Select Committee on Public Accounts Minutes of Evidence


APPENDIX 2

Supplementary Memorandum submitted by the Chief of Defence Procurement, Ministry of Defence

MINISTRY OF DEFENCE APPROPRIATION ACCOUNTS 1996-97 (PAC 97-98/252)

QUESTION 154

BACKGROUND

  1. The damage occurred during the period September 1992 to April 1993 when the 16 aircraft concerned were undergoing modification work aimed at extending the fatigue life of the aircraft (the 25 FI modification programme) at RAF St. Athan. The modifications were to be carried out on up to 134 aircraft by a working party employed by Airwork Ltd (AWL) under a contract valued at £4.8 million. It was discovered that damage prejudicial to the strength of the aircraft structure had been caused, in the form of gouging of metal surfaces and over-sizing and distortion of fastener holes. After a technical appraisal of the aircraft, and supported by legal advice, MOD decided that the damage represented a substantial failure of performance under the AWL contract, which was terminated in May 1993. The 25 FI modification programme was resumed satisfactorily under RAF management and is planned to complete in 2002.

  2. There was pressure to get the damaged aircraft back to the front line because in the meantime the resumed 25 FI modification programme itself depleted the front line. Two aircraft, believed to be representative of the sixteen, were subjected to detailed technical examination. The findings were available early in 1994 and, based on them and subsequent advice from the contracted design authority, the Department decided that replacement of the damaged fuselage centre sections of all 16 aircraft with those from surplus Tornado F Mk 2 aircraft, in storage awaiting disposal, was the most cost-effective, quickest and lowest risk solution. This solution brought with it an additional benefit since the F Mk 2 fuselages had had little use and offered a fatigue life bonus over the aircraft which had successfully gone through the 25FI modification programme without damage. This meant that the ex AWL aircraft would not need to undergo a further, mid-life, fatigue modification programme which the others were expected to need later in their lives. The cost of this was estimated at about £600,000 per aircraft. The value of the fatigue bonus was accordingly estimated at £9.5 million.

NEGOTIATIONS WITH BRICOM

  3. Negotiations with Bricom (the owner of AWL at the time of this contract) began in 1995 based on recovery of the full cost of the rectification, initially believed to be in excess of £20 million but which was subsequently shown to be £19.26 million. Their initial offer of compensation, without admission of liability, was less than the £600,000 they had been paid. Negotiations continued through 1996, and by the end of that year the Bricom offer had increased to £5 million, but the company made it clear that it would be prepared to defend an arbitration case rather than increase its offer further.

  4. In taking stock with its legal advisers, the Department took account of the following factors:

    (a)  Reassessment of the original MOD view of the damage, based upon surveys suggesting that the two aircraft initially subject to detailed examination may have been two of the most serious cases, and not representative of the others, and that the overall damage might have been less serious than first thought;

    (b)  Difficulties in demonstrating to the standards expected at an arbitration tribunal that AWL caused all the damage found;

    (c)  Difficulties in wholly refuting Bricom's contention that they did not receive the level of technical support and assistance from RAF St. Athan to which they believed they were entitled.

  It was Counsel's opinion that these considerations would have substantially reduced any award to the MOD. Recognising that the legal and administrative costs of arbitration (estimated at £1.5 million) might not be recovered the Department's judgement, fully supported by Treasury Solicitor and Counsel, was that the amounted offered by Bricom should be accepted.

  5. There have been two complementary studies into the lessons to be drawn from this case. The first reported in December 1993, with recommendations addressing quality management and the monitoring of training given to contractor's personnel. Once settlement was reached with Bricom a wider study was initiated to look at, inter alia, how the case was managed after discovery of the damage and how legal advice had been brought to bear

in preparing the claim. That study reported in September 1997 and its recommendations are in the process of being implemented.

Chief of Defence Procurement

Procurement Executive, Ministry of Defence

14 April 1998


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 9 July 1998