Select Committee on Public Accounts Minutes of Evidence


Examination of witnesses (Questions 140 - 154)

WEDNESDAY 4 MARCH 1998

PROFESSOR JOHN KREBS, MR COLIN READ and MR JOHN HANSFORD

  140.  I did not mean pecuniary, I just meant there is a sort of comfort in knowing people whom you have worked with. That is not a professional approach but it is understandable in small business activity. This asset is supposed to last something like 125 years. Can I ask why there was no attempt to do a lifetime evaluation of this asset? It says in paragraph 2.27 words to that effect. Secondly, while you are thinking about that, if it is supposed to last 125 years how long is the warranty? One year? What guarantees have we, given we have spent all this money on this project, that some of the 12 gases referred to by Mr Leslie will not start escaping, mixing up and blowing up, or whatever they do?
  (Professor Krebs)  The answer to the second part of the question is that the design warranty is for 12 years.

  141.  So 10 per cent of the projected lifetime.
  (Professor Krebs)  Yes. The question about a life cycle analysis—I accept that the Council did not commission a life cycle analysis although we did commission reports on key elements to do with energy provision and the use of construction materials. Of course in our used guidelines it is standard practice to commission a full life cycle analysis.

  142.  So you have got a 12-year guarantee on everything.
  (Professor Krebs)  On design.

  143.  On bits and pieces. That is no more than you would expect if you had got your roof repaired? That is a rhetorical question. I notice that you have got these consultant and various people involved in making decisions but they do not seem to have proper responsibilities for time delays and cost overruns and you have got leading members of the Council who make these decisions who do not have effective management, they face no sanctions and no liabilities in a situation where an organisation continues to make decisions against a backdrop of lost taxpayers' money. Do not you think there is a problem here that there are no checks and balances and accountability in the way this is meandering forward and what do you suggest should happen in the future about that?
  (Professor Krebs)  I think with regard to a project of this sort in the future, and indeed at present, the NERC would appoint an independent project manager with responsibility for delivering the project on time and on budget. With regard to the responsibilities of the Executive and of the Council, of course ultimately the accounting officer, in this case myself, carries the responsibility for the Council's budget.

  144.  Finally just a small question. I notice the contractors were paid in advance of their work. Why was that? Is it not normal to do some work and monitor it, quality check, and move on? In terms of controls I think one of my colleagues mentioned that there were something like only 260 controls on 1,900 instructions.
  (Professor Krebs)  Yes, the question about the payment profile was one that we did touch on earlier. Perhaps I can ask Mr Read to just rehearse that point.
  (Mr Read)  Yes, we negotiated a payment profile with Wimpey at the outset before we placed the contract. That was perfectly normal procedure and we followed reasonably closely, although not exactly, the recommended profile in the standard contract document we were using. The basis of this contract was that you agree a payment profile and you agree a programme of work and as long as milestones are reached at particular points in the programme that triggers the payment. As it happens if you actually valued the work on site during early stages of the contract the payments were running a little ahead of that value. Later in the project they were running correspondingly higher than that value.[6] That was not intentional, that was how it happened and we would perhaps be a little more rigorous in agreeing a payment profile in a future contract.

Mr Love

  145.  Good afternoon, Professor Krebs. I will not prolong your anguish much longer. I have only got a couple of very brief questions. I think by way of the introduction I should reaffirm what has been said around this table this afternoon which is the seriousness with which we judge the way this project has been handled and I am sure that you will take that message away with you this afternoon. My first question is in relation to the £5 million or so which you spent which was not actually charged to the project. I think it appears in Figure 11 on Page 29. Can I just ask you why you felt it was not necessary to include that when it is quite clearly related to the project and in projects that have been completed or are in process at the moment is this a common feature of the way you handle projects of this nature?
  (Professor Krebs)  Chairman, if I may just clarify. I think there may be a slight lack of clarity in what I said earlier. It is not that we did not include the £4 million staff relocation costs in part of the original project, it is just that the budget described in Figure 10 does not include in the column that ends with £48.9 this £5 million figure. If you want to include it in there then it would come into the outturn. So you either include it with the original estimate and in the outturn or you treat it as a separate item. It was simply referring to the cross-reference between 11 and 10. Clearly when the Council made the decision to build the Southampton Oceanography Centre they knew they would have to invest in staff relocation costs and that was built into the cost calculation. It was merely a technical point about the relationship between Figure 11 and Figure 10.

  146.  I take your point that perhaps it is a technical point and it is not important but is it not a little indicative of the way that this whole project was managed? Is it not slightly, if I can use the colloquial phrase, sloppy not to include what was clearly a project cost within the overall budget and work to the full budget rather than have two separate budgets and make it appear as if there was a lesser cost? There is no need to comment on that. Can we be reassured that in your normal way of handling a project of this nature now that you will include all the costs related to the project within your overall budget?
  (Professor Krebs)  You can be reassured.

  147.  Can I turn to Figure 5 for my second question. I was intrigued by the comment made by the Treasury but I wanted to ask you first of all in relation to Figure 5, do you believe, looking back with hindsight, that you have got the best balance of functions within the Oceanography Centre that you could have got for the money you expended?
  (Professor Krebs)  I would need to think have hard about what alternative balance of functions one might wish to achieve. What I can say with confidence is in terms of the core objectives of providing scientific facilities for research and teaching, the centre very largely reached its original objective. If you want a specific case where I think something could have been done better, it would have been desirable to have a larger lecture theatre. It is a very large centre and it does not have a very large lecture theatre. There is a case for saying that the functionality of the building would have been better with a larger lecture theatre. But the core scientific, teaching and research objectives were uppermost in working through Figure 5.

  148.  It struck me in exactly the same way as it struck my other colleagues the way it is presented in Figure 5, and you can correct me if I am wrong, that the only criteria you operated to as you moved from stage C down to the agreed tender was simply reducing it as a matter of cost saving. What I would like to hear from you is some criteria used that still allowed you, as costs had to be pared back, to maintain the best balance of function within the building.
  (Professor Krebs)  I would reiterate that the priority was to enable the scientists to carry out their scientific research effectively and for the teaching of undergraduates and postgraduates to be carried out effectively. It is science led. Although it looks as though some of the items in Figure 5 relate to science, they indeed do like the plankton tower that was already referred to, the science that is involved in the study of the plankton is being carried out in another way. We were absolutely rigorous in determining that the scientific capability of the centre would not be damaged by the cuts.

  149.  It says somewhere within the Report, I cannot find the immediate paragraph, that you did not set priorities and criteria for the functions within the building explicitly. Is that something you do now with projects that you are undertaking?
  (Professor Krebs)  Yes, it is part of our new guidelines.

  150.  Can I then move on and I will ask you the question first and perhaps I will ask it of the Treasury. Is the mechanism by which you went through this from stage C, in other words building up, if you like, the gold-plated Oceanographic Centre and then pinning it down to your budget, is that a system you still use? Would you do that on a current project?
  (Professor Krebs)  No, I would not do that in a current project.

  151.  What of the good practice contained in here would you still include?
  (Professor Krebs)  I would follow our current guidelines in which I would appoint a project manager. In fact we have a project going on at the moment where I have implemented this, I have appointed a project manager, it is a fixed fee basis for consultants, I have a senior person in the organisation as project sponsor, we benchmark, we use competitive tender and I also collect performance indicators on a regular basis to measure our performance in managing and delivering projects that involve capital investment. Mr Hansford provides those to me on a regular basis.

  152.  Can I ask the Treasury: my understanding of what you said earlier was that you felt there was some merit in building up the gold-plated service in order that you could bring back to the standard of the budget. Perhaps you could explain that in more detail?
  (Mr Martin)  I am sorry, if I did not explain myself well. I was saying that I regarded in a purchasing process a component whereby somebody challenges the initial specifications as built up by the users as good practice, because past experience has shown there is often a tendency on the part of the users to over-specify and to gold-plate. So I am simply saying that as part of good practice in purchasing, that process of challenge between the users on the part of either the project manager or the project sponsor is good practice.

  153.  Can I ask you whether you have adopted that practice? Do you critically look at the user profiles which are given to you when you are drawing up the project?
  (Professor Krebs)  Yes, we do.

  154.  And that is part and parcel of your project?
  (Professor Krebs)  Yes.

Chairman:  Professor Krebs, I think everything has been covered in some detail by all the Committee members today, I therefore do not have any additional requests for you. You have a couple of notes to provide. The Committee would be grateful if you could provide those as rapidly as possible, consistent with our provisions. It simply remains for me to thank you for your evidence and indeed that of your two colleagues. Thank you very much.


6   Note by Witness: Later in the project they were, in fact, running correspondingly behind that value, not higher as stated. Back


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 16 June 1998