Select Committee on Defence Minutes of Evidence



Examination of witnesses (Questions 120 - 138)

WEDNESDAY 10 FEBRUARY 1999

MR KEVIN TEBBIT, MR COLIN BALMER, AIR MARSHAL SIR JOHN DAY and MR JOHN HOWE

  120.  Yes.
  (Mr Tebbit)  Of course there is great variation.

  121.  I would like an average so that we can compare that average with the slippage.
  (Mr Howe)  I cannot quote an average I am afraid, no. Some of these contracts go over ten years or more.

  122.  Okay.
  (Mr Howe)  Substantially more in the case of the very large projects.

  123.  That would be useful for the future to have that comparison so that we can have the average period of the contract and the average slippage can be checked.
  (Mr Howe)  Yes. Bear in mind that the slippage here is a slippage that occurred in the year——

  124.  1997-98, I understand.
  (Mr Howe)  So you get some idea of proportionality from that.

  125.  You have compared it to previous years, I understand that.
  (Mr Howe)  Yes.

  126.  Then I would like to ask whether there are any calculations as to how much these delays have cost the MoD. Do you have anything like that?
  (Mr Howe)  We cannot quote a reliable overall figure for the cost of delays, no, because some of the costs are pretty indirect although they must certainly exist: the cost of the older equipment running on, the high cost of maintaining it, the cost of changing plans because when equipment runs late you have to change your plans to receive it and to put it into service, and the new equipment is often cheaper to run of course. I do not think we can produce a reliable figure for the overall impact of what the delay is, no.
  (Mr Tebbit)  We know that something at the moment is costing us slightly less in crude terms because as the chart there shows there is a 0.2 per cent change in project costs, but of course the opportunity cost of not getting the stuff on time is a different matter.
  (Mr Howe)  That is just the equipment related costs you are looking at.

  127.  On page thirty it mentions one programme for the year that slipped further while its timetable was reassessed, right at the bottom of page 30. Can you say something about that and, indeed, the two projects that failed to meet their 1997-98 in-service date although they did in the subsequent year? Are you able to say anything about those three projects?
  (Mr Howe)  I am not sure what that remaining programme at the bottom line is I am afraid, I would need to let you know that.

  128.  Okay. Perhaps you could do that in writing.
  (Mr Howe)  Yes, I will sweep that up.

  129.  That chart also says what was achieved in terms of unsatisfactory technical performance was nought per cent, everything worked, which got me a little bit alarmed and thinking has the actual checking standard been reduced. Did everything work that came on?
  (Mr Howe)  The response to technical problems when they occur in a project is often to take more time to solve them rather than to accept equipment which is sub-standard. I think that technical problems, would tend to be reflected in a missed timetable target rather than in equipment which comes into service sub-standard. One of the features of Smart procurement, as I think I mentioned earlier, is that with a new procurement process, a more integrated procurement process, we feel that we are better able to make judgments of trade-off between time, cost and performance.

  130.  Have you any slippage targets for this financial year and perhaps for next year?
  (Mr Howe)  For the present year our target is 1.1 months in a year, so a very slightly tighter target than the one we reported against in this report.

  131.  Have you any indication of how close you are getting to that or not, or is it too early to tell?
  (Mr Howe)  We are analysing it at the moment. We will have to wait and see I think. For the future we will be held to the targets in the agreement with the Treasury on our performance and we are going to be held in the post-Smart Procurement era to much tighter targets of just under a month for existing projects and 0.3 of a month for new projects' slippage.
  (Mr Balmer)  We have expressed it in days in the Public Service Agreement. It is measured as ten days for major new projects and less than four weeks for existing major projects.
  (Mr Tebbit)  But there will be a long period, I have to say, or a significant period while older projects come through and continue to show slipped timescales.

  132.  So on to Smart procurement then, clearly that will have a significant impact on that slippage performance indicator, but where will we actually see the results? Where will you publish your assessments of the achievements of Smart procurement? Will it be in the SDE, the performance reports in future years, or where?
  (Mr Tebbit)  It will be coming out in the annual output analysis. This is now part of, as I say, our Public Service Agreement; we are obliged formally to publish performance against these targets that are now, as I say, published in December, so you will be seeing them on an annual basis. Meanwhile, let me say that we now have 20[3] pilot projects up and running, the first 20[4] integrated project teams up and running, where we are putting together the operational requirements people with industry to define projects in a more collegiate and a more informed way on both sides, so we know what industry can deliver and it knows exactly what we need. We are also forming 150 of these teams in all over the next year, by the end of the year and good progress has been made so far. Examples of the targets which we have identified so far are cost savings of between 5 and 10 per cent in the through-life cost of one of our projects, Brimstone, some of which goes to industry again and some of which we take, as it were, as a saving. A reduction of up to five years in the time from main investment to in-service of the future offensive air system. And s reduction of up to 20 per cent in the logistic support cost for VC10 with an 18 per cent improvement in aircraft serviceability. Now, those sorts of improvements we are pretty confident we can get across the board, as I say, as a result of talking much more specifically to industry that is coming to us on these projects and putting to them time, cost and quality trade-offs rather than finding at a late stage in the project that things are too locked in to be moved around after the initial point.

  133.  That is very welcome. Then in the light of those, and you are in the early stages, I know, of these pilot projects, but have you got a latest assessment of the savings that you think that Smart procurement will bring about?
  (Mr Tebbit)  Well, we have pledged ourselves to £2 billion over a ten-year period and that is still the target, and I would take an opportunity to demonstrate openness in that if you would care to access the MoD website, you will find the Smart procurement section there which has documentation on it which is basically trying to put across what we are seeking to achieve and inviting comment on it and we are trying to engage industry really seriously in this, so it is not just for the general public, but it is also for companies to actually latch on to.

Chairman:  Well, I am sure that we have located it.

Mr Colvin

  134.  I think that is very important because maintaining a defence budget for the next three years at the level which is 4 per cent less than last year, and we have had to accept a cut, can only be maintained if we achieve the targets set out in SDR on Smart procurement, on asset disposals and on greater efficiency, so I am glad that those three items are addressed in the performance report, but could they be very specifically costed so that when the performance reports come out, we can see whether we are on track, otherwise in real terms we are going to face another 4 per cent cut in the defence budget over three years and that is something we would be very concerned about?
  (Mr Tebbit)  They will be and, as I say, going right back to the beginning, I am still a little lost to understand the problem about asset sales and revenue realised from selling off property because, as far as I am concerned, that is very much part of the transparency picture.

Mr Blunt

  135.  And where you are achieving efficiency savings, that is part of the transparency and that will be made clear?
  (Mr Tebbit)  Indeed. The 3 per cent challenge on efficiency. At the moment this year we will do rather better than that, we think.

  136.  You will tell us not that you have done it, but how?
  (Mr Tebbit)  And where, in which budget area and that sort of thing.

Mr Blunt:  Thank you, that would be helpful.

Chairman

  137.  Thank you very much for coming, you have emerged less bruised than your former boss in the Foreign Office.
  (Mr Tebbit)  I have not received such a nice letter from my Secretary of State, Mr Chairman.

  138.  We have only achieved 65 per cent of our target of 22 questions. We would like to write to you as well as expecting you to write to us, perhaps with the additional questions, unless you would like to come back and answer them verbally. I suspect that you would prefer to write your answers. I might give you some encouragement: we are producing a performance report and it occurred to me that maybe you could get a team together in the MoD, including Richard Mottram and Lord Gilbert and maybe you could reverse roles. With the television cameras in that could be quite an interesting session.
  (Mr Tebbit)  Three hundred and sixty degree reporting by the sound of it.

Chairman:  Thank you very much to you all for coming.


3  Note by witness: figure should read 10. Back
4  Note by witness: figure should read 10. Back

 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1999
Prepared 24 May 1999