Select Committee on Culture, Media and Sport Minutes of Evidence


Memorandum submitted by Sport England

SECTION SIX—DISCUSSION OF KEY ISSUES

  50  This section of the submission discusses a number of key issues which have been raised in recent months:

  50.1  proposals for the provision of a warm-up facility;

  50.2  value for money comparisons related to World Athletics at Wembley and other options; and

  50.3  the monitoring of progress against the funding agreement.

WARM-UP FACILITIES

  51.  In its Report of 13 May 1999, on Staging International Sporting Events, the Committee was concerned about the proposals for a warm-up facility for major athletics events (see para 134 of the Report).

  52.  The original brief required the provision of a warm-up facility. Provision for warm-up facilities was a weakness in nearly all bids for the project. One bid proposed the use of existing facilities distant from the stadium, whilst three bids proposed the use of temporary facilities on the car park (including Wembley). It was generally recognised that the allocation of land adjacent to the stadium would be problematic—land is at a premium, and warm-up facilities conflict with the need to provide car parking space, or to capitalise on higher value regeneration opportunities.

  53.  Furthermore, the British Athletic Federation could not provide a definitive view on the specification required for the warm-up facility, nor indeed criteria for its location in relation to the stadium. This was the result, in part, of their consideration of recent athletic events where the warm-up facility had been distant from the stadium.

  54.  During the negotiations with the FA and WNSL on the terms of the Lottery Funding Agreement, it was agreed that the warm-up facility would not be provided as part of the stadium development. This was because at that time, UK Athletics had identified Copelands School as an acceptable location for thewarm-up facility for the World Athletics Championships, with its legacy being a community facility (school and community programmes). In this context, the Government confirmed to WNSL and the FA, that they should not have to pay for warm-up facilities.

  55.  In July 1999, the Government established a Task Force for Wembley, to develop a regeneration framework for the area around the stadium. This includes an assessment of the feasibility, costs and funding possibilities for options for the warm-up facility. Four options have been under consideration, including the Copelands School site, and a decision was due to be made in the near future. Sport England has co-ordinated the input of the BOA, UK Athletics and DCMS to ensure that an agreed sports view is developed.

  56.  The four options are:

  56.1  Copelands School—this option could have been developed at a cost of £2.4 million. It is 850 metres from the stadium, and would have required an agreed transport strategy to ensure smooth transfer of athletes to the stadium. It would have been acceptable for the World Athletics Championships, but not for the Olympic Games. The main advantages were cost, and the potential to act as a legacy for school and community sports programmes;

  56.2  Sherrins Farm—immediately south of the stadium, separated from the stadium by the Marylebone-Birmingham railway line cutting. Cost—£7.6 million. Difficulties included potential planning problems, and whilst acceptable for both World Athletics and the Olympic Games, it would not have provided the same legacy potential as Copelands School;

  56.3  Stadium Car Park—cost £12.2 million, inclusive of land acquisition. Adjacent to the stadium, with the advantage of direct and secure access to the stadium. Suitable for both World Athletics and Olympics, but difficulties would have included the impact on car parking for the stadium, and land acquisition; and

  56.4  South East Corner—cost £15.4 million, inclusive of land acquisition. Adjacent to the stadium, with the advantage of direct and secure access to the stadium. Suitable for both World Athletics and Olympics, but difficulties would have included land acquisition. This option would have been favoured by the Task Force as it would have been consistent with plans to improve the stadium access corridor from the North Circular Road. SRB funding had already been allocated to this corridor improvement.

  57.  A further issue relates to the debate regarding the need to provide the warm-up facility on a temporary or permanent basis. The main argument in favour of the permanent option is that the facility is then available for the Olympic Games. However, if its principal use is for Word Athletics in 2005, then it could be provided on a temporary basis, and then released for development after the event. This would reduce the cost to the event considerably (construction cost is estimated at £800,000, plus site preparation).

  58.  Since the Committee Report on Staging International Sporting events was published in May 1999, therefore, considerable progress has been made:

  58.1  Four options have been identified and agreed by the sports organisations involved—Sport England, BOA, UK Athletics, and DCMS;

  58.2  The options have been evaluated by the Task Force, in terms of feasibility and cost. The Task Force have a preferred option, and are in the process of taking this forward in co-ordination with their overall strategy; and

  58.3  There are a range of cost options open for athletics bids based upon the need for proximity to the stadium, the need for a permanent as opposed to a temporary facility.

VALUE FOR MONEY COMPARISONS ON CAPITAL COSTS

  59.  It has been reported that the cost of the new Wembley Stadium is high in comparison with other recent stadium developments. However, the total cost quoted for Wembley is inclusive of site acquisition, planning obligations allowances, fees, financing costs, and items added to the brief such as a proposed visitor attraction, hotel and office accommodation. The costs are similar on a per unit (cost per seat) basis, when compared like for like with Cardiff, Paris and Sydney.

59.1  New Wembley £3,178 per seat;
59.2  Cardiff£3,031 per seat;
59.3  Stade de France£3,351 per seat;
59.4  Stadium Australia£3,144 per seat.

SPORT ENGLAND MONITORING

  60.  Throughout the negotiations with the FA and WNSL on the terms of the LFA, Sport England has sought to ensure that its key objectives for the project have been delivered. In addition, Sport England has secured a substantial commitment from football to the project, substantially in excess of the FA starting position.

  Sport England, through its funding agreement with WNSL and the FA, has extensive rights to monitor the project. These are rigorously enforced to ensure that the stadium is developed in accordance with the terms of the LFA. These rights include:

  61.1  Ability to audit WNSL with access to all papers, documents, correspondence, accounts and files. Full rights of audit access are protected for the National Audit Office, Parliamentary committees, and the DCMS.

  61.2  Ability to attend all meetings of WNSL (other than those solely with their legal advisors), including observer status at the Board.

  61.3  Requirement for WNSL to meet a series of development conditions set out in the agreement.

  61.4  Monthly review meetings with WNSL to monitor progress against the milestones and to identify issues which need to be resolved.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 8 February 2000