Previous Section | Index | Home Page |
Mr. Ruffley:
To ask the Minister of State, Lord Chancellor's Department if he will list the sets of barristers' chambers in London who have rendered
31 Mar 1999 : Column: 775
services for his Department since 1 May 1997 and the remuneration made in respect of such services in each case. [68623]
Mr. Hoon
[pursuant to his reply, 1 February 1999, c. 480]: I regret that some of the figures given in the answer were incorrect. The correct figures as at the date of my original answer are set out in the table.
£ | |
---|---|
London Chambers | Total paid |
Blackstone Chambers, Blackstone House, (formerly 2 Hare Court) | 13,565 |
4 Breams Buildings | 6,373 |
1 Brick Court | 3,995 |
Brick Court Chambers 15-19 Devereux Court | 731 |
1 Crown Office Row, Ground Floor | 5,551 |
Devereux Chambers, Devereux Court | 1,486 |
5 Essex Court | 164 |
39 Essex Street | 20,180 |
Falcon Chambers | 2,361 |
4-5 Gray's Inn Square | 3,624 |
1 Hare Court | 3,348 |
Keating Chambers, 10 Essex Street | 1,686 |
1 King's Bench Walk | 3,378 |
6 King's Bench Walk | 7,832 |
11 King's Bench Walk (Chambers of Mr. Eldred Tabachnik QC and Mr. James Goudie QC) | |
(i) excluding fees paid to Mr. Philip Sales | 3,143 |
(ii) fees paid to Mr. Philip Sales whilst on the Attorney General's Panel, but prior to his appointment as First Treasury Counsel on 1 December 1997 | 9,370 |
(iii) fees paid to Mr. Philip Sales since his appointment as First Treasury Counsel on 1 December 1997 | 39,596 |
11 King's Bench Walk (Chambers of Mr. Franz Muller QC) | 1,645 |
Monckton Chambers, 4 Raymond Buildings | 2,355 |
13 Old Square, 1st Floor | 2,393 |
3 Pump Court, Upper Ground Floor | 2,585 |
6 Pump Court, Ground and Lower Ground Floor | 2,350 |
Queen Elizabeth Buildings | 18,682 |
3 Raymond Buildings | 1,092 |
3 Serjeants' Inn | 840 |
7 Stone Buildings, Ground Floor | 1,175 |
1 Temple Gardens | 34,213 |
Mr. Gorrie: To ask the Secretary of State for Scotland what was the initial budget for converting and fitting out the Church of Scotland Assembly Hall and adjacent buildings as a temporary home for the Scottish Parliament; and what is the latest estimate of the cost. [70210]
Mr. Dewar [holding answer 15 February 1999]: The current estimates are:
The initial estimate was given in my answer on 12 May 1998, Official Report, column 88, to the right hon. Member for Caernarfon (Mr. Wigley), and included rent and rates. This was a provisional estimate and I made it
31 Mar 1999 : Column: 776
clear then that it did not include fitting out costs, which were still being assessed. The estimate of building conversion costs at that time was £2m. Full building condition surveys were carried out on the CEC office buildings when the Scottish Office took occupation at the end of November 1998. These surveys revealed that significantly more work would have to be carried out in these building than was previously envisaged. In particular, work was required to ensure that lighting throughout the office buildings complied with current statutory requirements and to improve electrical systems, fire alarms and emergency lighting to meet current building regulations. In addition special services to meet the needs of the Parliament such as IT networks, security measures and provision for broadcasters have had to be provided.
The costs of these items could only be properly assessed once the Scottish Office had occupation of the buildings.
All of these costs will be met from the financial provision made for the establishment of the Parliament in 1998-99 and 1999-2000.
Mr. Gorrie:
To ask the Secretary of State for Scotland what is the estimated cost of those roadworks made necessary by the siting of the new Scottish Parliament building. [77939]
Mr. Dewar
[holding answer 26 March 1999]: I refer the hon. Member to the answer I gave him earlier today.
Mr. Gorrie:
To ask the Secretary of State for Scotland what is the estimated cost in relation to the new Scottish Parliament building of (a) VAT, (b) fees, (c) site purchase, (d) site clearance and preliminary works and (e) road works; and which of these are included in the £50 million cost referred to in his answer of 28 January 1999, to the hon. Member for Linlithgow (Mr. Dalyell), Official Report, column 385. [77438]
Mr. Dewar
[holding answer 24 March 1999]: The figures requested (with the exception of (e)) are shown in the table, along with the estimated construction cost of £50 million (excluding VAT and fees) referred to in my answer to my hon. Friend the Member for Linlithgow (Mr. Dalyell) on 28 January 1999, Official Report, columns 385-86.
Cost estimate £ million | |
---|---|
Site Purchase | 4 |
Site Preparation | 1 |
Construction | 50 |
Fees | 10.5 |
VAT on construction and fees | 10.6 |
The figures shown are estimates and subject to review in the light of the development of the detailed design for the building and, in due course, of the results of the competitive procurement of works packages. The costs for item (e) will be estimated once the proposals for the surrounding area have been developed further.
Mr. Maclean:
To ask the Secretary of State for Scotland what (a) reviews, (b) task forces and (c) advisory
31 Mar 1999 : Column: 777
groups have been established by his Department since 1 May 1997; what costs they have incurred to date; and what reports they have published. [71514]
Mr. Dewar
[holding answer 22 February 1999]: Details of reviews, task forces and advisory groups established since 1 May 1997 and of the reports they have
31 Mar 1999 : Column: 778
published follow. Where the information is readily available, approximate costs incurred on matters such as members' expenses, publication of reports and consultation exercises are shown. Staff costs are not included as these are subsumed within the Department's running costs.
31 Mar 1999 : Column: 777
31 Mar 1999 : Column: 779
31 Mar 1999 : Column: 779
From 1 July, this will be a matter for the Scottish Parliament.
Next Section | Index | Home Page |