Select Committee on Defence Written Evidence


Letter from the MoD concerning the article published in the Observer Newspaper, 23 January 2000

  An article appeared in the Observer newspaper on 23 January. It made three principal claims. First, a high proportion of RAF aircraft are grounded; secondly, the RAF is short of pilots; and thirdly, a new laser guided bombing system does not work properly and is significantly over budget.

  The article drew on information given in answer to a Parliamentary Question asked by the Rt Hon Menzies Campbell QC MP in December 1999. The answer gave details of levels of aircraft serviceability across the RAF at a snapshot in time (8 am on 25 October).

  The total Tornado GR1/4 fleet allocated to front line units at that time was 108. Of these, 87 were either fully serviceable (ie immediately ready to fly—53) or on first line servicing (ie undergoing maintenance for faults normally rectified within hours 34). This number of Tornado GR1/4 aircraft far exceeds any number we have deployed on operations. It was also sufficient to enable the RAF to meet its operational, training and immediate readiness requirements, as it always does on any given day. Indeed, in the days leading up to the snapshot, an analysis of performance in support of operations found that over 99 per cent of tasked missions had been flown successfully.

  66 Tornado GR1/4 not allocated to front line units were undergoing either Mid-Life Upgrade (MLU), which is incorporating new weapons, avionics and night vision systems to provide a major uplift to Tornado's capability, or other major servicing.

  As for the claims about the Tornado MLU, this is referring to the Thermal Image and Laser Designator (TIALD) element of the laser guided bombing system. This precision bombing capability is being incorporated as part of the Tornado MLU. The aim of the overall MLU programme is to enhance Tornado's ability to find and successfully attack its targets in all weathers and at night. The overall MLU programme is on schedule and within cost. 50 upgraded aircraft have been delivered so far with the balance due by early 2003. Technical problems have been experienced with TIALD, but these are close to resolution and an operational clearance is expected by the middle of February.

  Finally, figures on junior officer fast jet shortages were given to the Defence Select Committee during an evidence session on 19 January. As at 1 December 1999, the requirement for flying and ground appointments was 554, while the actual trained strength was 459, giving a shortfall of 95 (17.1 per cent). The shortfall is being addressed in a number of ways, primarily to increase retention, including the introduction of schemes to counter the pulling factor of civil airline recruiting. These are known as LINKUP and the RAF Civil Airline Recruiting Scheme, under which MoD pays for RAF pilots to gain a civil license in exchange for a commitment to remain in the RAF until at least 38. Other options being pursued include restructuring of additional pay. It is hoped that the combination of measures will substantially improve retention. The RAF will continue to monitor the position and introduce new measures if appropriate to do so.

  Recruitment for RAF pilots remains buoyant. The RAF has more than met its recruiting target this year, recruiting 208 against a target of 187. The numbers completing training and entering service are being increased from 45 in the current year to 60 by 2002-03.

2 February 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 10 February 2000