applied to cash flows to enable comparisons to be made between payments at different times. The rate quantifies the extent to which a sum of money is worth more to the Government today than the same amount in a year's time." I think that concept is awfully confusing and difficult to understand, at least for my simple brain. That, again, is a bit of a guessing game, is it not? It is a stab in the dark of a figure?
  (Mr Haynes)  Again, it is the advice that we have had from Treasury as to the right rate to use.

  78.  You cannot have absolute certainty about that, can you?
  (Mr Haynes)  I have absolute certainty on the rate.

  79.  Maybe I should ask the Treasury that question.
  (Mr Mortimer)  I agree, these things are very much a matter of judgement. On the basic question of whether you need to apply discounts rates I think the answer is clear. If someone offered me £100 now or £100 in five years' time I would say, "I will have the money now please". I could invest cash received now, do all sorts of things with it and the money is safer. Discounts rates are a way of taking into account the extra value of having the money up front. The standard approach within economic theory when you look at costs and benefits extending over a number of years is you apply discount rates. Having said all that, I quite agree the appropriate discount rate to use is a matter of judgement.


2   Note: See Evidence, Appendix 1, page 16 (PAC 232). Back

3   Note by Witness: RMG refers to A1(m). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 18 June 1998