Select Committee on Public Accounts Sixty-Eighth Report


THE DISTRIBUTION OF LOTTERY FUNDS BY THE ENGLISH SPORTS COUNCIL

MAKING GRANT PAYMENTS

25. One of the Sports Council's main controls to safeguard the use of lottery funds is that payments are only made on receipt of claims showing expenditure incurred. However, the National Audit Office found that in five of twenty cases examined, claims had been approved for payment in respect of invoices which merited further investigation. The main criteria applied seemed to be whether the amount claimed was within the overall level of grant awarded.[22] We asked the Sports Council what action they had taken to strengthen their controls over the payment of lottery grants. The Sports Council maintained that invoices had in fact been checked, but that this had not been evidenced in the sense of case officers actually signing off that the invoice had been checked. The Sports Council told us that they had put two things in place. All case officers and senior case officers now had to sign for the fact that they had checked invoices against applications and that the invoices were correct both in terms of content and amount. Secondly, the compliance team provided an additional check to make sure that this had been done.[23]

26. We pressed the Sports Council on the question of invoices not being checked, by referring to case studies in the National Audit Office report.[24] The National Audit Office had found one case where, after the work was said to be largely complete, a final invoice, representing 30 per cent of the total project cost, was received by the Sports Council. This invoice gave no details of the work carried out and brought the amount claimed exactly to the amount of the lottery award approved by the Sports Council.[25] We asked the Sports Council whether they were satisfied that this did not amount to fraud. The Sports Council admitted that they were not at all satisfied with the way they had handled this particular project and had asked their management audit team to have a look at it. They added that the outcome of this project was very good and that the club was providing a very good community facility.[26]

27. The Committee also noted one case where the construction work had been carried out by a firm owned by the secretary of the club, which we considered was a breach of best practice and a clear conflict of interest. We again asked the Sports Council if this would not be close to fraud. They told us that it was a feature of small voluntary clubs that members offered to do things at cost price or cheaper, but that they had taken the view that the club must go out to tender in all circumstances. They told us that their checking of invoices had been strengthened considerably and the checking that tendering procedures had been followed had been built into the monitoring procedures which they had adopted.[27]

28. Where a project comes in under budget, the amount of grant needed by the applicant to cover the difference between the project cost and the level of partnership funding will be lower. Although the Sports Council can seek to recover the full amount of any underspend, they only act where the underspend is significant (five per cent or more). Their practice is to consider whether the unspent grant can be used to enhance the project and, if so, they would not seek to reduce the award. The National Audit Office's report reviewed four cases where the underspend was greater than five per cent and found that the Sports Council's approach had not been entirely consistent and that much had depended on the positions taken by the applicant and the Sports Council. In one case, the Sports Council did not identify an underspend which amounted to seven per cent of the approved project costs.[28]

29. We questioned the Sports Council over their attitude to underspends and whether they should be more critical in terms of the return of underspends. The Sports Council told us that the presumption was that they would take the money back, though they would look at it on a case by case basis. In some cases, they made a conscious decision to allow the applicant to retain the funds or to allow them to spend the money to enhance the project. They recognised that they had a responsibility not just to the applicant they were dealing with at that point, but to the hundreds of others coming through the system. They said that in 49 cases, adding up to about £800,000 where there had been such an underspend, they had taken that money back to be recirculated into other projects.[29]

Conclusions

30. Robust controls over the payment of lottery monies are essential in order to safeguard lottery funds. We are thus deeply concerned that the Sports Council have undertaken little detailed checking of invoices before making payments and that the main check made is that the amount claimed does not exceed the level of lottery money awarded. In five of twenty cases examined by the National Audit Office, the Sports Council approved claims for payment in respect of invoices which merited further investigation. We note the Sports Council's view that invoices are checked and that this is just not evidenced, but consider that the cases reported by the National Audit Office indicate that the weaknesses in control are more fundamental than this. We recognise that the Sports Council have since acted to strengthen their controls over the checking of invoices. We recommend that all claims for payment of grant be thoroughly checked against supporting documents and against the project specifications and approved cost and that in future this is properly evidenced on the documentation.

31. We are concerned about the Sports Council's approach towards projects that underspend and which therefore need less grant than originally envisaged. The Sports Council have not been consistent in the way they handled such cases and, in one case examined by the National Audit Office, the Sports Council had not identified an underspend of seven per cent of the approved project cost. We note that the Sports Council only pursue significant underspends and, even then, first consider whether the underspent grant can be used by the applicant to enhance the project. We note the Sports Council's view that there is a presumption of recovery, but that every case should be looked at individually. We look to the Sports Council to take a more robust and consistent line with applicants on the recovery of underspends.


22   C&AG's report (HC 617 of Session 1997-98), paras 4.5, 4.6, 4.8  Back

23   Q5 Back

24   Q60 Back

25   C&AG's report (HC 617 of Session 1997-98, para 4.8 (case study 13) Back

26   Q60 Back

27   Qs 61-62 Back

28   C&AG's report (HC 617 of Session 1997-98), paras 4.11-4.14 (case study 17) Back

29   Qs 40-41 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1998
Prepared 2 December 1998