Select Committee on Public Accounts Minutes of Evidence


Examination of witnesses (Questions 1 - 19)

WEDNESDAY 4 MARCH 1998

PROFESSOR JOHN KREBS, MR COLIN READ and MR JOHN HANSFORD

Chairman

  1.  This afternoon we welcome Professor John Krebs, chief executive and accounting officer of the Natural Environment Research Council. We are considering the Comptroller & Auditor General's Report on the construction of the Southampton Oceanography Centre. Good afternoon, Professor Krebs, perhaps I could start by asking you to introduce your colleagues to the members of the Committee?
  (Professor Krebs)  Thank you, Chairman. On my left is Mr Colin Read, who is the Finance Director of NERC. On my right is Mr John Hansford, who is Director of Personnel and Estates.

  2.  Thank you very much. I understand this is your first visit to this Committee, so we work pretty closely to the C&AG's document. I will start with a question which arises from Figure 5 in the document. Despite your cost cutting initiatives, the cost of the Southampton Oceanography Centre increased. Why did this happen?
  (Professor Krebs)  Chairman, the Figure to which you refer on page 17 shows the process from the very beginning of the development of the brief. At the very start the brief was developed by consulting the users and that led to an ambitious aspiration and an initial estimate, which is shown in the top left hand corner of January 1990. Following that, there was a period of progressive cutting-back on the aspiration of the users which ended up with an agreed tender shown in the bottom left in November 1992 of £29 million. So the reduction really was from a wish list to a feasible and realistic project which was agreed as the final specification for construction. In terms of working from that agreed tender, the overall project including the construction of £29 million had a value of £48.9 million, the overall project, and as of today the project has reached a sum of £49.6 million, so an over-run of £0.7 million or 1.4 per cent.

  3.  Others will no doubt come back to that. Let's move on to paragraph 3.4 which tells us that construction of the building started 15 months later than planned. Why was there such a long delay in the start of the construction?
  (Professor Krebs)  There were really three factors which contributed to that, Chairman. First of all there was uncertainty about the financial situation. As you will be aware from having read the Report, there was a coming together of funds from NERC, which came through the Science Vote, and from Southampton University, coming through the Funding Council, and it took a while to put that together. That was part of the contribution. There was also work on developing the specification to which we have already alluded to some extent in talking about Figure 5, and that took a while. Then there was also a period associated with that of making the specification fit with the budget, so there was a period of cutting-back which again we have described in Figure 5. So there was a concatenation of those three events which led to the long delay. So refining specification, uncertainty about the allocation of money to NERC, to Southampton University, and reducing the budget from the initial wish list of the users down to a realistic sum.

  4.  I see from paragraph 4.22 your consultants' fees doubled from £4.3 million to £8.6 million. I suspect we will re-visit part of that answer, but why did you let this happen?
  (Professor Krebs)  This is certainly not something which would happen today, and this came about in large part through the extension of the period of development of the brief, and then also in addition partly through the extension of the construction period. It is possible my colleague, Mr Read, may wish to add something to that.
  (Mr Read)  I think, Chairman, the accounting officer has summed that up quite well, to the extent the increase in the fees is largely due to the fact the design period was extended by 15 months and matters about which we have already spoken.

  5.  Going back to paragraph 2.22, it says that the design team presented the project board with proposals based on a single concept. Why did you not ask for alternatives? Might that not have simplified the process?
  (Professor Krebs)  I think if one were doing it today, one would look at alternatives. However, the process of developing the design which the design team presented to the project board had involved considerable iteration and discussion with the users, the people who were going to work in the centre, so although it arrived as a single concept it had been derived through an iterative process.

  6.  That rather brings me to what I think is a rather important question. Paragraph 5.5 says that the Council's normal practice was to take a collective approach to project management. Why did you not follow the Treasury recommended practice and appoint a professional project manager to deliver the project on time and within project?
  (Professor Krebs)  Clearly today, if we were initiating (and I can give you some examples of projects we are involved with at the moment) we would appoint an independent project manager. At the time, looking back into the late 1980s, the accepted best practice was evolving quite rapidly and it could be argued that NERC should have looked ahead to the way best practice was developing rather than looking back to what had been best practice earlier on in Government guidance.

  7.  Before we pass on from that, can I ask the Treasury a question? Your guidance was extant in the late 1980s, at the beginning of this project, was it?
  (Mr Martin)  If we were to be absolutely accurate, I could not point to a piece of Treasury guidance in the late 1980s which was specifically about the appointment of project managers. That partly reflects the fact that in the 1980s the bulk of projects within Government were done by the Property Services Agency, and their internal guidance and indeed their practice would be for the appointment of project managers. In the late 1980s, the Treasury's concern was rather more about the role of the project sponsor. The problems we had identified in managing projects were that the client, so to speak, was not getting his act together in dealing with the project manager which, as I say, typically would come from the Property Services Agency in that period. I think, though, it would be true to say, as reflected in the way the Property Services Agency worked, best practice would be for the appointment of a project manager.

  8.  Certainly that was evident to anybody in the commercial centre at this time.
  (Mr Martin)  Indeed.

  9.  What I think the Committee would find useful is a note on what, if any, advice was available up until January 1990, the start of the project——
  (Mr Martin)  Specifically on project managers, Chairman?

  10.  Yes, on project management advice.[1]
  (Mr Martin)  Certainly.
  (Professor Krebs)  Chairman, may I add one more point? The Council at that time, in the late 1980s, had undertaken other projects in using the collective approach which had been highly successful, so there was a history of successful management of projects in this way which also may have influenced the Council's decision.

  11.  You say that but according to my note here no less than eight reviews advised the Council against your collective management approach.
  (Professor Krebs)  I agree. That was starting from 1991.

  12.  I see. Let's go on. Paragraph 5.12 says that because there was no clear allocation of responsibilities between your consultants there were problems with the management of the contract. Why did you let this happen?
  (Professor Krebs)  Again, this is an area where our current guidelines would take a slightly different approach. In fact, we would appoint an independent project manager with clear responsibilities for project management. I think that the historical development of this led to the view in NERC that the principal responsibility for management project lay with the consultant team. Perhaps Mr Hansford would like to add to that.

  13.  Would you like to, Mr Hansford?
  (Mr Hansford)  Yes, I can confirm that. I think what we would accept is that there were weaknesses in the way that the allocation of responsibilities was set out at that time. That is well recognised but I think we have learned that lesson very clearly now and our procedures, which I hope we will have a chance to talk about a little later on about how they have evolved, have fully taken on board the need for clear and concise allocation of responsibilities.

  14.  Others will return to a number of these questions as we carry on. My last question before I open it up for the Committee, I see from paragraph 4.2 of the Report that you have not settled the final account with Wimpey. When do you expect to resolve this expensive dispute?
  (Professor Krebs)  Chairman, the current situation is that the building is complete. As I said a few minutes ago, there is an overspend of £0.7 million. It may look slightly different in figure 10 where it seems to show a slightly bigger figure. Do not forget that in interpreting Figure 10 Footnote 4, we deducted £2 million in liquidated damages which we still hold so the current figure is 49.6 not 51.6. As far as we are concerned in NERC our position is that that is the final cost of the project. At the moment there is a dispute between Wimpey and their subcontractor Matthew Hall over the costs of the M&E part of the building and we watch with interest the development of that dispute between Matthew Hall and Wimpey. As far as we are concerned the final figure has now been determined and there is no further action that we are taking ourselves other than I have employed a legal team of advisors who have prepared a very careful brief should there at a future date be some approach by Wimpey. That is not in our hands.

Chairman:  Again, others may come back on that. Let us open the questioning up. Maria Eagle?

Maria Eagle

  15.  Good afternoon, Professor Krebs. I wonder whether or not you could just clarify some points that have arisen in my mind out of the Chairman's opening questions and your answers. You said on a number of occasions "if we were doing it now we would doing it differently". What has changed between when you were doing this and now that has made you introduce some of your answers with those remarks?
  (Professor Krebs)  What has changed is that NERC has as a result of this project and other projects learned a number of things about management of large capital projects. We have issued new guidelines which in fact match very well with many of the recommendations in the NAO Report. We commissioned our own post-project evaluation of the Southampton Oceanography Centre project which again provided us with some additional lessons. The reason we are doing things differently now is because of acquiring experience.

  16.  There is nothing like getting your fingers burned to learn to stay a bit further away from the fire. You have learned some expensive lessons, have you not? According to the NAO Report the overrun on this project could run to £20 million. You have spent £5 million under other budget heads. You could be facing additional costs if Wimpey do send that writ of another £15 million. That is a set of expensive lessons, is it not?
  (Professor Krebs)  I think we should stick to the actual facts.

  17.  Do you dispute what the NAO have said in their Report in respect of these figures?
  (Professor Krebs)  No, I absolutely agree with Figure 10 which shows that the current overspend is £0.7 million and our position is and remains that any further overspend has no credibility.

  18.  Do you accept that you have spent £5 million under other budget heads which is related to this project?
  (Professor Krebs)  That was not part of the original bill. You are referring to Figure 11. The staff relocation costs were always treated as a separate item.

  19.  Would the staff have been relocated if you had not built this centre?
  (Professor Krebs)  That was always considered to be a separate budgeting item.


1   Note by Witness: A number of guidances on works projects were issued by the Treasury's then Central Unit on Purchasing prior to 1990, including guidances on project sponsorship and the selection and appointment of works consultants. These provided guidance on project management but not on the project manager's detailed, day-to-day management responsibilities. This approach reflected the fact that the primary concern, following studies of works projects in the mid-1980's, was to improve departments' performance from the project "owner" or "sponsor" perspective. To illustrate this approach, a section of CUP guidance No 8 (Project Sponsorship: Role of Project Sponsor and Relationship with the PSA", November 1988) included among the project sponsor's responsibilities to "commission those professional services required to implement the project. Particularly for the management of the detailed design, procurement and construction phases of the project, obtain the services of a suitable project manager (and staff as necessary). In conjunction with the project manager ensure that these various groups are welded into a team motivated to meeting the success criteria of the project". Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 16 June 1998