Select Committee on Public Accounts Sixtieth Report


THE SALE OF AEA TECHNOLOGY

RESTRUCTURING

43. Restructuring AEA Technology between April 1994 and March 1996, and separating them from the United Kingdom Atomic Energy Authority before the sale, cost £121 million. Most of the money was spent on premature retirements and redundancy and on relocation costs. One of the objectives of rationalisation had been to improve accounting systems. In December 1995, however, after the bulk of the restructuring, a report indicated very serious shortcomings in AEA Technology's financial management information. Schroders concluded that the company could not be floated by the then target date of June 1996 because AEA Technology's financial information would not meet the standards required by the London Stock Exchange.[36]

44. In February 1996, AEA Technology's plan to meet these problems, including the secondment of two senior staff from Coopers and Lybrand to improve the finance functions, was implemented and the issues were resolved to a point where the Department felt the flotation could proceed. One lesson to be drawn from AEA Technology's experience is that it can be difficult and time consuming to recruit finance staff with appropriate experience at a time when future ownership of an organisation is uncertain. In AEA Technology's case, this resulted in difficulties in producing robust financial information on a timely basis at a key stage in the sale process.[37]

45. The Department told us that they were aware of the existence of these problems but not of their seriousness until a report was delivered to them in December 1995. They said they had then taken rapid action to remedy the deficiencies and that privatisation had been postponed by only six months as a result.[38]

46. Without rationalisation AEA Technology was unsaleable and in December 1995 the Department justified additional funding for the rationalisation by reference to the impact they expected the rationalisation to have on the sale.[39]

47. We therefore asked why the Department did not regard these rationalisation costs as costs of sale. The Department told us that the costs should not be regarded as sale costs because restructuring would have been necessary even if AEA Technology had remained in the public sector.[40]

48. We asked whether the decision to sell the company precipitated the restructuring. The Department said that the restructuring would have taken place anyway and was part of a longer term programme designed to improve competition for decommissioning services. Competition was likely to reduce decommissioning costs substantially, perhaps by as much as 25 per cent. In 1994, decommissioning costs were expected to total £9 billion and in 1997 they were shown to total £7.2 billion. Although this was not purely attributable to the restructuring of AEA Technology, the Department consider that the restructuring of AEA Technology played a significant part.[41]

49. We asked whether the saving in decommissioning costs would have occurred if AEA Technology had not been privatised. The Department told us that savings would have been smaller under Government ownership because competitors would not believe there was real competition. If the Government was both placing the contract and owning the company with whom the contract was placed, competitors would consider that the competition was fixed.

Conclusions

50. We note the Department's view that the £121 million that it cost to restructure AEA Technology and separate them from the United Kingdom Atomic Energy Authority before the sale should not be treated as sale costs because restructuring and separation would have been necessary even if AEA Technology had been retained in the public sector.

51. We are not convinced by this argument: without rationalisation the business was unsaleable and additional funding for rationalisation was justified by the Department by reference to the impact they expected rationalisation to have on the sale. It is unacceptable for Department's to seek to inflate net sale proceeds by ignoring expenditure related to the sale.

52. We note that one of the objectives of rationalisation was to put in place a new financial management information system. We are concerned that deficiencies in this system were not discovered until a late stage and that this delayed the sale by six months. We note that this was attributable to AEA Technology not having the finance staff with the necessary expertise. In the future, we look to vendor departments to ensure that finance staff with the required expertise are in place in time to provide the financial data required by the market for privatisation.


36   C&AG's Report paras 2.2-2.3, 2.11-2.12, Figure 5 Back

37   ibid paras 2.13-2.15 Back

38   Q10 Back

39   C&AG's Report paragraph 3 Back

40   Q127 Back

41   Qs 13-15, 62-65, 126-129 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 5 August 1998