Select Committee on Public Accounts Minutes of Evidence


Examination of witnesses (Questions 80 - 99)

WEDNESDAY 4 MARCH 1998

PROFESSOR JOHN KREBS, MR COLIN READ and MR JOHN HANSFORD

  80.  Well, we know it should not have happened and you said that in your answer to a colleague earlier when we were talking about the over-run. It is a 39 per cent over-run, if my crude arithmetic is about right, on architects' fees alone, so they are getting a 39 per cent uplift on the agreement there, they are busting the rules in every direction, they are spending the taxpayers' money, you do not even know about it, you have no system of reporting to tell you it is going on, how could it have arisen? I do not think it is enough to tell me it should not have happened, we all know it should not have happened, how did it come to pass?
  (Professor Krebs)  I can certainly say it would not happen now, that is not the system——

  81.  I can understand that. Professor, you and your colleagues are giving a very good impression of three honest men squirming with embarrassment at what is, by the standards of this Committee, a fairly average cock-up but nonetheless a very embarrassing situation. Let us try some specific questions. Paragraph 4.8. Why was no allowance made for risk in the project?
  (Professor Krebs)  There was a contingency set in the final contract for the projects. The contingency was a small one, it was considered at the time to be sufficient given the degree of design development which had gone on before the contract was let.

  82.  But when the budget was set the allowance was not there in anything like sufficient provision. Let me ask you to move on to 4.14. Why was there no provision for design development as the project goes on? What we have seen here is a sorry tale of something getting totally out of hand, the architects authorising changes at every turn, your Council not having a clue what was going on, occasional meetings when there was no doubt panic and consternation and a decision to cut the spec, hence no large auditorium and all those other things we saw in that first table to which I alluded when I started speaking.
  (Professor Krebs)  If I may clarify, the cuts to the specification were before the contract was let. When the contract was let, a very considerable amount of design development had been undertaken and the construction company, Wimpey, in looking at the specification accepted that as a brief for the build.

  83.  Why do you suppose, if I may move you on to 4.16, there was such a large gap between the estimates for the mechanical and electrical services and the lowest tender? Why was there such an unrealistic position adopted? I suspect, Professor, that nobody from the start had any sort of grip on what a project of this size really entails. But if you can tell me otherwise I am happy to be corrected. Before the Chairman stops me I am going to move on to another area but can you answer that?
  (Professor Krebs)  I am not sure exactly what your question is. Is your question whether more detailed design development should have been done on the M&E?

  84.  It is as I stated, why was there such a large gap between the lowest tender and the estimate in that budget for the M&E services? How could there have been such a large variation between what anyone was prepared to estimate in their tender and what you actually put in your budget? In other words, did your budget bear any resemblance to the real world?
  (Professor Krebs)  Might I just ask my colleague?

  85.  Of course.
  (Professor Krebs)  The method of calculation of the budget was a standard procedure but it has a high variance.

  86.  You will be relieved to know I am coming to the end of my questions. I want to ask two more and one will be an uncomfortable one. So far as the surveyors are concerned and the one of the three architects firms that was chosen, is there anybody on the Council who has now or did have at any stage any kind of commercial relationship with people from either of those firms?
  (Professor Krebs)  I think the answer is no.

  87.  Chairman, may I ask that that be checked?
  (Professor Krebs)  I am happy to follow that up in writing.[2]

  88.  My final question turns to paragraphs 5.11 onwards. The NAO Report tells us there was no project plan, no defined responsibilities, no project handbook. In 5.34 we are told that the Council has learned lessons and you have suggested that yourself in your evidence. Can you answer me this, Professor, why should the Council ever be placed in charge of such a project again to squander taxpayers' money in this fashion?
  (Professor Krebs)  I think if the Council is undertaking similar projects or smaller projects that involve capital investment it should have guidelines and procedures in place that are robust and will not lead to this situation. Under those conditions they should be given responsibility for that kind of work.

Mr Leslie

  89.  I am interested in looking at the scale of your cost overrun. You have mentioned before that you had a small contingency set aside initially at the beginning of the whole project. How small was that contingency? Two per cent, is that right?
  (Mr Hansford)  It was a contingency on the constructions contract and was two per cent of the value of that contract.

  90.  Why did you choose two per cent?
  (Mr Hansford)  That was the figure advised to us by our professional consultant advisors.

  91.  Do you regard two per cent as a large sum or a fairly limited amount?
  (Mr Hansford)  I am struggling to find the reference but the Report comments on this that it was recognised as a tight but nevertheless achievable contingency. I cannot find that particular comment but I know it is in there somewhere.

  92.  It was not particularly achievable, was it? What does two per cent imply to you? If you set a contingency of two per cent if you overrun in any significant way what happens to the project?
  (Mr Hansford)  Well, if one exceeds that contingency one overspends.

  93.  Or you cut-back what you spend.
  (Mr Hansford)  There was a process in the history of the project of cuts being made at times when there was evidence that the project was in danger of overspending.

  94.  You could either overspend or cut-back and pare the project down to size but you did not, you chose to overspend.
  (Mr Hansford)  I think the history of the project shows that when it became clear that costs were likely to exceed budget action was taken to reduce the spec. That is clearly set out in one of the figures that we have been looking at. So I believe action was taken at the appropriate time to try and control the project within the budget.

  95.  Most of the reasons why a lot of these extra costs have come on have already been alluded to. In terms of consultant fees they doubled from £4.3 to £8.6 million and there was a variety of reasons for that. They were not initially appointed in line with best practice, they did not have a fixed relationship with the total overall cost of construction and there were all these late design changes that came into place. The design changes that you had in the process of this construction project were not necessarily always to pare down the scheme to bring it back into a manageable budget. They were just design changes that came along as you developed the brief, were they not?
  (Professor Krebs)  I think a substantial part of the delay in the pre-construction phase was to refine the design, to minimise the risk. That is the point. It was not changes to the design as much as refining the design.

  96.  Forgive me if I do not get the terms correct because I have not actually seen this magnificent centre, although I am sure it is very good but it is full of all sorts of pipes and service channels throughout the building. In fact, you manage to somehow channel 12 different gases to all your laboratories around the building. Why do you need 12 gases? I am curious. You are pumping these gases all around the building. I can imagine you need oxygen and nitrogen and a few others, my chemistry is very basic, but that is a very generous, luxurious building, is it not?
  (Professor Krebs)  It relates to the kind of science that is done in the building. We could get into a very technical discussion about chemical oceanography and geochemistry.

  97.  I do not want to do that obviously! But it was a very generous, ambitious project and the services, of course, that you needed to put in place should have really struck you at the beginning of the design phase and yet in terms of putting in these chemical and electrical services and so on you did not really incorporate them into the whole design until very late in the day.
  (Professor Krebs)  I am not sure where the impression comes from that the mechanical and electrical services were only incorporated late on.

  98.  When did you appoint Building Design Partnership, the services engineers who were the ones who put in the services? You appointed them very late in the day, did you not? I think paragraph 2.12 makes reference to that.
  (Professor Krebs)  Well, BDP were appointed in March 1990 which was a considerable time ahead of letting the contract for the construction.

  99.  But in terms of the outline design stage it was fairly late in the day, was it not?
  (Professor Krebs)  It was after the users had developed their specification requirements, then it went to the experts to see how that could be implemented.


2   Note by Witness: As far as can be ascertained no Members of Council have, or had, a commercial relationship with the Consultants employed on the SOC project. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 16 June 1998