The wider site and the warm-up
track
30. For the National Stadium to have its desired
impact and for major events to be staged at Wembley, there is
a need for far more than the Stadium itself. As Mr Banks put it,
summarising his reply to an Adjournment debate on Wembley Stadium
in June 1998:
"It is not just about
building a new National Stadium; it is about redeveloping the
whole area around Wembley. You cannot just put a new National
Stadium into that mess which is Wembley at the moment."[112]
31. The problems of the present site were all too
apparent during this Committee's visit to Wembley Stadium on 14
April 1999. They were set out to us clearly by WNSL, as reported
in the published notes of the visit:
"Mr Stubbs raised the
issue of a future Olympic bid. If such a bid were launched, the
bidding team may well wish to see further facilities developed
around the National Stadium. However, no organisation or agency
appeared to be taking responsibility for such a development or
for preserving the opportunity to create such a development in
the future. No assessment of what further facilities would need
to be built had been undertaken, nor had any indication been given
of how they would be financed or when they would be developed."[113]
Later the same day Mr Stubbs held a meeting with
Brent Council. The next day he summarised the outcome to us as
follows:
"Increasingly, both
ourselves and Brent see it as a Government responsibility to make
sure there is an appropriate environment for the National Stadium,
appropriate in the sense of world athletics, World Cup, Olympics
and just a general setting of a national stadium".[114]
32. During our visit on 14 April 1999, Mr Stubbs
also drew our attention to the fact that there was no secured
site for a warm-up track, an essential requirement for the World
Athletics Championships and for the Olympics.[115]
We observed in our Report the following month that "the lack
of coordinated thought given by public bodies to the needs of
major events at Wembley Stadium is typified by the doubts which
still surround the provision of a warm-up track".[116]
In its submission in January 2000, Sport England explained that
"provision for warm-up facilities was a weakness in nearly
all" the original bids for the site of the National Stadium.
Three bids, including that from Wembley, proposed the use of temporary
facilities on a car park.[117]
London International Sport argued that provision for a warm-up
track should have been made in the original land purchase.[118]
Sport England stated that the warm-up track was excluded from
the eventual Lottery Agreement because UK Athletics had identified
a suitable location 850 metres from the Stadium with a legacy
as a community facility. According to Sport England, "the
Government confirmed to WNSL and the FA that they should not have
to pay for warm-up facilities".[119]
33. In our Report on Staging International Sporting
Events we concluded that "the planning process provides an
opportunity to establish an environment and infrastructure surrounding
the Stadium which would be appropriate to a new National Stadium
and which might contribute to Wembley's development as a potential
Olympic site".[120]
We stressed the need for urgent coordination of Government involvement
with the project.[121]
Conclusions
34. The conclusions of this Committee about the wider
site in May 1999 reflected a broader theme of the Report. We stated
that we were "greatly concerned at the apparent lack of strategic
thinking in the approach to the project by the English Sports
Council and the Government".[122]
More generally, we argued the case for stronger Government leadership,
to impose strategic coherence, to engage all Government Departments
concerned with events and to provide the focal point for decision-making
on matters of national importance. We recommended the designation
of a Minister in the Cabinet Office as Minister for Events and
argued that, along with the Manchester 2002 Commonwealth Games,
Government and public sector involvement with the Wembley Stadium
development "should be at the very top of the in-tray of
the Minister for Events".[123]
35. We reiterate those comments now in order to demonstrate
that our conclusions in this Report are not based simply on the
benefit of hindsight. In the light of subsequent developments
and the more detailed evidence we have received, it is possible
to reach fuller conclusions about developments before May 1999.
It is evident that a Stadium project that was originally conceived
for events sponsored by the governing bodies of three sports was
greatly complicated by the addition of potential Olympic ambitions.
The uncertainties which surrounded and still surround those Olympic
ambitionsabout whether the BOA proposes to make a bid,
about whether the Government is minded to give the necessary support
to make such a bid worthwhile, about whether the BOA would choose
Wembley as the focal point of the bid and about whether any bid
has a realistic prospect of successmade all parties concerned
with the project weaker in their response to the complication
than would have been desirable. The conceptually sound project
for a National Stadium was threatened by the Olympic dimension
and by the lack of strategic leadership.
73 HC (1998-99) 124-II, p 144. Back
74 Evidence,
p 67. Back
75 HC
(1998-99) 124-II, Q 510. Back
76 HC
Deb, 3 March 1997, col 500W. Back
77 Evidence,
pp 130, 10. Back
78 Evidence,
p 2; Q 352. Ten bids have been submitted for the 2008 Olympics.
Two of the cities in question are Paris and Seville, IOC Press
Notice, 2 February 2000 ( available at www.olympic.org). Back
79 Evidence,
p 2. Back
80 Evidence,
p 1. Back
81 Q
8. Back
82 Evidence,
p 130. Back
83 HC
(1998-99) 124-II, Q 108. Back
84 Ibid,
Q 83. Back
85 Evidence,
p 132. See also Evidence, pp 3, 10; Q 3. Back
86 Q
124. Back
87 Evidence,
p 131. Back
88 Evidence,
p 137. Back
89 HC
(1998-99) 124-III, p 250; HC (1998-99) 124-II, p 28; Evidence,
p 121. Back
90 Q
50. Back
91 QQ
184, 298. Back
92 Q
224. Back
93 Evidence,
pp 58, 68. Back
94 Evidence,
p 2. Back
95 Evidence,
pp 3, 131; QQ 10-11, 14, 20. Back
96 Q
126; Evidence, p 58. Back
97 The
Financial Times, 8 December
1999. Back
98 Q
1. Back
99 Evidence,
p 11; HC (1998-99) 124-II, Q 108. Back
100 Evidence,
pp 3, 4. Back
101 Evidence,
p 9. Back
102 Evidence,
pp 11-13. Back
103 Evidence,
pp 10-14. Back
104 Evidence,
p 6. Back
105 Q
238. Back
106 Evidence,
pp 62, 67; Q 234. Back
107 HC
(1998-99) 124-II, p 145. Back
108 Evidence,
p 137. Back
109 Evidence,
p 56. Back
110 HC
(1998-99) 124-II, Q 447. Back
111 Evidence,
p 58. Back
112 Q
102. See HC Deb, 29 June 1998, cols 123-130. Back
113 HC
(1998-99) 124-I, Annex 4, para 9. Back
114 HC
(1998-99) 124-II, Q 465. Back
115 HC
(1998-99) 124-I, Annex 4, para 7. Back
116 HC
(1998-99) 124-I, para 134. Back
117 Evidence,
p 69. Back
118 Evidence,
p 120. Back
119 Evidence,
p 69. Back
120 HC
(1998-99) 124-I, para 137. Back
121 Ibid,
para 140. Back
122 Ibid,
para 138. Back
123 Ibid,
paras 118-129. Back