Select Committee on Defence Written Evidence


Further Memorandum from the Ministry of Defence (19 April 2000)

BOWMAN

  Bowman will provide a secure, robust data and voice communications system in support of land operations, to replace the Clansman combat radio and the HQ infrastructure element of the Ptarmigan trunk system. It will also play a key role in the MoD's Battlespace Digitization initiative. A risk reduction programme is currently under way under a contract with Archer Communications Systems Ltd. It is planned to seek approval to place the first supply contract in 2000.

OPERATIONAL REQUIREMENT

  1.  Bowman is required to provide a secure combat communications system for the Army and elements of the other Services, in support of land and littoral operations. It will serve as the primary means of voice and data communication for tactical level operations, where operations are characterised by mobility and are undertaken by many individual platforms and by dismounted individuals. The system will, therefore, be based on radio communications that can operate without relying on fixed infrastructure. As well as man-portable versions, Bowman will be an integral part of the communications fit of major equipments such as the Challenger 2 Main Battle Tank, the attack helicopter and warships. In addition to radios, Bowman will also provide a local area sub-system. That sub-system will distribute information within key platforms and around deployed divisional, brigade and unit level headquarters, as well as providing the inter-connection between Bowman and other military and civil communications systems. A management information system will enable operational deployment of the system to be planned and managed.

  2.  The requirement for Bowman was first endorsed in 1988 as a two-stage project: stage 1 to provide a replacement for the Clansman capability with a simple vehicle harness, and stage 2 to enhance this system to allow for increased data and interoperability requirements. Approval was given to enter a competitive Project Definition phase for stage 1, PD1, and a simultaneous Feasibility Study phase for stage 2, FS2. The latter concluded that the system demonstrated in PD1 would not support the data demands of the number of information Systems that would be in service with Bowman and which would be needed to support the digitization programme. The requirement was therefore revised to include additional capacity for data transmission and the computing infrastructure to support new information systems. These included the local area sub-system, an additional radio, known as the High Capacity Data radio and computer terminals. FS2 also demonstrated that it would be lower risk for the communications harness for Bowman, known as the Vehicle Integrated Communications Distribution System, to be provided by the Bowman prime contractor rather than provided by the MoD as a separate project. This system was, therefore, merged with the Bowman requirement in 1997.

TRADE-OFFS

  3.  Close liaison with the prime contractor has led to agreement on a series of cost/capability/time trade-offs. In particular, the delivery of capability will be staged; elements of the system that are assessed to require prolonged development to reduce risk will be delivered after the in-service date. Some detailed reductions in functionality have also been agreed. Ruggedized off-the-shelf, rather than bespoke, computer terminals will be used. Where feasible, Bowman will be certified to less stringent US Military Build Standards rather than to UK Defence Standards, which increases the degree of commonality with the US systems on which some elements of the system will be based. More limited protection against jamming and interception of transmissions will be accepted for some radio types.

NUMBERS

  4.  The number of combat radios required depends primarily on the force structure and numbers of vehicles and other platforms in service. The current assessment is that about 55,000 man pack and vehicle mounted radios will be procured. Bowman radios would be installed in some 23,000 vehicles, 43 major ships and some 450 battlefield and support helicopters and transport aircraft. These numbers are subject to review.

STRATEGIC DEFENCE REVIEW

  5.  The Strategic Defence Review highlighted the importance of effective command control and communication Systems and confirmed the requirement for Bowman. Force changes arising from the SDR are likely, however, to have an impact on the numbers of equipment required and the programme for converting units.

MILITARY CAPABILITY

  6.  As the primary means of communication at the tactical level for land operations, Bowman will be used across the spectrum of conflict, for all missions and at all scales of deployment. Bowman will be central to the command and control, and therefore the effective deployment, of forces used for military tasks ranging from disaster relief to regional conflicts.

EQUIPMENT TO BE REPLACED AND IN -SERVICE DATE, ISD

  7.  Bowman will replace the Clansman family of combat radios, which has been in service since the 1970s. It will also replace those elements of the Ptarmigan trunk communication system within tactical headquarters, that is vehicle borne HQs at divisional, brigade and unit, ie battlegroup level.

  8.  Bowman was originally endorsed against an ISD of December 1995. In 1993 this was revised to June 1999 as a result of budgetary constraints and an increased understanding of the technical complexity of the project gained from the Phase 1 Feasibility Studies. During the competitive PD1 phase, the ISD was revised to April 2001 for budgetary reasons. Following the completion of PD1, the ISD was slipped to March 2002 as a result of the revised procurement strategy and the redefinition of the ISD to reflect the delivery of a true operational capability. In the light of an assessment of the technical risk remaining in the programme, the ISD was further slipped in December 1999 to late 2003/early 2004, subject to a Main Gate approval. Since August 1998 the ISD has been defined as the date when a brigade HQ and two battle groups are equipped and capable of deploying on operations other than war. The Clansman family of combat radios and the relevant elements of Ptarmigan will be progressively removed from service over the period 2003-2010, as Bowman is introduced.

  9.  It has been possible however, to plan for the early delivery of a small but significant operational capability that previously was tied to the delivery of the whole system. Through the application of SMART Procurement principles, in particular incremental procurement, the Personal Role Radio, a short range, non-secure tactical radio for use at section level will now be procured in advance of the delivery of the main BOWMAN system with initial deliveries expected to start by the end of 2001.

PROCUREMENT APPROACH

  10.  Development of the system was carried out by two competing consortia: YEOMAN, led by Siemens Plessey Systems, now BAE Systems and Racal; and CROSSBOW led by ITT UK Ltd. Following international competition in 1993, contracts were placed with these two consortia for both PD1 and FS2. The opportunities for international collaboration at system level were also assessed at that time, but the timing of the UK's requirement did not coincide with that of any of our major NATO partners. However, it was decided that the contractors providing other nations' new combat radio Systems would be invited to bid for Bowman.

  11.  Following completion of PD1 in late 1996, the competing consortia announced their intention to form a joint venture company, known as Archer Communications Systems Ltd, ACSL, to bid jointly for the Bowman supply contract. This resulted in a review of the procurement options open to the MoD, namely continuing with either one of the consortia, continuing with Archer or finding a new prime systems integrator. A revised, single source, procurement strategy for Bowman and the remainder of the risk reduction work was approved in March 1997, and a risk reduction contract was placed with Archer in August 1997.

  12.  Work on defining the supply phase is continuing linked to the incremental introduction of technology and the staged delivery of capability. Before the first supply contract is awarded, further risk reduction work, known as Package 0, is being undertaken to ensure the necessary confidence in performance, time and cost of the programme for the Main Gate approval and before contractual commitment. The contract for Package 0 was placed with Archer in October 1998 at a value of £185 million.

  13.  In order to achieve best value for money for sub-system solutions, Archer is required to hold competitions wherever possible. Some 60% by value of sub-contracts will be subject to competition. Where sub-contract competition is not possible, the MOD applies NAPNOC, no acceptable price, no contract, conditions.

***

ALTERNATIVE PROCUREMENT OPTIONS

  14.  The options of upgrading Clansman or procuring an austere off the shelf solution were examined at the time of the review of procurement options in 1997 but were considered to be less costs effective options for meeting the requirement. However, Archer has not performed well on the programme to date, and the way forward is under consideration. Archer remains the preferred supplier but studies have been set in train with potential alternative providers (Computing Devices Canada and Thomson CSF) in order to protect the department's value for money position. Collaboration was also considered, but not found to be viable, see paragraph 10.

 EXPORT POTENTIAL

  15.  There will be marketing opportunities in those countries operating VHF and HF radios bought from the selected Bowman suppliers, ITT and Racal, which might be upgraded using elements of the Bowman system, or in those countries which wish to improve their capability at Brigade level and below. The sophistication and cost of Bowman will limit the market for the total system but there will be scope for supplying parts in many countries.

INDUSTRIAL FACTORS

  16.  Of the procurement options considered in 1997, only Archer combined all aspects of design, manufacture, assembly, systems integration and support in the UK and would maintain a significant UK capability in all these areas. Archer revised their Joint Venture agreement earlier this year, with BAE Systems taking over the management role. Shareholdings were not changed. The impact of the potential purchase of Racal by Thomson is not yet clear.

SMART PROCUREMENT

  17.  The project is now following Smart Procurement principles, including a "partnering" approach with Archer. It will use technology and modules developed in Project Definition and for other customers. A contract strategy of incremental acquisition is proposed.

ACQUISITION PHASES

  18.  FS1, FS2 and PD1 have been completed. The award of the package 0 contract in October 1998 enables Archer to complete sub-system definition and subcontractor selection, prepare for and commence system integration, and prove the platform installation design process prior to full commitment to "Supply and Support". It was planned to award the first of the production contracts, in late 1999. However, following a submission from industry in March 1999, an affordability review and some redefinition of the project, was carried out. The principal area of risk leading to this delay is the integration of sub-systems supplied by a number of different sub-contractors. A further key risk to the timescale for contracting for installation design certification and conversion in over 200 platform types with complex existing design rights. Progress has been made. Archer has selected ITT to supply the VHF radios, which are the heart of the Bowman system. Improvements have been made in the company's management arrangements for the project. Further progress in reducing the risks will need to be demonstrated. If we can agree with the prime contractor an acceptable programme in terms of performance, time and cost we intend to place a production contract at the end of the year.

MILESTONES AND COSTS

  19.  Key milestones now in prospect for this project are:


Approval for Package 1   end 2000
Placement of Package 1  end 2000



  Cost summary Approved stages as at 31 March 1999, at 1999-00 prices.


Breakdown of procurement costs
Development
Production
Total

Current estimate of costs
341
341
Estimate of costs at MOD approval
132
132
Difference
+209
+209


  Reasons for difference: costs resulting from changes to the scope of work undertaken, +£12M; accounting adjustment, +£1M; slippage of PD1 work, +£5M. Extension of Risk Reduction phase +£196M. Expenditure at 31 March 1999 was £185M. Reduction in forward buy of GFE in advance of Main Gate submission -£5M.

***

The years of peak expenditure are likely to be 2002-03 and 2003-04 onwards.

  The revised ISD for Bowman has resulted in additional costs of £9M to run on Clansman longer than originally planned.

IN -SERVICE SUPPORT

  20.  There are two aspects to Bowman support: the provision of initial spares and facilities to support operations, which will be provided with the prime equipment and installations; and on-going support that enables reprovisioning corrective action and contractor support to ensure sustainability of the deployed system. The planned single Supply and Support contract will encompass both aspects. The level of support required is being determined using integrated logistic support principles. The importance of reliability and spares availability, and their impact on equipment sustainability, is reflected in the draft contract. The use of existing spares and equipment, where appropriate, has been mandated. Training is being addressed under the tri-Service Training Needs Analysis, which will identify the recommended training methodology, including training media.

  21.  The Bowman conversion programme is a major task that will be carried out over a period of eight years. Conversion will be by operational grouping, principally brigade; there is therefore a vital link between conversion planning and the Army's Formation Readiness cycle. Units will be converted in their "other tasks" year. The Bowman Fielding Plan addresses the requirement to provide support to both the new system and that being replaced. Dual Clansman and Bowman training will be needed at certain locations.

FRONT LINE, STORAGE AND RESERVES

  22.  In accordance with the principles of whole fleet management Bowman equipment not assigned to the front line will in effect be held in reserve, although there will be no formal war reserve. Spares to support Bowman will be held in storage, under arrangements still to be decided.

INTEROPERABILITY

  23.  National interoperability for land operations will be achieved, since all elements of the three Services that take part in the land or littoral battle will be equipped with Bowman International interoperability with other nations is more difficult. The intention is that Bowman should meet currently agreed and likely future NATO standards. Use of extant US national protocol standards was considered, but was not judged to offer an acceptable degree of protection for the lifetime of Bowman. A standard for encryption has been agreed by certain countries, including the US and UK, and will be adopted by Bowman. Standards developed for Bowman could be made available for adoption for the next generation of US tactical radio communications, or as future NATO standards.

DISPOSAL OF EQUIPMENT TO BE REPLACED

  24.  Defence Export Services will consider the most appropriate disposal route, sale or scrap, for Clansman equipment that is no longer required. Relevant parts of Ptarmigan will be retained as spares to support the Ptarmigan elements remaining in service.

IN -SERVICE LIFE

  25.  Bowman is planned to be in service for at least 25 years.

DEVELOPMENT POTENTIAL

  26.  Given the pace of change in information systems technology, it is likely that there will be developments that require technology insertion over the course of Bowman's service life, and the system is being designed accordingly.

April 2000

FUTURE CARRIERS—CVF

  The decision in the Strategic Defence Review to purchase two large aircraft carriers, to replace the three Invincible-class carriers from around 2012, is being taken forward and competitive contracts for the CVF Assessment Phase were awarded in November 1999 to BAe Land and Sea Systems, now BAE Systems, and Thomson-CSF. The first part of this phase, Analysis of Options, is examining a wide range of carrier design options, to reflect the options for the Future Carrier Borne Aircraft, FCBA, see separate memorandum.

OPERATIONAL REQUIREMENT

  1.  The Strategic Defence Review concluded that the ability to deploy offensive air power will be central to future force projection operations, and that aircraft carriers can provide valuable flexibility in a range of operational circumstances. They can also offer a coercive presence, which may forestall the need for war fighting. The SDR recognised that there is an increasing likelihood of future operations being conducted by forces far from their home bases. In such operations, host-nation support, including access to suitable air bases, cannot be guaranteed, particularly during an evolving regional crisis or the early stages of a conflict. The SDR concluded that there is a continuing need for Britain to have the capability offered by aircraft carriers. Our three Invincible-class carriers were designed for Cold War anti-submarine operations. The intention, announced in the SDR, is to plan to replace these with a new class of larger and more capable carriers, known as the CVF, Carrier Vessel Future, class.

  2.  In accordance with the Smart Procurement model, CVF is following a two-stage approval process that involves an Initial and Main Gate. Initial Gate approval, utilising the Smart Procurement model, was given in December 1998 for an Assessment phase. Studies being undertaken in Assessment will examine the User Requirement Document and develop it, using cost/capability trade-offs to produce an affordable and achievable Systems Requirements Document. The objective is to build a replacement for the current carriers that has an increased emphasis on offensive air operations and is capable of operating the largest possible range of aircraft in the widest possible range of roles.

TRADE-OFFS

  3.  Trade-offs between cost/capability and time/capability are integral to the Assessment work.

NUMBERS

  4.  The original plan was to replace the three Invincible-class carriers with three 20,000 tonne vessels. Operational analysis demonstrated, however, that it would be more cost-effective to procure two large carriers, each capable of carrying up to about 50 aircraft. The SDR also saw advantage in future carriers being capable of carrying more fixed-wing aircraft than the current vessels, in order to be able to contribute more effectively to the support of operations on land and at sea.

STRATEGIC DEFENCE REVIEW

  5.  The SDR assessed the requirement for aircraft carriers within the overall requirement for an offensive air capability. It concluded that "there is ... a continuing need for Britain to have the capability offered by aircraft carriers" and the emphasis for replacement carriers should be on "increased offensive air power, and an ability to operate the largest possible range of aircraft in the widest possible range of roles"—The Strategic Defence Review, Supporting Essays, pages 6-6 to 6-8.

MILITARY CAPABILITY

  6.  The CVF will deploy offensive air power in support of the full spectrum of future operations, including force projection as a central component of the maritime contribution to joint operations.

 EQUIPMENT TO BE REPLACED AND IN -SERVICE DATE

  7.  The planned out of services dates for HMS Invincible Illustrious and HMS Ark Royal are 2010, 2012 and 2015 respectively. The SDR introduced no changes to this programme of withdrawals from service. The first CVF is scheduled to enter operational service in 2012 and the second in 2015. The in-service date for CVF is defined as the "Operational Date Materiel Assessment", which is the date at which it will be accepted as fit for entry into the operational fleet.

PROCUREMENT APPROACH

  8.  The CVF procurement strategy is based on competition and prime contractorship, with clear and unambiguous output requirement specifications. Although we intend that the ships should be built in the UK, prospective prime contractors are from the UK and France.

  9.  In accordance with the Smart Procurement model, the project is following a two-stage approval process. Invitations to tender for the Assessment phase were issued in January 1999 to six potential prime contractors—BAe Lockheed Martin, Boeing, Marconi Electronic Systems, Raytheon, and Thomson-CSF. Responses were received in May from two teams; the first led by Thomson-CSF of France with BMT Defence Services Ltd and Raytheon systems as major sub-contractors; the other by BAe Land and Sea Systems with Marconi Electronics Systems as a sub-contractors. Following tender evaluation and face-to-face meetings with industry it was judged that the bids offered the basis for robust and effective competition and contracts were awarded to both teams in November 1999. BAe and Marconi subsequently merged to form BAE Systems, and in February 2000 Lockheed Martin joined the Thomson-CSF team.

  10.  The Assessment phase comprises two main stages. The first, analysis of Options, involves the examination of carrier design options and will help inform the decision, expected in late 2000/early 2001, on the type of aircraft to meet the Future Carrier Borne Aircraft, FCBA, requirement. Progress to the second stage of Assessment will be subject to satisfactory completion by BAE Systems and Thomson-CSF of stage one, based on a review of their performance, and the timeliness and quality of their deliverables. The second stage will involve detailed work to determine the carriers' design parameters and to reduce technological risk, informed by the choice of FCBA. It will culminate in the Main Gate approval decision, planned for 2003, to down-select to one preferred prime contractor to proceed to Demonstration and Manufacture of two carriers. The Demonstration phase will begin with the design of a virtual prototype by the selected prime contractor, using computer-aided technology. The intention is to achieve, so far as possible, a freeze on a mature design before construction begins.

  11.  A cost model is being developed to generate whole-life cost estimates for CVF and this will be populated with data from industry. In the event of competition collapsing, this model would be used as the basis for No Acceptable Price, No Contract negotiations.

ALTERNATIVE PROCUREMENT OPTIONS

  12.  During Assessment, a wide range of carrier and aircraft options, including conventional take-off and landing, short take off and vertical landing, and short take off but arrested recovery will be considered. As part of this work and following normal practice, the cost of life-extending the three existing carriers, by10 years, will be assessed to provide a baseline against which all the options can be evaluated.

COLLABORATION

  13.  It is too early to be specific about the prospects for collaboration. Some informal discussions have taken place with the US, Spanish, French, and Italian navies to identify any common ground in carrier replacement programmes or requirements. At present, whole ship collaboration would appear unlikely to be a viable option, but collaborative opportunities will be reviewed during Assessment, especially for equipment and systems.

EXPORT POTENTIAL

  14.  It is unlikely that this project will lead directly to whole-ship sales, although the commercial marketing of CVF design skills and production technology could benefit UK industry. Much of the ship's equipment could have export potential. Industrial Participation proposals will be invited, as appropriate, for offshore content of the proposed solution.

INDUSTRIAL FACTORS

  15.  In accordance with government policy for the construction of warships, the CVF will be built in a UK shipyard. Industrial factors will be taken into account in the selection of a contractor.

 SMART PROCUREMENT

  16.  The CVF programme will adopt a range of Smart Procurement techniques including a greater emphasis on identifying, evaluating and implementing effective trade-offs between system performance, whole-life costs and time; the adoption of incremental acquisition for areas such as the combat systems; the use of off-the-shelf equipment and commercial standards, where appropriate. An Integrated Project Team, IPT, is managing the project under the leadership of an industrialist recruited in an open competition. In accordance with Smart Procurement, what would previously have been Feasibility and Project Definition stages have been combined into a Single Assessment phase, with increased investment at this stage to achieve early risk reduction. The two consortia have been encouraged to be innovative throughout the project.

ACQUISITION PHASES

  17.  A number of small-scale pre-feasibility studies were completed prior to the award of the assessment contracts, described at paragraph 9. A risk register will be maintained throughout the life of the project as the core of an integrated risk management system. It will contain both MoD and contractor inputs from the Analysis of Options studies undertaken by industry and will be the focus for work during the Risk Reduction phase. These will help to provide confidence in the data to be assessed in the Combined Operational Effectiveness and Investment Appraisal that will support the Main Gate submission to proceed with Demonstration and Manufacture.

MILESTONES AND COSTS

  18.  CVF milestones, as currently planned, are shown in the table below.

User Requirements Document endorsement and Initial Gate approval December 1998
Issue ITTJanuary 1999
Start AssessmentNovember 1999
FCBA downselectionlate 2000/early 2001
Systems Requirement Document endorsement and Main Gate approval late 2003
Order datelate 2004
Contract acceptance date2011
ISDs2012 and 2015

  19.  We envisage a total acquisition cost for the two carriers of around £2 billion, including combat system and initial support costs, but excluding the aircraft. The peak years of expenditure are likely to be between 2008 and 2012. Costs incurred so far, including pre-feasibility studies, total just over £5 million.

 IN -SERVICE SUPPORT

  20.  We plan to investigate the let of a design/build/through-life support/disposal contract as one package. Collaborative support arrangements are unlikely.

  21.  Manning levels will be based on work by human factors designers, to achieve a balance between automated and manual tasks, and by training needs analysis, in accordance with the RN training equipment strategy. The size of ship's complement is planned to be about the same as for the Invincible class. Contractors will be tasked to propose the most efficient manning strategies for their designs, which will be examined during Assessment.

  22.  All logistic support associated with CVF will be considered as a direct cost to the project, with an emphasis on avoiding expenditure on new infrastructure. The maintenance management system will be required to integrate with other MoD logistic systems and to take account of emerging developments in IT. Innovative support solutions will be examined, using Integrated Logistic Support methodology to minimise costs throughout the ship's life.

  23.  Contractor Logistic Support CLS, will be examined for some or all the maintenance and logistics. The benefits of CLS include a strong focus on reliability for initial designs; better standards of availability, reliability and maintenance; and an incentive to the contractor to design and build systems that minimise support costs. One option to be considered is the adoption of best practice in supply chain techniques, to minimise MoD ownership of spares, by contracting for agreed spares availability from industry. CLS options for up to 30 years will be examined during Assessment.

  24.  The upkeep cycle of the CVF will reflect the vessels' modern design, and developments in upkeep practice such as "reliability centred maintenance" rather than lengthy and expensive refits. This will enable availability requirements to be met by only two carriers.

FRONT LINE NUMBERS

  25.  Both CVF will be assigned to the front line.

INTEROPERABILITY

  26.  The aim is to maximise the interoperability of the CVF with the greatest possible range of UK and allied aircraft and with other carriers, to the extent that this can be achieved cost-effectively. Clearly, the type of aircraft chosen as FCBA will be a major factor in determining the degree of interoperability with other nations, especially within NATO. The issue will be explored further during Assessment with due regard for the developing FCBA business case.

DISPOSAL OF EQUIPMENT REPLACED

  27.  Prospects for the sale of the Invincible class to other nations will be explored in due course.

IN -SERVICE LIFE

  28.  Each CVF is planned to have an in-service life of 30 years.

DEVELOPMENT POTENTIAL

  29.  The CVF programme is closely linked with the FCBA and Future Organic Airborne Early Warning programmes.

EUROFIGHTER

  Eurofighter is an agile fighter aircraft that will serve as the cornerstone of the RAF's fighting capability from the early years of this century. The 232 aircraft we plan to acquire will replace the Tornado F3 and Jaguar in air defence and offensive air support roles. Eurofighter is being developed in a collaborative project with Germany, Italy and Spain. Contracts for the production of the first tranche of 148 aircraft, of which 55 are for the RAF, were signed in September 1998 and the UK expects first deliveries in June 2002.

OPERATIONAL REQUIREMENT

  1.  The original European Staff Target for the Eurofighter—then European Fighter Aircraft, EFA—was signed in Rome on 11 October 1984, by France, Germany, Italy, Spain and the UK. The nations' air forces agreed a requirement for a new fighter aircraft to enter service in the 1990s. EFA was to be agile and designed to fulfil air defence, including air superiority and interception, and air to surface roles. France attached equal importance to both roles; all other nations, while wishing to retain good air-to-surface capability, recognised air-to-air as the conditioning role. EFA was to be capable of intercepting, fighting in air combat, and destroying a wide range of aerial targets including cruise missiles, remotely piloted vehicles and drones at a threat level expected in the mid 1990s and beyond, as well as attacking enemy airfields and enemy surface forces. EPA was to be able to operate in the electronic warfare environment of a late 1990s European scenario by day and by night, in all weathers for air defence and in poor visibility and low cloud-base for its air-to-surface role. The numerical superiority of hostile air forces was to be compensated for by EFA's superior quality and operational flexibility. Low observability and survivability were key design goals, as were reliability, maintainability and testability.

  2.  Following a 1984-85 feasibility study, the other four nations found it impossible to reconcile all their requirements with those of France, which wanted a lighter aircraft that would not provide the overall operational capability required by the others. France accordingly withdrew from the programme in August 1985. The key parameters agreed by the other nations—an unstable, delta-winged aircraft, with canards, to have a "basic mass empty" of 9.75 metric tonnes, a wing area of 50 square metres and two engines each producing a static sea level thrust of 90 kilonewtons—were incorporated in the European Staff Requirement, ESR, and signed by the four Chiefs of Air Staffs in December 1985.

  3.  The collapse of the Warsaw Pact and the re-unification of Germany led to a "reorientation" of the programme. The ESR needed to be updated to reflect the radically changed political and military situation in Europe after 1989 and to address the requirement for the year 2000 and beyond, taking account of EFA development work. Amendments were embodied in the European Staff Requirement for Development, ESR-D, of a European Fighter 2000—Eurofighter—signed on 21 January 1994. The ESR-D acknowledges that specific threats are no longer predictable in detail, but stipulates that a future European fighter aircraft must be capable of operating effectively in a variety of roles and theatres.

TRADE-OFFS

  4.  ***.

NUMBERS

  5.  The original requirement of the four partner nations was for a total of 765 aircraft—250 for Germany, 165 for Italy, 100 for Spain and 250 for the UK. The current requirement is for 620 aircraft—180 for Germany, 121 for Italy, 87 for Spain and 232 for the UK. Germany, Italy and Spain reduced their numbers during the reorientation. The UK reduced its own requirement following studies that concluded that the UK required 232 aircraft to meet its operational commitments. The UK is now committed contractually to the Tranche 1 production of 55 aircraft. Future production contracts would commit the UK to 89 and 88 aircraft for Tranches 2 and 3 respectively.

STRATEGIC DEFENCE REVIEW

  6.  The SDR confirmed our commitment to acquiring 232 Eurofighter aircraft. The acquisition of Eurofighter will provide a step change in the RAF's ability to achieve air superiority and provide air defence. Its multi-role capability will also allow it to fulfil the ground attack roles now performed by Jaguar.

MILITARY CAPABILITY

  7.  Eurofighter will bring a significant increase in our air superiority capability as it replaces the Tornado F3. It will also provide a true, adverse weather, multi-role capability. This will allow it to be employed in the full spectrum of air operations from air policing to peace support through to high intensity conflict.

EQUIPMENT TO BE REPLACED AND IN -SERVICE DATE

  8.  The Eurofighter will replace the Tornado F3 and Jaguar, the out of service dates for which are 2010 and 2008 respectively. The currently forecast in-service date for Eurofighter, defined as the date of the delivery of the first aircraft to the RAF, is June 2002. This represents a delay of 42 months against the original ISD of December 1998. The slippage is attributable to procurement delays caused by reorientation, delays in signature of the Memoranda of Understanding for the Production and Support phases, some 22 months slippage, and technical difficulties resulting from the application of complex technologies required to enable the equipment to meet the original Staff Requirement, some 20 months slippage. The definition of the ISD for Eurofighter relates to procurement factors and was agreed internationally some years ago.

***

 PROCUREMENT APPROACH

  9.  Early work in each participating country by defence contractors working to their national governments was co-ordinated under Memoranda of Understanding between the partner nations. Full collaborative development was launched in 1988. Collaborative Production Investment and Production including Initial Support, was launched by the partner nations at the end of 1997, following signature of further MoUs, and contracts were signed in January 1998. Contracts for production of the first tranche of 148 aircraft, including 55 for the RAF, were signed in September 1998.

  10.  Eurofighter development and production are undertaken by two consortia. Eurofighter GmbH, and Eurojet GmbH. Eurofighter comprises BAE Systems from the UK, DASA from Germany, Alenia from Italy and CASA from Spain, and is responsible for developing and producing the airframe, avionics and the other aircraft systems, and for the integration of the EJ200 engine. The latter is being developed and produced by Eurojet GmbH, comprising Rolls-Royce from the UK, MTU from Germany, Fiat from Italy and ITP from Spain.

  11.  The purchasing arrangements are described in further detail in the table at Annex.

COLLABORATION

  12.  Government oversight of the programme is exercised through the Board of Directors of the NATO Eurofighter and Tornado Development, Production and Logistics Management Agency, NETMA, which carries out day to day management of the international contracts. The Agency has some 300 staff and an annual budget of about 75 million DM. Funding for the agency is shared in accordance with the respective participation of each nation in the Eurofighter and Tornado programmes. The UK contribution is about 35%. The UK national project office element of the programme is managed by an Integrated Project Team (IPT), which co-ordinates UK input to the programme and provides national oversight, currently comprises some 111 staff. Its annual budget is about £5 million.

  13.  Development work and costs are shared on the basis of nations' planned production off-takes, as declared in 1987, giving the UK and Germany 33% shares each, Italy 21% and Spain 13%. Production Investment and Production work and cost share are based on aircraft off-take declared at the start of these phases in 1997, giving the UK some 37.5% share, Germany 29%, Italy 19.5% and Spain 14%.

  14.  Seven MoUs commit the four collaborative partners to the various phases of the programme and its management.

EXPORT POTENTIAL

  15.  Eurofighter GmbH has identified several potential customers for Eurofighter in Europe, the Middle East; the Pacific Rim; and South America. In Europe, Greece has stated that it will buy up to 90 Eurofighters subject to satisfactory negotiations, and Norway is close to completing its evaluation of Eurofighter and F16 bids. Export sales could run to several hundred aircraft over many years but there will be competition from a variety of American, French and Russian combat aircraft types.

INDUSTRIAL FACTORS

  16.  The Eurofighter project is fundamental to maintaining an industrial capability within the UK for the design and build of advanced military aircraft. As the only suitably qualified UK firms to undertake the development manufacture of advanced fast jet aircraft and engines, BAE Systems and Rolls Royce were the natural choice as the major UK partners. Similar factors influenced the selection of contractors by our collaborative partners.

SMART PROCUREMENT

  17.  The Eurofighter programme embraces several Smart Procurement features. The UK has an integrated project team with collocated operational requirements, procurement and logistics staff. The design standard of delivered aircraft will follow an incremental acquisition path, with the first aircraft being delivered to an initial standard—to allow early training—with full standard delivered later to meet the declaration of operational capability. The prices negotiated with industry have taken account of efficiency improvements by industry: arrangements have been agreed to share further efficiency benefits beyond those already included in the price. Elements of the production contracts include firm, non-revisable prices for the five years and, for subsequent years. Variation of Price formulae based on Producer Output Indices. There is provision for liquidated damages and the right of termination. Much effort is being put into developing a partnership with industry to support the aircraft in service.

ACQUISITION PHASES

  18.  There are four distinct phases within the Eurofighter programme: pre-development, development, production and support.

  19.  Pre-development comprised a number of activities. Following early concept studies and various efforts to establish a collaborative programme, two key demonstration activities were completed by the UK before development: the Experimental Aircraft Programme, an airframe programme primarily aimed at proving the feasibility of unstable flight control concepts, and the XG40 engine demonstrator programme at Rolls Royce. The results of these demonstrators and associated studies, and similar work by the other nations, were harmonised in a definition, refinement and risk reduction phase that ran from the end of 1985, when the four nations signed the MoU covering this phase, to 1988.

  20.  The main development contracts were signed in November 1988 and amended in November 1995.

  21.  The Eurofighter production contract strategy is based on an "umbrella contract" that secures maximum prices for all production investment and the total order of 620 aircraft. Commitments against this contract are made as a series of supplements against fixed prices within the overall maximum price. The umbrella contract and the first supplement covering production investment were signed in January 1998. The second supplement, covering the production of the first tranche of 148 aircraft, was signed in September 1998.

  22.  Integrated logistic support procedures were embedded in the programme from the outset, to ensure that adequate attention was given to support issues throughout the development phase. Concurrently with the umbrella contract, the first two support procurement contracts were let, following agreement that industry would ensure that support is available when the first aircraft is delivered.

  23.  A reliability maintenance panel meets every three months to monitor progress against the reliability plan. In-service demonstration is also part of the programme.

  24.  The current assessment of risks associated with the timely completion of the programme highlights the integration of the avionics within the overall weapon system and the achievement of incremental increases to avionic functionality. Risk management processes in industry and the MoD, and contractual incentives for industry, aim to ensure that these risks do not impact adversely on delivery.

MILESTONES AND COSTS

  25.  The four nations signed the Full Development MoU and consequent contracts in November 1988. MoUs for Production Investment/Production and Support were signed in December 1997. These were followed by signature of the Production Investment/Production and Support overarching contracts in January 1998 and the first tranche of production contracts in September 1998. The first aircraft is scheduled to be delivered to the UK in mid-2002. Dates for the two further production tranches have still to be determined.

  26.  Details of expenditure of 31 March 1999 and further expenditure in prospect are provided in the table at Annex.[1]

  27.  In the event of late delivery, the production contracts with Eurofighter GmbH and Eurojet GmbH both include provision for liquidated damages up to a maximum of 3% of individual weapon system value. All interim payments made prior to delivery are subject to the achievement of technical milestones. If a milestone is not achieved, payment is withheld.


IN -SERVICE SUPPORT

  28.  Support of Eurofighter is being managed collaboratively to reduce life cycle costs. MoUs and International Framing Agreements aim to ensure that all elements of the project are taken forward on an agreed international basis. Costs are shared in proportion to the aircraft off-take of each nation. This is the first major international project to apply integrated logistic support, ILS, procedures, thus enabling all aspects of logistic support to be optimised. Emphasis is being placed on partnership with industry to define the most cost-effective solution.

  29.  The Eurofighter IPT is maintaining close liaison with all three RAF Commands throughout the planning process to ensure that the end users contribute to the development of support policy and have a clear understanding of the developing support concepts. The IPT is also ensuring that, where it is cost effective, maximum use is made of existing support capability; and also that, where possible, any new generic support equipment being procured is compatible with Eurofighter.

  30.  The most obvious potential bottleneck is the support infrastructure at the Main Operating Bases, MOBs. As each MOB converts, there will be a short period where both Tornado F3 and Eurofighter will be required to operate together and, as each maintenance facility is converted, the Tornado F3 would potentially be left unsupported. This risk will be overcome by ensuring that the MOBs provide mutual support during the conversion phase. Another potential problem that has been identified is the maintenance of minimum manning levels at the front line whilst training the first tranche of Eurofighter tradesmen, and building up the Operational Conversion Unit and the first squadrons. Such potential difficulties are being addressed by a series of working groups. All are currently considered to be manageable.

FRONT LINE, STORAGE, AND RESERVES

  31.  The active RAF fleet of Eurofighter will be 137 aircraft, covering the seven front-line squadrons, the Operational Conversion Unit, OCU, and the Operational Evaluation Unit. Each squadron will have one in use reserve and the OCU will have two in use reserves giving a total of nine. The remaining aircraft allow for assumptions of attrition and overall use of the aircraft over the 25 year life of the aircraft, with the last aircraft being scheduled for delivery in 2014. The fleet once in steady state will be managed around engineering requirements, such as scheduled servicing and modification programmes.

INTEROPERABILITY

  32.  Interoperability is fundamental to Eurofighter design. The Eurofighter programme has adhered to Standard NATO Agreements and protocols to ensure Eurofighter's compatibility with current and future systems, both operational and logistic.

DISPOSAL OF EQUIPMENT TO BE REPLACED

  33.  The aircraft being replaced will be at the end of their productive lives and will probably be scrapped.

IN -SERVICE LIFE

  34.  Eurofighter is planned to be in service for 25 years.

DEVELOPMENT POTENTIAL

  35.  Unlike previous programmes, where major enhancements were incorporated via a major in-service upgrade, we shall, following Smart Procurement principles, establish a programme for through-life evolution of the RAF Eurofighter fleet. The aim is to acquire and incorporate emerging technology, on an incremental basis, to maintain the capability of the weapon system. Partnership between the MoD and industry will provide the necessary expertise and focus to enable us to identify, prioritise and pursue modifications to Eurofighter that balance operational effectiveness, life cycle costs and obsolescence issues.

  36.  Adapting Eurofighter for operations from aircraft carriers, or "marinising", is one of the possible solutions being considered to meet the requirement for the Future Carrier Borne Aircraft. Various Eurofighter derivatives are also among the options being considered to meet the requirement for Future Offensive Aircraft Systems.

April 2000


1   p 60. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 6 July 2000