Select Committee on Public Accounts Minutes of Evidence


Examination of witnesses (Questions 120 - 139)

WEDNESDAY 1 APRIL 1998

MR J MORTIMER, Treasury Officer of Accounts, further examined.

  120.  From what date were they involved?
  (Mr Jenkins)  They were involved from late 1994.

  121.  They were involved from 1994, through 1995 and at the point of decision to go live with the phase 3 system.
  (Mr Jenkins)  Yes; correct.

  122.  Then clearly it went horribly wrong as we can see from the report. What was their advice then? What was their reaction as things went wrong around you? What were they saying to you? What was their involvement then?
  (Mr Jenkins)  The consultancy period had in fact concluded by go live.[7] The tender only related to the period up to the time of operation.

  123.  So they were not involved after the decision was made.
  (Mr Jenkins)  That is correct.

  124.  Were any other consultants involved?
  (Mr Jenkins)  In so far as the issues of main concern were with the software we clearly were in touch with Oracle. We consulted them on the need to make improvements. As indicated in paragraph 24, there were these two software bugs for example and we were in very close contact with Oracle to resolve these issues.

  125.  You were without independent advice apart from Oracle who were actually writing the software and advising you on it after you made the decision to go live. I am confused about how consultants fit into this whole picture and I am just trying to get a picture over time of the role consultants were playing at each stage.
  (Mr Jenkins)  We employed the consultants for assistance with the development of the system. That was KPMG for phase 3. Following the go live situation in May, we retained some technical consultants and we still retain them, IBM, for the routine maintenance and correction of upgrades as you always require in the computer systems. We are also consulting Oracle Financial as the suppliers of the software. We are in regular touch with them.

  126.  The cost overruns for implementation, including phase 1 and 2 and including phase 3 amount to some £4.7 million, that is the overrun on the estimates leading to the total of around £11 million on implementation to date. Is that about right?
  (Mr Jenkins)  Without quickly looking at the figures, that sounds about right generally, yes.

  127.  That is the difference between the estimate for phase 1 and 2 of £2.65 million and therefore it came out at £6.6 million and between £2.62 million and it came out at £3.46 million so that cost overrun is around £4.5 million or thereabouts.
  (Mr Jenkins)  Yes.

  128.  The consultants who were involved up to and including the decision to go live were a part of that decision making and therefore could be expected to bear some liability for that cost overrun. Would that be true or not true?
  (Mr Trevelyan)  We felt the main failure in the system arose from the software and therefore from the software supplier and therefore from Oracle. The finger in industry has pointed in that direction and has led Oracle to issue a number of statements in explaining their position. More importantly, the contractual arrangement we had, was with Oracle as supplier and that is why they have been collaborating with us under the terms of the original contract in effectively repairing or rebuilding the system in the areas where we found it not to be functioning properly.

  129.  What was your contractual arrangement with KPMG? When you called them independent advisers, what was the nature of that contract? What role were they playing? If Oracle were doing all the work and doing all the software and getting all the blame, where were KPMG in all of this? What were they taking their money home for doing?
  (Mr Bryant)  We had a fixed price contract and we set it out as a project with specified deliverables over specified periods of time. Each time a deliverable was set up by KPMG it was tested by the agency and what we would technically describe as signed off. In other words we would say we accepted that part of the delivery in accordance with the terms of their contract. Therefore, having accepted it, it would in essence relieve them of any responsibility which we had not detected in our testing.

  130.  They had a get-out clause essentially in the contract with you that if something went pear shaped, as it did, they did not have to bear any of the consequences.
  (Mr Bryant)  We have never described it as that at all. What we said was that it was up to the agency to take the decision on whether what had been delivered was operable. So we tested it and took that decision. It was not KPMG's decision as to whether I ran the software.

  131.  I am glad it was not. It is your job to make the decisions and theirs to give advice but whether advisers give good advice or bad advice they have to stand by that in some way. Was one of the deliverables then an assessment of the wisdom of going live or not? Was that part of the contract they were asked to deliver, which you signed off, an assessment of whether to go ahead?
  (Mr Bryant)  It was more in the negative. The decision was the Board's but they saw no reason why we should not proceed.

  132.  That sounds like a non-denial denial so I will just try to press it again. They did not say you should but they did not say you should not.
  (Mr Bryant)  It was not their decision.

  133.  It was not their decision but advice I am getting at. Was it their advice that it was a wise move to go ahead on 1 May? Did they give judgement? Was it part of their contract to give a judgement? What were they there for with regard to that decision? Were they giving advice or not? If the answer is no, just say no. I am happy to accept no as an answer. I am just trying to find out what the answer is.
  (Mr Trevelyan)  Mr Jenkins was the chairman of the project board and is probably the best placed.
  (Mr Jenkins)  The precise terms of the contract did not say "Thou shalt give advice as to whether or not we go live". They were party to both the project and also another committee which I set up, an executive committee of the key players, where a partner from KPMG was present. We discussed regularly the question of go live. As part of the combined agreement they were party to that expression of agreement. All parties there, including KPMG and the Intervention Board, agreed it was time to go live. The final decision clearly rested with me on the advice I received.

  134.  Would it be too much to ask for a brief note about the role KPMG were playing? I do not want to see the full contract but I should like to have some clarification of exactly what role that consultancy group were playing in this process. That would help me.[8]
  (Mr Trevelyan)  Certainly.

  135.  Another consultant is mentioned. Forgive me but I am intrigued by the whole area of how consultants work and how we manage and relate to them as agencies. Paragraph 27 talks about another consultant being brought in to do an assessment of the system and the problems you were having in October 1997. Who was that? It says, "The consultant's preliminary observations" etcetera.
  (Mr Trevelyan)  That was KPMG as an independent contract consultant who then supplied us with a team of contract consultants with whom we have been working since then.

  136.  Up to and including the decision to go live in May they were there. It went pear shaped and badly wrong and they were at the committee where decisions were being made and where things went wrong and you have taken full responsibility for that, taken any burden away from them. Then at the very point that you realise it has gone badly wrong and you think you had better get this sorted out you bring the same consultants back in who have been sitting at the table whilst you were making decisions which clearly went wrong. Was that appointment put out to competitive tender?
  (Mr Trevelyan)  No. We wanted immediate assistance. The urgency was quite clear.

  137.  Why did you not go to competitive tender? Why did you appoint the same consultants you had been sitting round the table with for the previous 15 months who failed to spot the problem you were about to hit? You then hit the problem and you appoint the same consultants to tell you that you have hit a problem. Do you find that bizarre, strange?
  (Mr Trevelyan)  No, because what the Committee is tending to obscure is the distinction between the software supplier who supplies you with the kit and the contractor who gives you advice on how to implement that. The implementation in this particular case and the problems we were facing was a matter of accountancy. It was a matter of how, given the software you had in place, an accountant draws the books to account. That is not Oracle's job. Oracle provided a piece of software which was not providing satisfaction and we were pursuing them with our own resources. There is quite clearly a balance between our own resources, our own internal accountants, any advice we need on the operation of the system, which would be KPMG or another, and the software supplier which is Oracle. It may seem a complex arrangement and I am certainly very happy to explain it further in the note which you have asked for.

  138.  I still do not understand how you made a decision with a group of consultants present who do not bear any responsibility and then they go away and then when it has gone completely wrong with a catalogue of problems which have been sorted out you appoint the same consultants to come in to tell you something which I then understand, if I have read this right, paragraph 27, "The consultant's preliminary observations confirmed those already identified by my staff", that is the Comptroller and Auditor General's staff, "and by the Internal Audit report". If you had already been told what was going wrong, why did you appoint consultants to tell you again?
  (Mr Jenkins)  May I clarify? I believe you referred to paragraphs 27 and 28.

  139.  Twenty-eight is the IBM consultants, is it not?
  (Mr Jenkins)  In fact it is the other way round. Paragraph 27 is a very short term review by IBM to assess where the main problems were. That is the paragraph in which the NAO comments that confirmed the views expressed earlier.


7   Note by witness: In fact, the consultancy did not include the support of live running." Back

8   Note: See Evidence, Appendix 3, p. 25 (PAC 268). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 16 July 1998