Select Committee on Public Accounts Minutes of Evidence


Part of a Memorandum submitted by Mr Tony Purton

  This memorandum addresses MoD's execution of its professional buying function, as distinct from the associated planning and budgeting function. A number of dossiers placed with the Clerk of the Committee provide detailed expositions of the points made.

  The NAO's Major Projects Report 1997, and previous MPRs, confuse these two functions which makes it difficult to isolate and deal effectively with the causes of MoD's apparently abysmal procurement performance. In an article in RUSI NEWSBRIEF last October I suggested that the NAO's reports start at the wrong place and draw the wrong conclusions. Long serving Committee members have in the past expressed their exasperation at the task of trying to examine the MoD on this subject in just two hours once a year, and the format of the NAO's report does not help—see Dossier 1.[1]

  To put the two functions in perspective, planning and budgeting is the guessing game that is essential to overall planning. It is notoriously difficult to get right, but provides a measure of MoD's corporate planning and decision-making ability. Despite the assertions of the C&AG and the Treasury at the Committee's examination of MoD on the Appropriation Account on 30 March that MoD's problems are no greater than those of other departments in this regard, defence procurement professionals believe they are and demand greater flexibility than the impact of the annuality of government financing procedures should be properly explained and examined.

  Having decided to buy something, the efficiency with which that decision is implemented is the professional "raison d'etre" of the MoD(PE), and can be measured in its own right.

  The Secretary of State for Defence has promised to cure all MoD's ills by adopting "smart" procurement to achieve "faster, cheaper, better" procurement. Since the past is a window on the future it will be essential for the Committee to assure itself that MoD identifies and deals the causes of its past failures and does not build old faults into any new system—see Dossier 2.[2]

MoD's "systemic" procurement failures:

    (a)  The influence of the Defence Exports Support Organisation (DESO), whose only function (with the support and encouragement of the DTI) is to help British industry secure MoD orders and export the resulting products, is inconsistent with MoD(PE)'s remit to buy the best available equipment for the UK armed forces—Dossier 3.[3]

    (b)  Failing to place comprehensive, taut and enforceable contracts by employing standard procedures which undermine that objective:

    —  announcing the winners of competitive tender competitions before all the contract terms and price have been unequivocally secured—Dossier 4;[4]

    —  failing to place risk squarely on contractors by accepting their proposals unconditionally, but instead re-offering a bidder his own proposal for him to accept from the MoD—Dossier 5.[5]

    (c)  Granting contractors indemnities against the consequences of their own performance failures:

    —  by insisting on contractual liquidated damages provisions for late delivery thereby encouraging and excusing late delivery and preventing MoD from securing adequate compensation for the real cost of the contractor's default—Dossier 6;

    —  granting blanket product liability indemnities to British industry such as the "Hedger Smeeton" indemnity relating to aerospace products against the consequences of "crashings and groundings" and other specific indemnities such as the flight risks indemnity—Dossier 7.[6]

    (d)  Failing to take full advantage of the "buyer's law" nature of the Sale of Goods Act in relation to "fitness for purpose" and reliability "durability" of equipment delivered under MoD contracts by accepting, and often paying extra for, specific warranties which reduce MoD's rights in law—Dossier 8.[7]

    (e)  Failing to enforce MoD's contractual rights by withholding payment for breaches of contract and rejecting equipment which does not meet the contract—Dossier 9.[8]

  Examples of these failures are found in the following projects:

    Challenger II tank—2½ years late and technically unsatisfactory—potential claim for extra costs of £38 million to MoD sacrificed in a £3 million liquidated damages indemnity—Dossier 10.[9]

    Rapier 2000—Late in development but contractual provision for the recovery of £85 million progress milestone payments foregone granting BAe a £23 million "interest holiday at public expense—Dossier 11.[10]

    Tornado 25 F1—A £5 million contract that cost £25 million to complete two years late, and after recovering £5 million from the contractor for default left MoD with £15 million unrecovered extra costs—Dossier 12.

  Dossier 13[11] contains a collection of published articles. Dossier 14[12] contains a series of unpublished "Legal Awareness" articles.

Mr Tony Purton

Former MoD Director of Contracts

20 May 1998


1   Not printed. Back

2   Not printed. Back

3   Not printed. Back

4   Not printed. Back

5   Not printed. Back

6   Not printed. Back

7   Not printed. Back

8   Not printed. Back

9   Not printed. Back

10   Not printed. Back

11   Not printed. Back

12   Not printed. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 6 August 1998