Select Committee on Public Accounts Fifty-Third Report


APPROPRIATION ACCOUNTS 1996-97 CLASS V, VOTE 7: PASSENGER RAIL SERVICES

INTRODUCTION AND SUMMARY OF CONCLUSIONS AND RECOMMENDATIONS

1. The Office of Passenger Rail Franchising (OPRAF) headed by the Franchising Director was initially responsible for letting the 25 franchises of the domestic passenger rail network as rapidly as reasonably practicable. With the franchise contracts now in place, OPRAF is responsible for their day-to-day administration, including making payments due to train operating companies and ensuring that they meet their contractual obligations in accordance with the franchise agreements. The Franchising Director's current objectives issued by the Secretary of State in November 1997 lay great emphasis on the interests of the passenger and securing an overall improvement in the quality of railway passenger and station services available to railway passengers.

2. On the basis of a report by the Comptroller and Auditor General,[1] the Committee took evidence from Mr John O'Brien, the Franchising Director, on the management of the franchise agreements with train operating companies.

3. The main general points to emerge from our examination pointed to the need for OPRAF to manage the franchise agreements more actively on behalf of the taxpayer, Parliament and the rail customer in three important respects:

  • First, the Committee was concerned at the Franchising Director's apparent reluctance to accept that he could suspend franchise payments to train operating companies, even in circumstances where they were not meeting their obligations for the delivery of a rail service. We expect him to clarify his position on this issue.

  • Secondly, it is unsatisfactory that much of the data on which OPRAF base their judgement of the train operating companies' performance comes from the companies themselves, and the rest is supplied by Railtrack. OPRAF therefore lack independent assurance on the level of performance achieved. To provide Parliament with greater assurance that the train operating companies are providing the services paid for from public funds, we strongly recommend that the Comptroller and Auditor General should be given powers of access to the data on the systems operated by the companies and by Railtrack.

  • Thirdly, we are concerned that OPRAF might be too easily satisfied. The Franchising Director told us that, against the benchmark of British Rail performance before privatisation, the performance of the network as a whole had improved. Within this overall picture, however, nine individual companies had shown a worse performance than before privatisation in the areas of service delivery covered by the incentive regime. We found this deterioration unsatisfactory, especially as performance under British Rail appeared to us to be relatively unchallenging as a benchmark for improvement in services. We expect the Franchising Director to take every opportunity to secure contractual commitments to enhanced customer service from the train operating companies, in particular when franchises come up for renewal in the future.

4. The Committee's more specific conclusions and recommendations which underpin the general views above are as follows:

On contract management

      (i)  We are concerned that the Franchising Director places too much emphasis on his contractual obligation to make franchise payments to train operating companies, as opposed to ensuring that they meet their obligations for the delivery of passenger rail services. The Franchising Director appeared to put little emphasis on ensuring specific performance of contractual obligations by the train operating companies (paragraph 10).

      (ii)  The Franchising Director seemed to have a limited view of the use of his discretion in the management of franchise contracts. OPRAF should develop a clearer statement of what they consider to be major as opposed to minor breaches of contract; and the transparency of the contract management process should be enhanced so that breaches of contract by train operating companies can be seen to be met with an appropriate response (paragraph 11).

      (iii)  We note the progress being made by OPRAF in improving their systems for monitoring the train movement data supplied by Railtrack. The design and operation of these systems should be kept under review so that OPRAF maintain an accurate and up to date awareness of the train operating companies' performance against their contractual obligations (paragraph 12).

On assurance for OPRAF

      (iv)  We consider that OPRAF rely unduly on indirect evidence of the accuracy of performance data supplied to them by train operators and Railtrack. More should be done to secure direct evidence that train operating companies are meeting their contractual obligations, including on a sample basis by refocusing the work of the compliance team (paragraph 21).

      (v)  OPRAF need to ensure that the current review of the TRUST system, which provides data on the number and punctuality of trains, gives independent assurance on the reliability of the full range of data relevant to the franchise payments, and not just on specific procedures within the new performance regime. OPRAF should consider repeating the review on a regular basis in the future (paragraph 22).

      (vi)  Efforts should have been made earlier to secure independent assurance about the operation of the GEMINI system, on which OPRAF rely for data on train capacity. The work plan agreed for the proposed independent risk assessment of this system should address the case for introducing substantive checks on data provided by franchise operators (paragraph 23).

      (vii)  Neither the TRUST nor GEMINI systems provide OPRAF with information on quality of passenger service. We consider that this is an area where OPRAF should look to improve the data available to them, and should consider whether more direct assurance could be obtained through the work of the compliance team. To the extent that they rely on customer satisfaction surveys conducted by the train operating companies, it is essential that OPRAF exercise rigorous scrutiny of the methods used for these surveys, and satisfy themselves as to the independence of the companies who conduct them. They should take full account of the results, and of feedback from the Train Users Consultative Council, in their management of franchise agreements (paragraph 24).

      (viii)  We note that the franchise agreements do not specify degrees of comfort or quality of passenger service. The Franchising Director should consider whether some of these aspects of performance, which are important to passengers, should in future be covered by contractual obligations in the franchise agreements (paragraph 25).

      (ix)  OPRAF have had no contact with the external auditors of Railtrack and the train operating companies, through whom they could have obtained representations on the quality of systems used by the train operators. OPRAF should examine the possibility of setting up such contacts as soon as possible, in order to establish what work the external auditors have done on these systems, and what reliance OPRAF can place upon it. The Comptroller and Auditor General's views should also be sought, as OPRAF's external auditor (paragraph 26).

On access for the Comptroller and Auditor General

      (x)  The Comptroller and Auditor General should be fully consulted on the basis for the new review of the TRUST system, and not just when the scope has already been agreed with third parties. OPRAF should also consult the Comptroller and Auditor General from the outset on their proposals for securing independent assurance on the GEMINI system. The Comptroller and Auditor General should also have direct access to the systems and data within Railtrack, British Rail Business Systems and the train operating companies (paragraph 30).

On train operating companies' performance

      (xi)  We were concerned to establish whether the train operating companies were currently meeting their investment obligations, especially those with the shorter franchises. OPRAF assured us that all of the companies committed to investment under their franchise agreements were meeting their obligations, and that none were not expecting to be able to meet their commitments because of the length of the current franchise agreements (paragraph 39).

      (xii)  We note that, as part of the deal for First Group to acquire the Great Western franchise, the Franchising Director has obtained a contractual commitment to provide 32 new vehicles, in addition to the extra 40 already promised. We expect him to monitor closely the delivery of this commitment to new investment in rolling stock (paragraph 40).

      (xiii)  In order to improve the transparency of the franchising arrangements, OPRAF should review the presentation of their accounts to make the notes as informative as possible about the performance of individual train operators, and its implications for the level of franchise and incentive payments made and penalties imposed (paragraph 41).

CONTRACT MANAGEMENT

5. We asked the Franchising Director what procedures he had put in place, now that all the franchise agreements were in operation, to ensure that train operating companies met their contractual obligations before franchise payments were made.[2] He told us that the amounts of money the train operators should receive for the services they provide were set down in the franchising agreements. These payments were a matter of contract, so it was easy to see that OPRAF were paying the right amount. He also said that to ensure train operators complied with their obligations under the franchise agreements, OPRAF's compliance teams visited each train operating company every six months; and OPRAF's franchise management teams were in almost daily contact with the companies, to make sure they delivered on their commitments. OPRAF ensured that payments to train operating companies, whether under contractual subsidy commitments or performance incentives, were based on information taken from OPRAF's systems, which were largely driven by Railtrack systems.

6. The Franchising Director also explained[3] that OPRAF reviewed monthly Passenger's Charter information on reliability and punctuality, which was independently verified by Sheffield University. Since a number of different parties were involved throughout the system, he did not think it necessary to check everything himself, and that it was reasonable for him to rely on other independent sources to enable him to form a view. He believed that OPRAF had done what was necessary to enable them to rely on the systems and for him to sign OPRAF's 1996-97 accounts.

7. OPRAF confirmed[4] that their in-house systems had been refined during 1996-97 and were now capable of finer analysis of the data supplied by Railtrack. OPRAF's experience was that their systems were identifying more queries to pursue with the train operating companies, and that the opportunity for errors to slip through OPRAF's systems was being narrowed all the time. The Franchising Director acknowledged, however, that none of this provided control over any errors that might arise in the source information within Railtrack, and that core systems supplying OPRAF with information needed to be subject to further review.

8. When asked about the rigour of OPRAF's response in the case of a breach of contract by train operating companies, the Franchising Director explained[5] that OPRAF monitored performance against expected levels on a monthly basis. By way of example, he explained how one train operating company had exceeded its cancellation limit of no more than 1.5 per cent within any four week period. This triggered the procedure whereby the train operator was "called-in" by OPRAF to provide an explanation. After three calls-in, OPRAF can regard the operator as being in breach of contract and can issue an enforcement order requiring the breach to be rectified within four weeks. Under powers conferred by the Railways Act OPRAF may impose a penalty if this is not achieved. In the case cited, OPRAF issued an enforcement order with an associated levy of £1 million. The train operator rectified the breach within the four week period. The Franchising Director additionally confirmed that in resolving this case he had been satisfied that a long term solution was in place and that the train operator had not subsequently exceeded the call-in level.

9. We asked about the distinction between minor and major breaches. We wanted to know whether or not an ordinary member of the public could see, in relation to the train company they use, a clear basis on which breaches were assessed as minor, significant or major; and that there had been appropriate penalties applied in each case. We asked how bad things would have to be before a franchise was cancelled. The Franchising Director emphasised that whether or not there was a breach was a matter of fact,[6] and he maintained a public register of all such breaches.[7] OPRAF regarded breaches very much in contractual terms which meant that there was little real discretion in the matter.[8] He said that there had only been one major breach[9] where he had issued an enforcement order. If there was repeated failure to comply with enforcement orders the franchise would be cancelled .[10] To illustrate the seriousness with which he treated less significant breaches, the Director gave the example of a train operator who had failed to meet a franchise commitment to integrate train and bus timetables.[11] In this case OPRAF had allowed a three month delay in the implementation of the timetable commitment in return for additional benefits totalling about £1 million being added to the operator's contractual commitments.

Conclusions

10. We are concerned that the Franchising Director places too much emphasis on his contractual obligation to make franchise payments to train operating companies, as opposed to ensuring that they meet their obligations for the delivery of passenger rail services. The Franchising Director appeared to put little emphasis on ensuring specific performance of contractual obligations by the train operating companies.

11. The Franchising Director seemed to have a limited view of the use of his discretion in the management of franchise contracts. OPRAF should develop a clearer statement of what they consider to be major as opposed to minor breaches of contract; and the transparency of the contract management process should be enhanced so that breaches of contract by train operating companies can be seen to be met with an appropriate response.

12. We note the progress being made by OPRAF in improving their systems for monitoring the train movement data supplied by Railtrack. The design and operation of these systems should be kept under review so that OPRAF maintain an accurate and up to date awareness of the train operating companies' performance against their contractual obligations.

ASSURANCE FOR OPRAF

13. In monitoring train operating companies' performance, OPRAF rely on information supplied to them by Railtrack and the train operators themselves. Information on train movements comes from the TRUST system operated by Railtrack, and information on train capacity comes from the GEMINI system owned by the train operating companies and operated by British Rail Business Systems. OPRAF had obtained some independent assurance about specific aspects of the operation of the TRUST system, but did not have independent assurance about the system as a whole. They had no independent assurance at all on the operation of the GEMINI system.[12]

14. We suggested that OPRAF had perhaps placed too much trust in the Railtrack system. The Franchising Director told us[13] that he did not believe it was sensible to use OPRAF's resources to try to replicate the data provided by Railtrack. Rather, he considered it made sense to rely on independent verification of that data sufficient to enable him to sign OPRAF's accounts each year, and this was what he wanted to put in place.

15. OPRAF explained that their approach to independent assurance had been to address first the areas of greatest potential risk.[14] This is what they had done in relation to Railtrack's TRUST system. They had put in place a multi-party audit based on a risk assessment by an independent firm of accountants, which identified the detection of potential fraud and inherent system weaknesses as the two main areas for review. OPRAF said[15] that since amounts paid to private sector operators under performance regimes would increase over time, a further overall review of the TRUST system was now planned. Additionally,[16] OPRAF had appointed another firm of independent accountants to carry out a risk assessment on the GEMINI system. The resulting work plan would inevitably involve visits to the train companies and independent checks designed to assure OPRAF that they could rely on the system. The Treasury said that for the future OPRAF needed to improve arrangements for independent assurance and they supported OPRAF's undertaking to do this .[17]

16. The Franchising Director explained that OPRAF took assurance from several other factors surrounding the operation of the TRUST and GEMINI systems, which they considered lent credibility to the information supplied to them. The TRUST system was integral to the day to day operation of Railtrack and, previously, British Rail, and had been working successfully for 25 to 30 years.[18] The system also provided the information that enabled the train operating companies and Railtrack to attribute faults and delays between themselves, where a gain for one would represent a cost to the other. There was therefore a clear commercial tension between parties, which limited the scope for any wrongdoing. Therefore the Franchising Director did not consider that individual franchise operators or Railtrack could obtain an unfair advantage and pull the wool over others' eyes without OPRAF knowing.[19] The Director also assumed that the auditors of Railtrack and the train operating companies would have examined the systems before giving an opinion on their accounts, although OPRAF had not contacted the auditors to verify their assumptions about what systems examination had been carried out .[20]

17. OPRAF have established a compliance team, who are responsible for checking with the franchise operators that they are meeting their contractual obligations. The initial visits carried out by this team were aimed at reminding franchise operators of their responsibilities and establishing what procedures had been introduced. The work of the team did not include checking that franchise operators had reliable data capturing systems, nor did they include sample checks on data .[21] We asked OPRAF whether an opportunity to gain more robust assurance on the train operators' activities had been missed .[22] The Franchising Director told us that, in the light of what he considered to be the wider background of independent assurance outlined above, he did not believe it was necessary to ask the compliance team to do further work.

18. On the information from the GEMINI system,[23] the Franchising Director told us that the system was important for train safety and maintenance, and provided OPRAF with information about the passenger capacity and length of trains provided by the train operating companies. However, he confirmed that neither TRUST nor GEMINI provided information on quality of service, for example whether there was a buffet on a train, or whether the heating and lighting were working properly.

19. The Franchising Director also told us[24] that neither comfort for passengers nor levels of service were covered in the franchise agreements. Instead, he let customers specify what was important to them, rather than telling them himself. OPRAF were aware of customer views because they required train operators to conduct customer satisfaction surveys every six months. Although these were carried out by the train operators, both the survey companies and the methodology they employed were approved in advance by OPRAF. The train operating companies were contractually bound to provide OPRAF with the results of the surveys carried out. OPRAF monitored how the train operators did against customer priorities as indicated by the surveys. If the operators fell below benchmarks that were set at or before privatisation, OPRAF would insist that they established an action plan to address the problem. OPRAF told us that so far there were two train operators where such action plans were in place.[25]

20. OPRAF also told us that they met with the Central Rail Users Consultative Committee (CRUCC) in a public meeting every three months. These arrangements provided the CRUCC with every opportunity to let OPRAF know of their concerns. In the period covered by the Comptroller and Auditor General's Report, punctuality and reliability had been improving and CRUCC had been, by and large, pleased with how things were going. More recently CRUCC were not happy with the deterioration in punctuality and the enforcement of some areas of the franchise agreements.[26]

Conclusions

21. We consider that OPRAF rely unduly on indirect evidence of the accuracy of performance data supplied to them by train operators and Railtrack. More should be done to secure direct evidence that train operating companies are meeting their contractual obligations, including on a sample basis by refocusing the work of the compliance team.

22. OPRAF need to ensure that the current review of the TRUST system, which provides data on the number and punctuality of trains, gives independent assurance on the reliability of the full range of data relevant to the franchise payments, and not just on specific procedures within the new performance regime. OPRAF should consider repeating the review on a regular basis in the future.

23. Efforts should have been made earlier to secure independent assurance about the operation of the GEMINI system, on which OPRAF rely for data on train capacity. The work plan agreed for the proposed independent risk assessment of this system should address the case for introducing substantive checks on data provided by franchise operators.

24. Neither the TRUST nor GEMINI systems provide OPRAF with information on quality of passenger service. We consider that this is an area where OPRAF should look to improve the data available to them, and should consider whether more direct assurance could be obtained through the work of the compliance team. To the extent that they rely on customer satisfaction surveys conducted by the train operating companies, it is essential that OPRAF exercise rigorous scrutiny of the methods used for these surveys, and satisfy themselves as to the independence of the companies who conduct them. They should take full account of the results, and of feedback from the Train Users Consultative Council, in their management of franchise agreements.

25. We note that the franchise agreements do not specify degrees of comfort or quality of passenger service. The Franchising Director should consider whether some of these aspects of performance, which are important to passengers, should in future be covered by contractual obligations in the franchise agreements.

26. OPRAF have had no contact with the external auditors of Railtrack and the train operating companies, through whom they could have obtained representations on the quality of systems used by the train operators. OPRAF should examine the possibility of setting up such contacts as soon as possible, in order to establish that work the external auditors have done on these systems, and what reliance OPRAF can place upon it. The Comptroller and Auditor General's views should also be sought, as OPRAF's external auditor.

ACCESS FOR THE COMPTROLLER AND AUDITOR GENERAL

27. We asked the Franchising Director when OPRAF would have an adequate level of independent assurance on performance information provided by the train operating companies and Railtrack, which the Comptroller and Auditor General could take into account in forming his opinion on OPRAF's accounts.[27] He told us that in his view the information available in respect of the 1996-97 accounts had been adequate, since the Comptroller and Auditor General had given the accounts a clean opinion. The provision of assurance in respect of the current year was in hand and OPRAF would ensure that the relevant work was completed before the Comptroller and Auditor General had to give his opinion on the 1997-98 accounts. The Franchising Director also told us[28] that he was not aware of any concern over the propriety of the £1.8 billion paid out in 1996-97, in particular the amounts of the franchise payments which were laid down in the franchise agreements. Regarding the £1.5 million paid out under the performance regime on the basis of data provided by the TRUST and GEMINI systems, he was committed to review these systems and therefore did not believe that there was a difference of opinion between OPRAF and the Comptroller and Auditor General on what was required.

28. The Comptroller and Auditor General told us[29] that his concern was not just with the technical correctness of OPRAF's accounts, but that the information necessary for the Franchising Director to carry out his duties was fundamentally under the control of the providers of the services. Therefore the Franchising Director was relying on information provided by those he regulated. The aim of his report was to draw the attention of Parliament to the fact that the Franchising Director's reliance on such a system represented a potential point of weakness in assurance about the propriety of the provision of public services; and that the Comptroller and Auditor General's lack of access to Railtrack and the train operating companies reinforced that weakness.

29. We asked how OPRAF proposed to address the Comptroller and Auditor General's concerns over assurance on the TRUST and GEMINI systems .[30] The Franchising Director told us that for the TRUST system, the terms of the new review were being agreed with all the interested parties; and that once this was done, OPRAF proposed to discuss the scope of the review with the Comptroller and Auditor General. OPRAF were equally content to discuss the work plan for the review of the GEMINI system.

Conclusion

30. The Comptroller and Auditor General should be fully consulted on the basis for the new review of the TRUST system, and not just when the scope has already been agreed with third parties. OPRAF should also consult the Comptroller and Auditor General from the outset on their proposals for securing independent assurance on the GEMINI system. The Comptroller and Auditor General should also have direct access to the systems and data within Railtrack, British Rail Business Systems and the train operating companies.

TRAIN OPERATING COMPANIES' PERFORMANCE

31. We asked the Franchising Director whether the overall level of service now being provided was better or worse than under British Rail before privatisation. He told us[31] that the privatised service was cheaper, more reliable and more punctual than before privatisation. In the last 12 months the number of passengers carried had gone up by 8 per cent across the network and the number of trains running had increased by approximately 5 per cent. In 1996-97 the cost of subsidy was £1.73 billion. This was expected to fall by £300 million in 1997-98 and reduce further the following year. As 1996-97 was a transitional year with British Rail running the service for part of the time it was difficult to make a clear comparison between the last year of British Rail and the first year of privatisation. The subsidy to British Rail in 1995-96 had been £1.7 billion, slightly less than the adjusted cost for the whole network in 1996-97, but there were several factors which meant that was not a comparison of like with like.

32. On the relative performance of individual train operators within the overall picture, it emerged that achieved performance was still consistent with the requirements of the franchise agreement.[32] Additionally, the Franchising Director confirmed[33] that in the areas of service covered by the incentive regime, nine train operators were currently performing worse than British Rail at the time of privatisation.

33. On incentive payments to train operating companies, the Franchising Director told us[34] that the benchmark for train operators' performance was the actual performance by British Rail at the time the franchises were set up. If the companies could improve performance they had the opportunity of earning more money. If performance declined money would be taken from them. In the last year OPRAF had paid out £13.3 million under performance regimes.[35] Although train operators' performance had got worse over recent months, it was still better overall than under British Rail; thus in the current year incentives were still being paid, but at a lower rate than in the previous year.[36]

34. On the extent to which the train operating companies met their investment obligations,[37] OPRAF told us that all the companies which had committed to investment under their franchise agreements were currently meeting their investment obligations. OPRAF confirmed that with some small exceptions, no companies were suggesting that they could not meet their investment commitments. One operator did not believe it could meet a £2 million commitment to staff training because to do so would take staff away from running the service. OPRAF expected this operator to propose alternative expenditure to produce passenger benefits. OPRAF confirmed that no train operators were suggesting that they would not be able to meet investment commitments because of the shorter length of their franchises.[38]

35. As regards the relationship between the profitability of train operating companies and the amounts of money received from OPRAF, the Franchising Director told us[39] that every company on the network would be massively in loss if it were not for the subsidy provided by the Government. He confirmed that the then Government had deliberately decided to let the franchises on the basis of full risk transfer, so there was no provision either for the Government to claw back profits, or for operators to be bailed out if things did not go according to their plans. This meant that train operators would retain any windfall profits made on the basis of public subsidy.

36. On the sale of Great Western Trains to First Group, the Franchising Director told us[40] that the original franchise awarded in December 1995 was a ten year contract conditional on the provision of significantly increased services within two years. In August 1997 the company had committed to acquiring 40 new vehicles and at that time OPRAF took the opportunity to reduce their subsidy by £93 million. As part of the discussions with First Group, OPRAF had now obtained a further commitment to 32 more vehicles, an overall increase of 72 vehicles. The first 40 vehicles have to be in place by 2001, and the company will try to expedite the remaining 32 vehicles as well. In addition, the franchise arrangements would be revised to provide for penalties to be paid for poor punctuality, such as a fine of £1,000 if a train was more than two hours late, and a free week's travel to be given to season ticket holders.

37. We were concerned to establish what OPRAF's accounts could tell us about the relative performance of individual train operating companies. In particular we asked OPRAF about the table of performance incentive payments at note 11 to their accounts. They said that not all train operating companies were included in the note because only 19 companies, the non-inter city companies, were included in the incentive regime, and not all of the companies covered by the regime had been operational throughout the year. Any company showing a net payment to OPRAF was in principle falling below the previous British Rail performance benchmark although, because of the transitional nature of 1996-97, direct comparison between the train operating companies on the basis of the table alone could be misleading. Payments or receipts under the performance regime were made on a monthly basis as a matter of course in the franchising process. In future years, information of this sort would be a sounder basis for comparison, as it would reflect a full year's performance for each company. In addition to their accounts OPRAF produce a separate annual report giving the details of payments to each train operating company.

38. We raised a number of further points of detail about the information disclosed in OPRAF's accounts. OPRAF told us[41] that they had spent £866,000 less on professional fees in relation to setting up the franchise agreements than had been anticipated. They also explained[42] that £16.1 million had been received from British Rail as not required by them in the final stages of their running the franchises. The accounts also disclosed privatisation costs of £25.5 million and redundancy costs of £33 million met by British Rail as their part of the privatisation process.[43]

Conclusions

39. We were concerned to establish whether the train operating companies were currently meeting their investment obligations, especially those with the shorter franchises. OPRAF assured us that all of the companies committed to investment under their franchise agreements were meeting their obligations, and that none were not expecting to be able to meet their commitments because of the length of the current franchise agreements.

40. We note that, as part of the deal for First Group to acquire the Great Western franchise, the Franchising Director has obtained a contractual commitment to provide 32 new vehicles, in addition to the extra 40 already promised. We expect him to monitor closely the delivery of this commitment to new investment in rolling stock.

41. In order to improve the transparency of the franchising arrangements, OPRAF should review the presentation of their accounts to make the note as informative as possible about the performance of individual train operators, and its implications for the level of franchise and incentive payments made and penalties imposed.


1   C&AG's report on OPRAF's 1996-97 Appropriation Account Class V Vote 7 (HC 251-V) Back

2   Q2, 51 Back

3   Q52 Back

4   Q30, 188-189 Back

5   Q4-6 Back

6   Q56, 59 Back

7   Q60 Back

8   Q55 Back

9   Q193 Back

10  Q194 Back

11  Q58 Back

12   C&AG's report paragraphs 23 and 25-28 Back

13   Q 42-44, 172, 190 Back

14   Q7-8, 45 Back

15   Q50 Back

16   Q100 Back

17   Q53 Back

18   Q 41, 50 Back

19   Q15, 17, 185 Back

20   Q20, 48, 50 Back

21   C&AG's report paragraphs 24 and 29 Back

22   Q8 Back

23   Q66-76 Back

24   Qs 78-85, 138 Back

25   Q110 Back

26   Q105-108 Back

27   Q9 Back

28   Q184 Back

29   Q10, 31 Back

30   Q100, 178 Back

31   Q63-65, 139-143 Back

32   Q161-164 Back

33   Q198-199 Back

34   Q116-117 Back

35   Q113-114 Back

36   Q115, 134 Back

37   Q144-145 Back

38   Q146-148 Back

39   Q155-158 Back

40   Q166-167 Back

41   Q32-34 Back

42   Q35 Back

43   Q36 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 22 July 1998