Letter from MOD on Resource Accounting
and Budgeting
In your letter of 17 December 1998, you requested
a number of documents relating to Resource Accounting and Budgeting.
I am sorry that it has taken some time to assemble the documents.
You will find enclosed:
Resource Accounting Policy Manual (RAPM). JSP
472[3].
Departmental Programme Plan Version 6.0[4].
New Zealand Defence Force Half Yearly Report[5].
The RAPM is an evolving document and as such,
is under constant review. The next formal update is due in June
1999. But the current version remains a live document that informs
the Department's accounting process. Copies of the Treasury's
RAPM can be purchased from the Stationary Office. I understand
telephone orders can be made on 0171 873 9090, or for general
enquiries, call 0171 873 0011.
The MOD Programme Plan sets out the projected
plans for each element concerned with the introduction of RAB
and includes the Trigger Point milestones.
The New Zealand Defence Force Half-Yearly Reort
illustrates how another Government is presenting output costed
information. Unfortunately we do not have the reports from other
countries introducing RAB such as Australia. Additional information
about the range of countries introducing RAB or producing RAB
style reports, is contained in the Treasury publication "Whole
of Government Accounts, July 1998", a copy of which is,
I understand, in the House Library.
When it comes to other documents which you request,
I am unable to provide them. I am sure you will understand that
documents such as Colin Balmer's letter to the Treasury and the
NAO input, constitute internal and inter-departmental discussion
documents, and as such are not normally made available to Select
Committees. Nothwithstanding this, I appreciate that it would
be useful to you and the Committee to have some information on
the Trigger Point Strategy and Stage 1 Approval. Consequently,
I have also enclosed a memorandum from the Department that covers
this area.
13 April 1999
IMPLEMENTATION OF RESOURCE ACCOUNTING AND
BUDGETINGTRIGGER POINT 1
INTRODUCTION
1. In response to concerns expressed by
the Committee of Public Accounts (PAC) about departments' Resource
Accounting and Budgeting (RAB) implementation progress, the Treasury
introduced a formal review process which requires departments
to achieve agreed criteria at specified "Trigger Points"
during the transitional period leading up to 2001-02.
2. Four Trigger Points (TP) have been agreed:
TP 1involving departmental
PFOs and the National Audit Office (NAO) providing assurances
about departments' accounting policies and systems by December
1998;
TP 2an assessment of
departments' data for the 19992000 Opening Balance Sheet
by June 1999;
TP 3requiring the NAO
to provide an audit report on departments' dry-run 1998-99 resource
accounts during autumn 1999;
TP 4requiring departments
to produce "shadow" resource-based Estimates for 2000-01
by May 2000.
3. It is the Treasury's intention to report
progress against the Trigger Points regularly to Parliament. The
last such update was provided in a Treasury Memorandum on RAB
to the PAC, the Procedure Committee and the Treasury Committee
on 12 January 1999.
TRIGGER POINT
1
4. There were five criteria that each department
had to achieve for TP 1:
An illustrative Departmental
Resource Account (DRAc);
A Departmental Resource Accounting
Policy Manual;
A preliminary view from the
NAO;
A letter from the PFO confirming
readiness of systems and processes.
5. All Government departments secured Trigger
Point 1 approval by the end of December 1998. The following paragraphs
provide a summary of MOD's progress against each of the TP 1 criteria
and significant points identified by the NAO and the Treasury.
ILLUSTRATIVE 1998-99
RESOURCE ACCOUNTS
6. The Treasury and the NAO were generally
content with the format of the accounts, having been closely involved
in developments during the course of 1998. Illustrative figures
were included to facilitate understanding of the account.
7. Both the Treasury and the NAO did express
concerns about the department's ability to produce the final resource
account schedule, "Schedule 5Statement of Departmental
Outputs". However, as the PFO explained in his letter:
"We have recognised for some time
that we would not have fully integrated output costing systems
in the early years [of RAB] as the priority has been the introduction
of basic accounting systems. To address this, an interim system
has been developed to allow basic apportionment of resource consumed
by Departmental output. A more sophisticated system will be introduced
when the full cost communication is operational."
8. Other NAO comments on the resource account
centred on the ability of the department to populate some of the
supporting notes to the account. The NAO also observed that the
Department was dependent on the Treasury for further advice on
accounting policy issues.
DEPARTMENTAL RESOURCE
ACCOUNTING MANUAL
(DRAM)
9. The NAO are broadly content with the
manual noting that it provided very good coverage of most areas
of accounting policy and practice likely to be faced by the Department.
Both the Treasury and NAO acknowledged however, the manual will
need to be updated as outstanding policy issues are agreed with
the NAO.
THE PROJECT
PLAN
10. A high level plan for MOD's implementation
project was passed to both the NAO and the Treasury, a copy is
enclosed.[6]
This included plans to address issues emerging from dry-running
the accounting systems and processes in 1998-99 as well as the
work planned to cover areas of concern highlighted by the NAO.
These work programmes aim to ensure that major issues are resolved
in time to meet the criteria for Trigger Point 2 at the end of
June 1999.
11. The NAO commented that the strength
of the planning process, and monitoring of progress against plan,
has been a major factor in the Department securing the level of
overall progress that has already been achieved.
SUPPLY/FEEDER
SYSTEMS
12. The most serious concerns expressed
by the NAO are reserved for the supply systems. In the main these
systems predate the RAB initiative. The NAO believe however, that
the systems problems are capable of being solved and that, in
time, they should adequately support the preparation of resource
accounts.
13. The PFO recognises that supply systems
provide a major area of concern, but added in his TP1 letter,
"significant work is in hand both to ensure data can be passed
efficiently to user TLBs and to improve the quality of the numbers."
NAO PRELIMINARY VIEW
14. In summary, the NAO noted there would
be risks for both the dry-run resource accounts for 1998-99 and
the live accounts for 1999-2000. But, given the good progress
the Department continues to make and the fact that areas of concern
are being addressed, the NAO were content for MOD to proceed to
Trigger Point 2.
TREASURY'S
LETTER OF
CONFIRMATION
15. The Treasury considered that the Department
had a good understanding of outstanding issues and was on track
to clear them in time to enable the criteria for Trigger Point
2 to be met at the end of June 1999.
16. Finally, Andrew Likierman, HM Treasury
Head of the Government Accountancy Service, in a separate letter
to Colin Balmer commented that, "the immense effort and determination
to achieve results, not only in changing hugely complex systems
but also in spreading knowledge has been truly impressive."
He added that TP1 agreement should not merely be noted but clearly
marked.
13 April 1999
3 Not printed. Back
4
Not printed. Back
5
Not printed. Back
6
Not published. Back
|