MANAGING THE MILLENNIUM THREAT
PROGRESS
MADE
IN
THE
NHS IN
ENGLAND
33. The NHS relies heavily on IT systems and electronic
equipment for many patient services. It is impossible to predict
the seriousness of malfunctions, but in extreme circumstances
failure or malfunction of equipment could put patients lives at
risk. The Chief Executive of the NHS has described the year 2000
problem as the highest nonclinical priority in the NHS.
There could be serious disruption to the NHS in the year 2000
unless urgent preemptive action is taken.[29]
34. Initially in May 1996 the NHS Executive set up
a small project to assess what action needed to be taken, and
alerted Trusts and Health Authorities to the problem and issued
information packs. The Executive first wrote directly to Chief
Executives of Health Authorities and NHS Trusts on the potential
problems of the year 2000 date change in September 1996. They
did not set a specific timescale for action, although they told
Chief Executives that they should know where they stood before
the end of 1996. In October 1997, the NHS Executive instructed
Chief Executives of NHS Trusts and Health Authorities to take
personal responsibility for ensuring patient services were not
compromised, and set timescales for action.[30]
35. The Committee asked the NHS Executive why they
had set any deadlines in 1996. They told us that initially they
had followed through with training events and information packs,
and that they had monitored action in the early part of 1997.
At that time, they found that the response had not been as good
as they had wanted and this was one of the reasons why they had
then set up the monitoring process against targets.[31]
36. The Comptroller and Auditor General reported
that in October 1997, 10 per cent of NHS Trusts were not
confident that their IT systems would be compliant by the end
of 1999, and 15 per cent were not confident that their clinical
equipment would continue functioning normally in the year 2000.[32]
We asked the NHS Executive how they would ensure all trusts were
ready in time. They said they had now set very clear deadlines:
- a planning deadline of December 1998 when all
critical systems should be fully ready and tested or, if they
were not, there should be detailed plans to cope without those
systems and equipment; and
- a final check deadline of September 1999 to ensure
all parts of the NHS were either fully prepared or in some cases
had proper contingency plans in place.[33]
37. The NHS Executive added that all the returns
they had suggested that the two deadlines would be met across
the NHS. They were confident that everyone would meet their targets
for fixing IT systems. However, they did not think everyone was
confident of fixing their medical equipment, and this was one
of the reasons why the NHS had set aside £150 million
as a contingency sum.[34]
38. We asked if the deadline of September 1999 left
them with enough time to sort out any problems, should difficulties
emerge They were confident that good progress could be made during
the period December 1998 to September 1999. They would be monitoring
quarterly until the end of December 1999. They would also be receiving
regular reports from their district auditors and samples of the
quarterly reports would be sent to an independent reference group.
And although the responsibility for meeting the deadlines lay
with each Trust Board and each Health Authority, regional offices
would, and indeed had already intervened.[35]
39. We had previously examined the NHS Executive
on the development of hospital information support systems.[36]
We asked whether these systems would be millennium compliant,
and what this would cost. The Executive assured us that all patient
administration systems were being actively investigated by the
individual trusts who ran them in conjunction with suppliers,
and they expected all of them to be resolved in terms of year
2000 compliance problems by the dates they had set.[37]
As regards the cost, they told us that of the nine sites involved,
seven had maintenance agreements with suppliers which covered
the costs. Of the two sites that did not have maintenance agreements,
Nottingham City Hospital NHS Trust estimated the cost at £61,000
while the Birmingham Heartlands Hospital NHS Trust put the cost
at £501,000.[38]
40. Many of the more sophisticated diagnostic and
treatment services which the NHS use rely extensively on electronic
equipment and failure of those systems could have serious consequences
for patients. Initially the Medical Devices Agency advised that
while medical devices might show some year 2000 problems, these
were unlikely to be serious and very unlikely to be life threatening.
However, in October 1997 the NHS Executive instructed NHS organisations
to draw up inventories of electronic equipment, prioritise equipment
whose failures could have serious consequences, contact suppliers
for advice, take corrective action if necessary and draw up contingency
plans for equipment failure. The Medical Devices Agency issued
a bulletin to all medical equipment manufacturers advising them
to assess all their produces, identify any affected by the year
2000 problem and make this information available to users. They
also emphasised the need to prioritise action, stating that resources
did not exist to investigate every item of hardware and software
in use, let alone to put right those affected by the problem.[39]
41. We asked the NHS Executive why the Medical Devices
Agency was so late in recognising the potential threat. They agreed
that it had taken some time for the whole question of embedded
chips in electromedical equipment to be given the same emphasis
that had been given to IT systems, but that the Medical Devices
Agency was now providing proper support to the NHS. They recognised
that there are some pieces of equipment that are so critical and
could not be tested in time. As a result, they had set aside £150
million as a contingency sum to enable replacement or renewal
of parts.[40]
42. We asked the NHS Executive how they planned to
ensure that no patients were exposed to risk from equipment or
systems failure. They told us that the each NHS Trust was having
to tackle the supply industry almost on an item by item basis.
With thousands of different items of equipment in use, the Executive
were following all available lines of enquiry. They were trying
to obtain compliance information. They were being clear about
testing procedures where these were relevant. They had agreed
with the Medical Devices Agency that the initial check on each
bit of equipment would be made by the appropriate person holding
the equipment in the NHS, and by the manufacturer. They had established
a clearing house, a database on which people could exchange information.
And manufacturers had sometimes exchanged information with them.
Where they thought there might be problems, they were ensuring
that they had contingency plans in place. [41]
43. They admitted, however, that they could not guarantee
that nobody would die as a direct result of year 2000 problems.
But they assured us they had systematically assessed all the risks
and would continue to deal with them up to December 1999, and
that patients' safety was the premium on all they were doing.[42]
44. The Comptroller and Auditor General reported
that the information available on the state of readiness in General
Practice suggested GPs were likely to have difficulty in achieving
year 2000 compliance. And almost one third of Health Authorities
did not have confidence that GP systems would be year 2000 compliant
in time.[43] We therefore
asked the NHS Executive how they would make sure that every GP
would be ready. They took the view that the problems in GP surgeries
were a lot less serious than in other parts of the NHS. This was
partly because manufacturers of GP systems had been very good
in pushing compliance. In addition, the latest returns showed
that more than 80 per cent of GPs were well aware of the problems
in store. And they assured us that systems for cervical screening
had been made year 2000 compliant in 1995.[44]
45. They also pointed out that all GP systems were
going to have to be upgraded to accommodate the Government's objective
of having the facility to pass information freely and electronically
between hospitals and GP settings. So the combination of improved
software and in some cases improved hardware meant that the problem
in general practice could be properly resolved. They added though,
that GPs had good paper backup systems and these were an
important safety net.[45]
46. The NHS Executive have told NHS organisations
that they should plan to meet the cost of their year 2000 compliance
programme from within existing budgets. The Comptroller and Auditor
General reported that inadequate resourcing increased the risk
of failure, and was the single largest area of concern identified
by respondents to the NAO survey about the difficulties they faced
in tackling the year 2000 problem. The Comptroller and Auditor
General also reported that the cost of tackling the year 2000
issue in the NHS was estimated at £230 million but could
be much higher.[46]
47. We therefore asked the NHS Executive about the
cost, and how they planned to ensure that the NHS had adequate
resources to complete the programme. They told us that on the
basis of information from each individual NHS Trust, GP and Health
Authority at the end of March 1998, the cost would be £320 million
in England. This was made up of £170 million to deal
with all of the IT issues and £150 million as a contingency
against problems with medical devices.[47]
48. This figure needed to be put in the context of
annual NHS expenditure on IT of £200 million and nearly
£1 billion on medical and surgical equipment. They thought
that the purchase of certain bits of equipment or upgrades of
software might be brought forward from the normal replacement
cycle but that any displacement activity would be under the capital
budget and would not impact on recurrent monies that pay for staff
and NHS activity.[48]
49. The Committee sought further reassurance from
the NHS Executive that every Trust would be able to fund its year
2000 programme without loss of service to its patients. The Executive
assured us that the money would be allocated on a nonrecurring
basis, with £210 million of the £320 million
being spent in 199899. They added that since May 1997, for
the NHS in England, the Government had allocated an extra £1.7 billion
and part of that was to deal with this pressure. Expenditure on
year 2000 work would be insulated from the routine of Health Service
spending and would not lead to any downgrading of patient care.[49]
Conclusions
50. In view of the potential impact of the year 2000
issue on NHS services and on patients, we are astonished that
the NHS Executive got off to such a slow start in addressing the
problem. The failure to set deadlines for action in September
1996 was a missed opportunity to ensure that all NHS bodies took
the threat seriously. The action taken by the Executive subsequently
means that they now have in place the elements of a well managed
project.
51. We note that the NHS Executive are confident
that all IT systems will be modified in time, and that medical
equipment will either be modified or replaced where required.
But we are concerned that the deadline of September 1999 for finally
checking that all parts of the NHS are fully prepared, or if not
have contingency plans in place, leaves them very little time
to deal with problems that emerge. We look to the Executive to
take strong and decisive action, including direct intervention
where appropriate, to ensure that all NHS organisations and GPs
are fully prepared.
52. Many of the more sophisticated diagnostic and
treatment services which the NHS use rely extensively on electronic
equipment, and failure of those systems could have serious consequences
for patients. We are therefore appalled that the Medical Devices
Agency did not realise the potential impact of failures until
late 1997. In our view, this delay, and the misleading advice
they gave the NHS in 1996 can only have increased the risks to
patients and the costs of remedial action.
53. We welcome the action the NHS has now taken to
tackle medical equipment, their assurance that they were putting
a premium on patient safety and the fact that the NHS has set
aside £150 million to help replace equipment or parts affected
by the year 2000 problem. But we are disturbed that the NHS Executive
could not give us a categorical assurance on the safety of patients.
We expect the NHS Executive to monitor the position on medical
equipment closely, and to take every step possible to ensure the
safety of patients.
54. We note the NHS Executive confidence that the
GP systems will be ready in time.
55. We note NHS Executive's assurance that expenditure
on year 2000 work will not lead to any downgrading of patient
care. However, we remain concerned about the possible impact on
capital programmes of diverting money to year 2000 work; about
the possible delay to other important projects; and about the
added pressure on already stretched budgets. We expect the Executive
to monitor closely the impact of the costs of tackling the year
2000 problem, and ensure that lack of resources do not result
in the failure of systems and equipment that are critical to NHS
services and patient care.
29 C&AG's report, (HC 724 of Session 1997-98) ,
paras 2.7-2.10 Back
30
C&AG's report, (HC 724 of Session 1997-98), paras 2.16-2.22 Back
31
Qs 67-68 Back
32
C&AG's report, (HC 724 of Session 1997-98), para 13 Back
33
Qs 10, and 41-46 Back
34
Qs 132-138 Back
35
Qs 56-57, 95 Back
36
7th Report of the Committee of Public Accounts, Session
1996-97, (HC 97) Back
37
Qs 114-122 Back
38
Evidence, Appendix 2, p19 Back
39
C&AG's report, (HC 724 of Session 1997-98) , paras 2.10, 2.18,
and 2.24-2.26 Back
40
Qs 131, 139-143 Back
41
Qs 9, 92-93, 96 Back
42
Q96 Back
43
C&AG's report, (HC 724 of Session 1997-98), para 15 Back
44
Q11 Back
45
Qs 19-20 Back
46
C&AG's report, (HC 724 of Session 1997-98), paras 2.54-2.56 Back
47
Qs 12, 24, 83-84 Back
48
Q54 Back
49
Qs 12, 130 Back
|