THE FUTURE OF THE EC DEVELOPMENT BUDGET
Underspends
35. One of the key concerns put to the Committee
during this inquiry has been the allocation of resources to programmes
which are politically important at the expense of those which
are developmentally important. This is all the more shocking given
that programmes which focus on better off developing countries
consistently underspend. A general trend showing consistent
underspends across Category 4 expenditure is demonstrated in Table
6 below.
Table 6: Disbursement rate of EC Category 4 Budget,
1993-97
(Million Ecu)
|
1993
|
1994
|
1995
|
1996
|
1997
|
Financial Perspective
|
4,120 |
4,311
|
4,895 |
5,264
|
5,622 |
Budget (Commitments)
|
3,407 |
3,289
|
4,094 |
4,520
|
4,860 |
Commitments |
3,191
|
3,191 |
3,769
|
4,247 |
4,486
|
Annual Budget for Payments
|
2,139 |
2,375
|
3,204 |
3,723
|
3,921 |
Actual Payments |
1,954 |
2,159
|
2,377 |
2,753
|
2,950 |
UNDERSPEND
(Annual budget for payments minus actual payments)
|
185 |
216
|
827 |
970
|
971 |
Sources: General Budgets of the EC 1994-98, Draft
General Budget 1999
Note: Within each annual budget, emergency aid
reserves appear under Category 6, separate from the external action
category. Out-turn figures for Category 4, which are published
in subsequent annual budgets include expenditure of both the budget
for humanitarian aid and any expenditure of emergency aid reserves,
but these two sources of funds are not separated out. We have
therefore excluded emergency aid from our calculations of budgets
for commitments and payments.
36. Table 6 shows that annual budgets fall consistently
and increasingly below the ceilings set out in financial perspectives.[77]
This is not necessarily something we would criticise, given that
financial perspectives are ceilings rather than targets, and in
light of DFID's explanation that "these trends reflect stricter
budget management than in previous years."[78]
It does, however, lend credence to DFID's argument that Category
4 ceilings should be stabilised over the seven years covered by
the new Financial Perspective,[79]
reflecting a more realistic expectation of the amount of external
action resources which can be managed by the Commission. This
point is further demonstrated by the failure of the Commission
actually to make financial commitments in line with the figure
for commitments in the annual budget. In 1997, for example, the
Commission made commitments amounting to 92 per cent of the budget
for commitment appropriations.[80]
Table 6 shows that in the period 1993-1997, the Commission made
commitments which, on average, amounted to 93 per cent of its
budget for commitments.
37. The new Financial Perspective proposes a cut
in the rate of growth in the Category 4 budget from an average
of 9 per cent per year from 1993-99 to around 2 per cent per year
from 2000-2006. It is clear that the rapid increase in the Category
4 budget from 1993-99 has been a significant factor in producing
the situation which now exists: budgetary allocations are being
made which simply cannot be implemented. Richard Manning told
us that "anybody in the development business would say that
the hardest thing is to manage a sharply rising programme."[81]
This point is demonstrated in Figure 2, which shows that the ability
of the Commission to disburse funds has not increased in line
with the rapid increase in its budgetary allocations over recent
years.
38. In the light of these problems, DFID is proposing
a further cut in the rate of increase in Category 4 budget ceilings,
beyond that which has been proposed by the Commission: "Given
the rapid growth of the EC's external assistance programmes over
recent years, and concerns over the quality of these programmes,
the Government considers that lower Category 4 ceilings for 2000-2006
than those proposed by the Commission would be appropriate."[82]
Richard Manning did not think that "additional resources
can easily be spent effectively given the other constraints which
exist."[83] In fact
Clare Short wanted "to constrain [Category 4] to the amount
it is now and then put a bit of energy into increased effectiveness
as the practical way of making progress."[84]
39. Once resources have been committed to a particular
project, payments are usually made over a prolonged period. This
is one of the reasons for the practice of setting separate annual
budget allocations for commitments and payments, with the budget
for payments usually being set lower than the budget for commitments.
The OECD DAC peer review of the EC suggests, however, that
in the EC, the gap between commitments and disbursements is unacceptably
large, concluding that, "A significant gap between amounts
committed for ODA and actual disbursements has become a persistent
concern in the Commission's programmes in the 1990s. Between 1992
and 1996, ODA commitments exceed disbursements by about $1600m
each year, with the gap having reached more than $2200m in 1994."[85]
This assessment is reinforced by an examination of the extent
to which the Commission succeeds in disbursing the amounts which
it predicts in its annual budgets.
40. Table 6 clearly shows that over a period of five
years, the Commission has failed to disburse payments in line
with its budget for payments, which is already significantly less
than its budget for commitments. Figure 2 demonstrates this trend
in graphic terms.
Figure 2: Difference between annual budget for
payments and actual payments for Category 4 expenditure 1993-97
(Excluding Humanitarian and Food Aid)
(Million Ecu)
Sources: General Budgets of the EC 1994-98, Draft
General Budget 1999
The OECD DAC suggest this inability to disburse the
allocated budget, "can be attributed to a range of factors,
some within the Union's sphere of influence - such as low staffing
levels and complex administrative procedures slowing down implementation
- and others beyond it - such as the absorption rate and administrative
capacities within recipient countries."[86]
Philip Lowe posed the following question in evidence: "Why
can the World Bank safely disburse probably more than the Commission
does in most of these countries? The answer is that the World
Bank has a system which is geared to doing this, the Commission
does not. The problem is that the amount of money does not match
the delivery mechanism."[87]
It is not enough, however, simply to blame underspends on the
inefficient management of the Commission. The fundamental mistake
has been to allocate excessive funds in the first place for predominantly
political reasons.
41. A closer examination of patterns of budgetary
discipline within particular Category 4 programmes reveals the
political nature of these demands. The Phare, Tacis and MEDA programmes,
all of which are close to the top of the political agenda of the
Union, have particularly poor records of budgetary implementation.
The difference between budgeted and actual payments for these
programmes are shown in Figures 3, 4 and 5 below.
Figure 3: Difference between annual budget for
payments and actual payments for the MEDA programme, 1993-97 (Million
Ecu)
Sources: General Budgets of the EC 1994-1998,
Draft General Budget 1999
Figure 4: Difference between annual budget for
payments and actual payments for EC Cooperation with CEECs (Phare),
1993-97 (Million Ecu)
Sources: General Budgets of the EC 1994-98, Draft
General Budget 1999
Figure 5: Difference between annual budget for
payments and actual payments for EC Cooperation with the New Independent
States and Mongolia (Tacis), 1993-97 (Million Ecu)
Sources: General Budgets of
the EC 1994-98, Draft General Budget 1999.
42. The DAC estimates that backlogs of payments (defined
as budgetary commitments for which contracts had not yet been
signed) at the end of 1996 amounted to 2.3 billion ecu for CEECs,
covered by the Phare programme.[88]
Despite a clear trend in underspends in the Phare programme over
recent years, which is shown in Figure 4, the 1999 Preliminary
Draft Budget presented by the Commission included a proposed increase
in the budgetary allocation for aid to CEECs of 29 per cent. We
met Catherine Day, the Director of the Phare programme in Brussels,
who informed us of measures which had been taken to improve the
record of the Phare programme in implementing its allocated budget.
These reforms had included the introduction of a 2-year time limit
within which a contract must be signed following a commitment,
and a further 12 months within which disbursement of funds must
take place. The Commission was now more sophisticated in its selection
of projects, and did not sign contracts until its projects were
ready for implementation, thus reducing the potential for project
failure after contracts had been signed. As a result, in 1997
the backlog of committed but undisbursed funds had stabilised
for the first time. Tangible results of the reforms of the Phare
programme are, however, yet to be seen because as yet, of commitments
made during 1996, only 20 per cent have been translated into payments.
Similarly, of funds committed made during 1997, only 23 per cent
have been disbursed.[89]
43. For new independent states, which are covered
by the Tacis programme, the DAC estimated the payments backlog
at the end of 1996 to be 0.7 billion ecu.[90]
The pattern of underspend in the Tacis programme is shown in Figure
5. DFID attributes the failure of the Tacis programme to disburse
the available resources to the following factors: "the late
agreement of the current regulation; staff shortages in DGIA;
lengthy administrative and financial procedures; and a lack of
absorptive capacity (the ability to identify appropriate projects)
in partner countries. These constraints have led to a backlog
of commitments, or projects agreed with partner countries, for
which the Commission has yet to enter into contracts with project
operators."[91]
44. A clear indicator of a lack of ability to manage
the available budget is the fact that the Tacis programme has
developed an atrocious record in making payments to NGOs and contractors.
The British Consultants Bureau (BCB) has been particularly trenchant
on this issue:
"There are now
five BCB member firms who are owed 1 million ecu each [by the
Tacis programme]. Fifteen BCB firms alone are owed a total of
£4.25 million with many owed lesser amounts. Payments are
many months late! Any payments delayed more than 60 days attract
interest at Belgian equivalent rates. Thus UK development money
is in part wasted on nugatory late payments rather than being
used for the purpose intended."[92]
We were told by the Director of the Tacis programme,
Mr John Kjaer, during our visit to Brussels, that steps were being
taken to rectify these problems. The establishment of the Common
Service Directorate (SCR), which we discuss later in this Report,
would go some way to improving the efficiency with which payments
were processed. The number of staff working on payments had been
increased, a set of uniform contracting rules had been implemented,
and the number of payments to be made under each contract had
been reduced. It was expected that these measures would begin
to address the problem of late payments.[93]
45. It must be remembered that Phare and Tacis are
not development programmes, although the Tacis programme does
disburse some ODA, and we can only hypothesise on the extent to
which funds allocated to Phare and Tacis which remain undisbursed
would have been allocated to other more poverty-focussed programmes
within Category 4. What is clear, however, is that funds appear
to have been repeatedly allocated to the Phare and Tacis programmes
which, for whatever reason, have been unable to disburse those
resources. This demonstrates an unacceptable over-emphasis on
political priorities during budget allocation discussions, with
a lack of attention to whether the money could be spent effectively,
or indeed whether it could be disbursed at all.
46. As has already been noted, our primary concern
in this inquiry is the allocation of official development assistance,
rather than the official aid of the Phare and Tacis programmes.
We are therefore particularly concerned to note the poor record
of underspends by the MEDA programme, which became significantly
greater during the period 1995-97, when the budget was increased
at a rapid rate, as is demonstrated in Figure 2. A Commission
Report on the Implementation of the MEDA programme during the
period 1995-97 reported that "for the period 1995-97, cumulative
payments have reached ECU 417 million, or 26.7 per cent of commitments
made over the same period."[94]
The Court of Auditors report on the Financial Year 1997 shows
that during 1997, the MEDA programme committed 98 per cent of
its budget for commitments, but disbursed only 64 per cent of
its budget for payments. The Report went on to suggest that
an increase in the level of funding for the MEDA programme would
only serve to exacerbate existing problems.[95]
Despite this fact, the 1999 Preliminary Draft Budget proposed
by the Commission included only a minute cut in the budget
6.7 million ECU out of 1,149.7 million ecu, less than one per
cent of the budget.
Figure 6: Difference between annual budget for
payments and actual payments for EC Cooperation with Asia and
Latin America (ALA), 1993-97 (Million Ecu)
Sources: General Budgets of the EC 1994-98,
Draft General Budget 1999.
47. When we met Mr Enrico Cioffi, Director-General
DGIB, which manages both the MEDA and ALA programmes, he told
us that the ALA programme would not be able to absorb any further
funds, and that it was therefore not possible to increase the
proportion of ODA being spent in that region.[96]
We have evidence which directly refutes this. The result is that
money remains unspent which could have been directed to Asia,
which contains 950 million of the 1.3 billion people in the world
who live on less than $1 a day. Figure 6 shows that, in fact,
the ALA programme has a record of budgetary implementation which
far exceeds that of the MEDA programme. In 1997, for example,
the ALA programme committed 99 per cent of the available appropriations
for commitments, and disbursed 93 per cent of its budget for payments,
which was unique among all the external action programmes in that
it set appropriations for payments at a level higher than the
budget for commitments. Clare Short told us in evidence, "I
think it is absolutely untrue to say Asia lacks the capacity to
absorb [an increase in its budget]. Asia is a very big place.
It is a very sophisticated continent in which we have very big
programmes."[97]
We agree with Clare Short's analysis. Despite this, the 1999 Preliminary
Draft Budget, proposed by the Commission, suggested a cut in the
budget for the ALA programme.[98]
We therefore support DFID's call for a decrease in the
allocation of resources to the MEDA programme, with a corresponding
increase in the budget for the ALA programme.[99]
48. Philip Lowe, Director-General of DGVIII, pointed
out to us that the budgetary discipline, or lack of it, evident
in the EC was far below the standard expected of its peers. He
suggested that the EC must adopt such procedures: "that is
we forecast a budget which we plan to meet 100 per cent and we
tell the member states at the beginning of the year how much the
contributions shall be and we stick to it and we do not take any
more or any less than what we say at the beginning of the year
... that is the normal budgetary mechanism of every national administration,
and by the way it is the normal budgetary mechanism which other
parts of the Commission respect."[100]
49. The excessive underspends in so many of the
Community's external programmes reveal a Commission unable to
manage and disburse its resources but unwilling for political
reasons to take the necessary budgetary action. In the light of
such underspends, we agree with the Government that there should
be no increase in Category 4 funds in the new Financial Perspective.
The Commission should concentrate on managing its current level
of funding and on distributing those funds more generously to
the poor.
50. Over recent months, serious allegations of
fraud and financial mismanagement within the Commission have been
raised. These have referred in particular to the MEDA and ECHO
budget lines. This is a matter of great concern to the Committee,
and we await with interest the results of current European Parliamentary
investigations. We are not surprised, however, to see such concerns
emerging from a Community where there are huge discrepancies between
political priorities and administrative capacity, over-commitment
of funds to programmes which cannot disburse them effectively,
and serious delays in the payment of some accounts.
77 Evidence, p.3 Back
78 Evidence,
p.3 Back
79 Q222 Back
80 Official
Journal of the European Communities 'Court of Auditors: Annual
Report concerning the Financial Year 1997' C349 vol. 41 1998 (English
Edition) p.91 Back
81 Q44 Back
82 Evidence
p.3 Back
83 Q25 Back
84 Q222 Back
85 OECD
DAC Development Cooperation Review Series No. 30, 'European Community',
1998, para 0.42 Back
86 OECD
DAC Development Cooperation Review Series No. 30, 'European Community',
1998, para 333 Back
87 Q43 Back
88 OECD
DAC Development Assistance Review Series No. 30, 'European Community',
1998, para 302 Back
89 Annex
ppl-li Back
90 OECD
DAC Development Assistance Review Series No. 30, 'European Community',
1998, para 302 Back
91 Evidence,
p.10 Back
92 Evidence,
p.98 Back
93 Annex
p.li Back
94 Commission
of the European Communities, 'Implementing MEDA, 1996-97 Report',
COM(1998)524, Oct. 1998, p.9 Back
95 Official
Journal of the European Communities, 'Court of Auditors: Annual
Report concerning the Financial Year 1997' C349 vol. 41 1998 (English
Edition) Back
96 Annex
p.xlv Back
97 Q266 Back
98 Preliminary
Draft General Budget of the European Communities for the Financial
Year 1999, Overview, 1998, p.8 Back
99 Evidence
p.10 Back
100 Q143 Back
|