THE
QUALITY
OF
THE
BUILDING
i) Design Development
13. Design work on the Southampton Oceanography Centre
did not begin until March 1990, only two months before the target
date for approval of the outline. There was thus little time for
preliminary design work on alternative schemes. In May 1990 the
design team presented to the Project Board a design proposal based
on a single concept[15]
which the Project Board approved. Users were invited to comment
on matters of detail but were not invited to query the concept.[16]
14. In evidence, the Committee asked why alternative
designs were not sought. The Council said that, if the project
were being done to-day, they would look at alternatives.[17]
They thought that their architects should have presented them
with alternatives.[18]
The design process had involved considerable iteration and discussion
with the people who were going to work in the Centre.16
15. The major influence on the design was the need
for flexibility in services to cope with changes in science. Consequently,
the design team provided for separate intermediate floors exclusively
for the distribution of mechanical and electrical services. These
floors provide a high degree of flexibility because they can accommodate
the rearrangement of existing services. However they increased
the cost of the building by up to £1.5 million.[19]
ii) Cuts in Specification
16. Throughout the briefing and design stages there
was pressure to keep within the target budget. This led to a series
of cuts and reductions in order to reduce building costs,[20]
such as the deletion from the project of a plankton tower, shoreside
facilities and a biology store.[21]
In making the cuts, the Management Committee were hampered because
the relative priorities of the project's objectives had not been
previously assigned.[22]
17. The Council considered that, if the project had
started with a specified sum of money and the users had been developing
a brief against it, the Council would have avoided a fire fighting
mode in deciding what to cut to keep within the budget.[23]
We asked the Treasury witness whether he saw any merit in building
up a gold-plated design only to cut it back later in order to
bring it back to the budget. They told us that, as experience
had shown that there was often a tendency to over-specify, the
process of challenging the users either by the project manager
or by the project sponsor was good practice.[24]
18. We asked the Council whether, with hindsight,
they believed that they had got the best balance of functions
within the Centre. They were confident that, in terms of the core
objectives of providing scientific facilities for research and
teaching, the Centre had very largely reached its original objective.
As to something that could have been done better, it would have
been desirable to have a larger lecture theatre.[25]
19. When asked about the criteria they had used in
reducing the specification in order to pare back costs, the Council
told the Committee that the priority was to enable scientists
to carry out their scientific research effectively. For example
the science involved in the study of the plankton was being carried
out in another way;[26]
and it was not the case that there was no capability for taking
photographs or for developing an underwater vehicle.[27]
The Council had been absolutely rigorous in determining that the
scientific capability of the Centre would not be damaged by the
cuts.[28] The core scientific
objectives had been achieved.[29]
iii) Facilities Provided
20. The Centre provides a research and teaching facility
which is unique within the UK.[30]
The Council told us that it is a world-class Centre.[31]
Its staff undertake physical, biological, chemical and geological
research on the oceans and seas and on their boundaries with the
air above and the rocks and sediments below. They also design,
develop and operate the specialised equipment needed to examine
ocean depths. The scope of the Centre's work extends from coastal
waters to the deep ocean floors. The building contains teaching
space, laboratories, workshops stores and offices for scientists,
engineers and administrators; and berthing for research vessels.[32]
However, because the brief set out few of the project's objectives
in full, it was difficult to assess how far they had been achieved.[33]
21. In March 1997 the Director of the Centre reported
that the new building was working very well. In particular the
common areas such as the library, lecture theatre and meeting
rooms were functioning very successfully and providing the necessary
opportunities for interactions among staff.[34]
The Council told us the staff considered the Centre to be an extremely
good working environment.[35]
The Council were confident that the building had the flexibility
and durability to serve whatever purpose was required over the
next 120 years.[36]
iv) Conclusions
22. We find it disturbing that design work on the
Centre started only two months before the target date for approval
of the outline. As a result the design period was needlessly compressed
and only one single concept emerged. We are concerned that no
other options were considered and that the architects did not
present the Council with possible alternatives. In any major project
involving large sums of public funds, several options should be
considered and the prospective users consulted. Had this been
done, an alternative method of distributing the services might
have been found which would have provided flexibility for the
future without any increase to the cost of the building.
23. It is clear from the evidence we took that the
Southampton Oceanography Centre provides many facilities of considerable
value to the scientific and teaching work that is undertaken there.
It is encouraging to learn that it provides a good working environment;
and that the Council are confident that it has the flexibility
and durability to last for a further 120 years. It is difficult
to assess how far the project's initial objectives have been met
because so few of them were set out in full at the outset.
24. We note the Council's evidence that they had
been rigorous in determining that the Centre's scientific capability
was not damaged by the cuts; and that it had very largely reached
its core science objectives. It is of course often necessary to
adjust the specification of a project in order that its costs
may be kept within budget. However, it is important for any cuts
to be made by reference to a set of carefully considered priorities
that have regard to the main purposes of the project. We are concerned
that this was not the case in the building of the Centre, and
that the reductions in the specification may have resulted in
the exclusion of some facilities that it would have been better
to retain.
15 C&AG's Report, paragraph 2.22 Back
16
C&AG's Report, paragraph 2.23 Back
17
Q5 Back
18 Q33 Back
19 C&AG's
Report, paragraph 2.18, 2.24 Back
20 C&AG's
Report, paragraph 2.25 Back
21 C&AG's
Report, Figure 5 Back
22 C&AG's
Report, paragraph 2.26 Back
23 Q28 Back
24 Q152 Back
25 Q147 Back
26 Q148 Back
27 Q107 Back
28 Q148 Back
29 Q107 Back
30 C&AG's
Report, paragraph 1.1 Back
31 Q108 Back
32 C&AG's
Report, paragraph 1.1 Back
33 C&AG's
Report, paragraph 2.36 Back
34 C&AG's
Report, paragraph 2.38 Back
35 Q66 Back
36 Q67 Back
|