Select Committee on Defence Thirteenth Special Report



ANNEX

This memorandum constitutes the Government's response to the House of Commons Defence Select Committee's 10th Report on Major Procurement Projects. This is the second report in which the Committee has conducted an annual survey of major procurement projects, with a view to measuring the success of the Smart Procurement Initiative (SPI), and we welcome the Committee's decision to scrutinise the Ministry of Defence (MoD)'s procurement in this way. We share the Committee's hope that their report will inform the Commons' debate on equipment procurement scheduled for this autumn. We note the Committee's intention to focus on the Future Carriers, inter alia, in its next report on this topic.

The Government welcomes the Committee's report, which we believe gives an objective view of the latest progress on major procurement projects. We acknowledge the Committee's criticisms of MoD's past procurement performance, which we are seeking to address through the SPI. We therefore welcome the thrust of the Committee's overall conclusion, i.e. that it can see signs of smart procurement delivering tangible results, even at this stage. MoD has now successfully put in place the machinery for change in its acquisition practice. The SPI, launched to drive out cost and time overruns from the procurement programme, will have a greater effect on programmes that are in their early stages, and consequently it will take time, indeed many years, for the full benefits to be achieved. However, the NAO findings, following their audit of the Major Projects Report 99, in common with the Committee's report, showed that there are signs of early successes from the application of the SPI principles even though the launch year was only completed on 2 May. As the Initiative has more time to demonstrate its worth, particularly on new projects, the Government is confident that the record on bringing major equipment projects to fruition on time and within budget, meeting the needs of the armed forces of the future and saving taxpayers' money, will radically improve.

BACKGROUND

(Paragraph 9) The test of the success of this at first sight risky decision to loan a senior civil servant [Mr John Howe] to a foreign-owned competitor for UK defence contracts will be whether the competitive pressures are in fact maintained, and whether there are identifiable consequential benefits in terms of price and innovative technical solutions, in the Carrier, Bowman and other programmes. These gains will have to be significant if this act of apparent altruism is to be shown to be actually self-interested. The MoD's case would be more persuasive had it been able to secure a reciprocal arrangement with the French defence department.

In our view Mr Howe's secondment to Thomson CSF was not an act of altruism; as Sir Robert Walmsley, Chief of Defence Procurement, explained to the Committee, it was taken on the basis that it would clearly be in the interest of obtaining best value for money to enhance competition within the defence electronics industry in the UK. It is also in keeping with the Government policy of broadening the experience of Senior Civil Servants through increased interchange with the private sector. The question of reciprocal arrangements with the French defence department therefore did not arise.

BEYOND VISUAL RANGE AIR TO AIR MISSILE (BVRAAM)

(Paragraph 15) Once any debriefings are completed, we expect the MoD to provide us with its more detailed assessment underlying its choice for the [Meteor] missile.

As the Committee notes, the Chief of Defence Procurement has not yet formally debriefed Raytheon on why its bid was not successful, so it would be improper at this stage to go into more detail on the technical reasons for preferring Meteor. These debriefings usually take place after contract signature, expected to be around the end of this financial year. We will then be in a position to provide the Committee with more information.

(Paragraph 16) The incremental approach to capability acquisition is that now favoured by the MoD's smart procurement initiative, . . . and uncertainties about the cost [of ERAAM+] should not have been a determining factor against it. If MoD is to get the full benefits of smart procurement, it will have to develop the tools and techniques it will need to assess rigorously the costs and benefits of bids which offer different routes to the full capability sought, so that it can fully demonstrate the financial case for the choices it makes.

The BVRAAM competition was decided on the basis of a balanced judgement of operational capability, missile performance, affordability, and overall value for money. We concluded that Meteor best meets our needs over the life of the Eurofighter aircraft, and represents best value for money. The overall performance of Meteor will ensure that Eurofighter will deliver the air superiority that is key to success in many military operations.

We agree that incremental acquisition is one of the tenets of Smart Procurement, and we have developed and used the tools to compare different paths to reach the full capability requirement—most notably the Combined Operational Effectiveness and Investment Appraisal (COEIA), which uses discounted cash flow to assess bid costs on a comparative basis. Careful comparisons were therefore made between the costs of the different procurements routes. However, in the case of the incremental ERAAM+ proposal, the uncertainties were not confined solely to the costs likely to be involved. Indeed, our assessment of both bids necessarily took account of a wide range of non-financial risks and uncertainties. We therefore have confidence that our decision to prefer Meteor was robustly based. But we are, of course, always on the lookout for better estimating and evaluation techniques applicable to both the conventional and incremental procurement approaches.

(Paragraphs 21, 22) The in-service date for the missile . . . is now expected to be 2008. When we asked CDP what confidence he had in the current in-service date for BVRAAM, he explained that such predictions were now based on a 90% confidence level . . . The cautious definition of the missile's target in-service date may be realistic, particularly in view of the technological challenges that will have to be overcome, but in BVRAAM's case it is a date that must be met if Eurofighter is to fulfil its potential.

The Government shares the Committee's view of the importance of keeping momentum behind the project to bring Meteor into service at the earliest opportunity. We have conducted a comprehensive risk assessment of Matra BAe Dynamics' proposed programme. A single contractor will have the responsibility of delivering to time and cost, and we will be putting in place a taut contractual regime, with its emphasis on demonstrable milestones and incentivised performance. We assure the Committee that these factors, together with the UK's strong project management role, give the Department very high confidence that the BVRAAM capability will be achieved within the approved time and cost thresholds.

The BVRAAM in-service date (ISD) of 2008 included in the Committee's report is the latest declared planning assumption prior to the selection of Meteor, as included in the NAO's Major Projects Report 99. 2008 is not the 90% confidence date referred to later in this paragraph; as described in the report, the 90% date is a prudent estimate, substantially after the date that the company is promising to deliver, which is used for planning and approval purposes. We aim to bring the missile into service in advance of the 90% date, to a timescale which will be set once the discussions with partner nations and the Prime Contractor have been concluded. This timescale will also be affected by the need to dovetail into the complex Eurofighter programme the integration of the missile onto the aircraft. We will be in a position to declare the set ISD at the time of contract signature.

(Paragraph 22) Eurofighter needs the BVRAAM capability to give it the air superiority for which it is designed. We therefore welcome the fact that MoD has now selected a missile and contractor . . . The Meteor missile has some clear advantages over its Raytheon competitor . . . Although the project is in its early days, it also offers the prospect of avoiding some of the problems which have plagued other European procurement collaborations, without arbitrary workshare divisions and with a clear project leadership role to be provided by the UK. The MoD needs to take advantage of that leadership role to keep momentum behind the project, including an early contract which will lock-in not just the contractor but also the commitments of our international partners.

The Government welcomes the Committee's recognition of the importance of a BVRAAM capability for Eurofighter, and of the advantages of choosing the Meteor missile to provide this capability. The Advanced Medium Range Air-to-Air Missile (AMRAAM) will provide Eurofighter with the capability required for its air superiority role until Meteor comes into service.

The Committee has recognised in its report the more imaginative and robust approach to procurement now in place and exemplified by the BVRAAM programme. We accept the Committee's conclusion that the UK must exploit its leadership to keep momentum behind this collaborative project, and in bringing together an experienced Integrated Project Team, including industry representation, to manage the project through-life, we have sought to provide that clear leadership. We will be working very hard to secure delivery of this high performance missile ahead of schedule and within budget.

Meteor will be a Smart Procurement programme with incentives to reward good performance and discourage poor performance. The programme will be run in a partnership with industry that will place emphasis on managed risk and continued delivery of value for money, and gain-sharing potential will be kept under continuous review. A culture of open reporting and shared problem solving will be established, underpinned by the formal process of Earned Value Management which instils a structured management reporting discipline. In addition, as the Committee is aware, the contractor has agreed to a series of key technological milestones, failure to achieve which may lead to the termination of the contract with all money being returned to the Partner Nations.

Since the UK's decision, all our partner nations have written to the Chief of Defence Procurement welcoming the announcement and reconfirming their own commitment to the programme. Progress with the Memorandum of Understanding has been very good and contract negotiations with Matra BAe Dynamics are forging ahead; we expect to sign both around the end of this financial year.

(Paragraph 26) The MoD does not envisage Eurofighter having a ground attack role . . . The MoD has however already sunk £90 million into the cannon which has now been wasted. The savings from not using the gun would only be £2.5 million a year. Admiral Blackham believed that that was no reason to go on sinking more money unnecessarily. We are less convinced of the economic sense of this decision at this late stage of the aircraft's development, and we look to MoD in its response to this report to provide further explanation of its rationale for not using the cannon, and how a very close range engagement capability could otherwise be provided.

Unfortunately there are a number of factual errors in this paragraph of the Committee's report, emanating from mistakes in the transcript of evidence. We apologise for not having picked up these transcript errors at an earlier stage. Corrections are as follows:

  • we have spent £19M, not £90M, on procuring the gun. That this money has been spent is of course not an argument for spending more. Having now assessed that the gun is not needed, it is common sense that we do not continue to spend taxpayers' money on it.
  • the deletion of the gun will save more than £3.5M (not £2.5M) every year of Eurofighter's operational life in projected support costs. In addition, it has saved some £30M in the forward equipment programme. But we have deleted the gun not in order to save this money, but because a gun capability on Eurofighter is simply not required.
  • we do envisage an air-to-ground role for Eurofighter in the future, alongside other aircraft and the extremely capable Apache, as stated in our written evidence to the Committee. For this role, the aircraft would carry weapons such as Brimstone and Storm Shadow. However, it is correct that our priority for Eurofighter is an operational air-to-air role. With Tornado GR4 and Harriers continuing in-service for many years, there is less immediate need for Eurofighter to assume an air-to-ground role at its entry into service, and the relatively indiscriminate nature of gun firing means that the cannon is a far less appropriate or effective weapon for Eurofighter in its future air-to-ground role than precision-guided munitions.

The rationale for our decision to delete the requirement for the Mauser cannon on Eurofighter is set out in the written evidence provided to the Committee (Evidence p93, paragraph A4). A close range engagement capability will be provided by the Advanced Short Range Air-to-Air Missile (ASRAAM), which has a shorter minimum range than any previous missile. ASRAAM will provide a significant contribution to achieving and maintaining air superiority: it can be employed in the full spectrum of air operations from air policing to peace support through to high intensity conflict, and will provide Eurofighter with a substantial advantage against the foreseeable threat in short-range air combat. But to perform its operational role effectively, Eurofighter needs to be armed not with very short-range weaponry but with longer-range guided missiles such as Meteor.

SEALIFT

(Paragraph 28) The lesson of the Kosovo campaign remains that such deployments depend on a great deal of sealift being readily available. Having dedicated assets, such as the six Ro-Ro ships envisaged by the MoD, will be essential if the UK is to maintain that deployability in less favourable circumstances.

The Government welcomes the Committee's conclusion on the value of strategic sealift. The Committee rightly identifies the potential difficulties in securing suitable sealift in the necessary timescale to support operations, and at a reasonable cost. While early planning and chartering avoided problems in the Kosovo operations, as we stated in the recently published 'Kosovo: lessons from the crisis' pamphlet, 'in operations in future where we do not have similar time to prepare, a national strategic sealift and outsize strategic airlift capability will be essential.'

While, depending on the requirements of individual operations, some take-up of vessels from trade to assist in rapid logistics support may remain necessary in some circumstances, the provision of dedicated shipping for this task is the best way to give assurance that the Joint Rapid Reaction Force's (JRRF) deployment can be supported. In order to guarantee the service, which includes the transit of warlike zones, crew availability is also crucial and the requirement is therefore for crews to be under terms of employment which guarantee service in warlike zones (i.e. they are likely to be seamen eligible to be called out as sponsored reserves). This is the basis of the current competition for a strategic sealift service and would also accommodate the security considerations necessary because of the operational and financial value of the cargo.

In the interim period, the MoD continues to have available two chartered strategic lift vessels, SEA CRUSADER and SEA CENTURION, until their charter arrangements expire in January and April 2001 respectively. We intend to provide by charter within the coming months an interim service of three ships continually available, with an additional vessel available for periods of peak demand and crises. This interim service will be tailed off as a dedicated RoRo service becomes available, and extended should there be any slippage. The Alternative Landing Ship Logistics that are being procured will also add to the potential amount of sealift available to the MoD as well as enhancing our amphibious capability .

(Paragraph 29) We share the concerns that have been expressed in many quarters about the consequences of a decision to build the MoD's Ro-Ro ships abroad might have for the UK's shipbuilding capacities. We trust that the MoD's decision will recognise the wider industrial and strategic issues involved.

It is government policy that warships for the Royal Navy are built in British yards. However, the Ro-Ros are non-warlike vessels. For instance, their design will not be especially specialised; they will not be fitted with weaponry and they are not intended for operations in a battle zone. For non-warlike vessels, we are obliged to follow European Treaty and public procurement rules. These prohibit discrimination in favour of national industries in this type of contract. We have, however, within the bounds of fair competition and our EC obligations, ensured that UK shipbuilders are given the opportunity to compete for these contracts . The RoRo service includes support, service and manning of the vessels, as the requirement is for the provision of a shipping service rather than a simple design and build procurement. The value of the contract that is spent in the UK, wherever the ships are built, would be the majority of the price paid.

Beyond the Ro-Ros, MoD has a very much more substantial naval procurement programme of warlike vessels indicated in the SDR, including the Type 45 destroyer, Alternative Landing Ship Logistics, the larger aircraft carriers, the Future Surface Combatants, and already under construction, other programmes such as the Landing Platform Dock (Replacement), the new fleet tankers, the Astute submarines and the survey vessels. These programmes provide a secure long-term platform for the UK shipbuilding industry to increase its efficiency and to secure further export orders.

AIRLIFT

The long-term airlift programme

(Paragraph 31) Last month [May 1999] the Secretary of State announced that the MoD intended to acquire up to 25 A400Ms to satisfy its longer term airlift requirements. This is somewhat lower than the "up to 45" that had been subsumed in collaborative "requests for proposals" issued to Airbus. Admiral Blackham told us that the lower figure reflected the work done in his organisation to balance investment in air and sea transport. It is quite a dramatic reassessment, however, which has not been matched by any increase in the requirement for sealift.

As the Committee recognises in the same paragraph, airlift is needed to deploy lead elements of the Joint Rapid Reaction Force (JRRF), with heavy equipment following by sea. Therefore a re-evaluation of the rate of airlift deployment does not automatically imply an increase in the amount of sealift required. However, in this case there has been a clear evolution in the definition of the requirement.

We originally announced in December 1994 our intention of rejoining the Future Large Aircraft (FLA) programme. At that stage, we were considering the FLA as a replacement for the balance of the Hercules fleet (beyond the 25 C-130J announced at that time) and other possible air transport requirements; the judgement then was that this could lead to a requirement for between 40 and 50 FLA. Since that date, the UK's force levels and force structure, and assumptions about the type, size and speed of deployment which might be needed under various (themselves evolving) crisis scenarios, have all changed significantly - most notably with the development first of the Joint Rapid Deployment Force, and subsequently the JRRF concept and other conclusions of the 1997 Strategic Defence Review (SDR). The SDR also reached a new judgement on the level of investment needed in sealift, with its conclusion that we should increase the amount of strategic sealift required through the acquisition of four additional Ro-Ros. We were able to confirm 25 A400M, after further detailed operational analysis (based on greater knowledge of the proposed aircraft acquired during the competition process and considering the numbers of aircraft required for the programme's launch), as the necessary number to deploy the lead elements of the JRRF in the appropriate timeframe for the various scenarios in which that would be necessary.

(Paragraph 31) Airlift is needed to deploy lead elements of the MoD's Joint Rapid Reaction Forces such as the Attack Helicopter, with heavy equipment following on by sea - not just tanks and AS90 artillery, but also armoured engineering vehicles and bridge-launchers, and in its response to this report we invite the MoD to explain the circumstances in which lead elements of the JRRF will be able to operate without engineering support capabilities.

In many foreseeable situations, heavy engineering support of the kind the Committee mentions will not be necessary at all - for instance, in Sierra Leone, strategic airlift was used to deploy elements of the JRRF, but armoured engineering vehicles and bridge-layers were not required. For the more testing potential scenarios where heavy engineering equipment is required, such as medium scale war-fighting, the A400M's outsized lift capacity will enable it to carry much more of the heavy engineering support equipment required than was previously possible. With the capacity to carry loads that range from the Warrior and its derivatives, through fuel tankers, dump trunks and 15 ton cranes up to a 35 ton Royal Engineer plant semi-trailer, the A400M will significantly enhance engineering support capabilities in the early stages of such a deployment. This will allow the remainder of the heavy equipment to arrive in a timely fashion by sealift and thus provide full engineering support facilities.

(Paragraph 35) The MoD needs to keep the industrial implications of its A400M commitments under close review.

The Government accepts the Committee's recommendation. Our aim is to ensure broadly equitable work-sharing arrangements, without detriment to overall value for money. A key element of Airbus's successful record in meeting challenging delivery timescales is their system of relying on centres of expertise in successive programmes. Thus BAE SYSTEMS has become the Airbus centre of expertise for wing design. A400M is no exception and we expect Airbus Military to use the partner companies' strengths in the normal way: we factored this into the cost and risk assessments that underpinned our decision. BAE SYSTEMS stated during the competition that a successful launch of the A400M could be expected to create 3,400 direct skilled jobs (and 10,000 indirectly related jobs) in the United Kingdom, and we will continue to assess the impact of current and future programmes on the UK's defence industry.

(Paragraph 35) Cooperation between Rolls-Royce and Snecma to build the A400M engine could be a useful development but only if the result is a better and more cost-effective engine. Whatever engine solution is adopted, however, the decision must be clearly the result of fair competition, it should not be foreclosed by prior development choices, and the costs and benefits underpinning it must be completely transparent, both to the MoD and to this Committee.

Our aim is to ensure that Airbus Military Company makes the selection of the engine for A400M on a commercial basis, in accordance with the principles on which the Future Large Aircraft programme was founded. We recognise the benefits to be gained from competitive selection of the A400M engine and anticipate it resulting in a better and more cost-effective engine. We expect transparency from Airbus on the basis for the selection, and will continue to press for this.

THE SHORT-TERM AIRLIFT PROGRAMME

(Paragraph 39) We welcome the fact that the MoD has made a clear decision on its short-term and long-term airlift programmes. This is a real step towards providing the range and the depth of strategic lift that is needed to meet the operational demands envisaged by the Strategic Defence Review.

The Government welcomes the Committee's conclusion. The Strategic Defence Review (SDR) identified an urgent need to improve our strategic transport, to allow us to move more powerful forces quickly to an overseas theatre. With the 25 new C130J now entering service, and four C-17 from 2001, as well as existing airlift assets (e.g. Tristar), we will have a flexible fleet of aircraft capable of meeting the short-term strategic airlift requirement. The A400M at the end of the decade will enable us to meet the long-term requirement and provide more aircraft capable of tactical as well as strategic airlift.

(Paragraph 39) We recognise the compelling reality that providing a capability to carry a worthwhile heavy armoured force by air is a super-power capability and one that would not be a sensible use of the MoD's limited resources. This is properly the domain of sealift.

The Government welcomes the Committee's conclusion. As the Committee recognises, the ability of the C-17 to lift a Main Battle Tank is of limited operational benefit unless enough such aircraft are available for deployment by air of a coherent force of heavy armour. We could not afford that. Other European nations have made a similar judgement, reflected in the European Staff Requirement for the Future Large Aircraft, which did not specify the ability to carry Main Battle Tanks. The planned enhancements to the strategic sealift capability will help us ensure that the heavy equipment which may be needed to support units deployed forward by air can be delivered in a suitable timescale.

(Paragraph 40) In that context [that a capability to carry a worthwhile heavy armoured force by air would not be a sensible use of MoD's resources], we welcome the selection of the A400M for our long term airlift requirements, as an effective way of rapidly deploying the lead elements of the Joint Rapid Reaction Force cost-effectively. In the meantime, the introduction of the four C-17 aircraft from next year will give us an early and effective boost to our capabilities.

The Government welcomes the Committee's conclusion. The A400M represents an effective aircraft that will enable us to meet the long term airlift requirement, satisfying both strategic and tactical roles and at an affordable price - the programme will cost some £3.5Bn. The C-17s clearly meet the shorter-term requirement, and their introduction from next year will allow them to participate in the major exercise SAIF SAREEA 2 in Oman, and substantially increase the capability available for crisis deployment. The C-17 will be supported through Foreign Military Sales case contracts with USAF, and will be operated to USAF procedures, greatly aiding interoperability and with significant cost savings.

(Paragraph 40) What is welcome on this occasion, however, is that (we presume) the leased C-17s will be handed back when the A400Ms come on stream, and in the case of the C-17s a large part of the support infrastructure will be provided by the US (though on repayment terms). Furthermore, as a package these two strands of our airlift capability unusually offer the MoD the best of all worlds. They hold out the prospect of acquiring an effective aircraft for the UK's long term needs, which would improve and standardise this important European military capability, and could provide a possible vehicle for further consolidating the European defence industry. At the same time, the lease of the C-17s gives the Department an insurance policy, in that if the A400M remains on the ground the UK's capability need not. Airbus and our A400M partners would do well to take this on board as they endeavour to take the programme forward.

The Government welcomes the Committee's conclusion. The acquisition of A400M by the UK and its seven partner nations, who publicly confirmed their commitment in the Farnborough Declaration of 27 July, represents a great step forward in European military capability. Like sealift, strategic airlift has been identified as a critical capability shortfall by NATO's Defence Capabilities Initiative and is particularly important for the successful fulfilment of the EU Headline Goal. The UK's decision to purchase A400M will substantially enhance European and NATO capabilities in this area.

The decision by the UK and subsequently its partner nations to commit to the A400M has undoubtedly strengthened Airbus Military Company, sending a clear signal that Airbus is trusted to take on this key military project as a player in its own right in the European defence industry. To this extent the Government believes that the A400M programme has already contributed to further consolidation of the European defence industry, and acknowledges the potential for it to act as a possible vehicle for even more consolidation in the future.

Our current planning assumption is indeed that the C-17s will be returned to Boeing when the A400M has entered service. The Government is confident that A400M will be delivered on time and will provide the capability and effectiveness the RAF needs. The commitment of our seven partner nations in the Farnborough Declaration of 27 July to a total offtake of 225 aircraft is well above the threshold for the programme's viability. Using state of the art virtual environment techniques, Airbus Military Company have already been able to design and test the plane, and we are confident it will be available to meet our, and our partners', requirements. But we acknowledge the risks in developing and delivering a new aircraft design, which were considered in the selection process. If Airbus cannot offer us and our partners an affordable and manageable programme in the requisite timeframe we will look to purchase Boeing C-17 aircraft as an alternative. The Government agrees with the Committee that we retain a viable option should the A400M programme fail to meet expectations, and this and our continued involvement in the procurement process should ensure that Airbus' feet are kept to the fire.

BOWMAN

(Paragraphs 42, 43) [Bowman's] progress has been woefully slow, however, since the MoD first defined its requirement in 1988 . . . In dealing with the complexities of the technologies and the problems over competition, the planned in-service date has regularly slipped, and is now running eight years behind its original schedule . . . Bowman remains a very good example of the antithesis of smart procurement - with over-ambitious requirements, inadequate competition and a lack of clear leadership (though on industry's side more than the MoD's).

The BOWMAN programme has suffered from a number of problems, including technical difficulties, changing defence priorities, and industrial re-arrangements impacting on the procurement strategy. Since its introduction, the Smart Procurement Initiative has allowed us to deal with the problem in a controlled and managed way. The freedom that SPI gives to trade requirements in search of a more cost-effective solution enabled us to seek `fallback' options in case the Archer Communications Systems Limited (ACSL) bid failed. This revealed that there were realistic alternatives to ACSL that could be pursued rapidly. Given our decision to terminate ACSL's preferred bidder status, we have therefore been able quickly to reopen competition in search of value for money rather than stopping the programme and starting again from scratch, delaying BOWMAN for many more years.

(Paragraph 44) To replace the Clansman radios before the delivery of the mainstream Bowman system, the MoD is now running a competition to produce nearly 44,000 'Personal Role Radios' for the infantry. They will not greatly improve capabilities—their transmission will not be encrypted—but they will be an improvement on Clansman's poor reliability and maintainability.

Using the flexibility provided by the Smart Procurement Initiative (SPI), we decided to separate the procurement of the stand-alone Personal Role Radio (PRR) from the total BOWMAN requirement in order to deliver these radios earlier to the front line than otherwise would have been the case. PRR is not a replacement for Clansman, but is the introduction of a new capability not provided by Clansman, that forms part of the Bowman requirement. BOWMAN will introduce a range of services which Clansman cannot provide, including a secure voice and data service, electronic protection measures, increased security and significantly increased VHF and HF capability for all three services. We are currently running a competition to produce nearly 45,000 `Personal Role Radios' primarily for the infantry which will provide an important new capability which was not previously provided. Although these radios will not be encrypted, they will offer low probability of intercept and commercial levels of protection, and will provide a major improvement in tactical awareness and operations. Particulary in the street-fighting and similar operations envisaged for its use, where the operational value of intercepted data quickly diminishes, the new radios are intended to provide a less expensive and early contribution to part of the Bowman package.

(Paragraph 50) . . . it is remarkable that Bowman's requirements have been established without close regard to their practicality or cost ...

The original requirement was defined, and has subsequently been developed and amended, in close consultation with industry, in order to ensure its realism and affordability. Since the formation of ACSL in 1997, we have worked with industry in developing the requirement. An extensive Affordability Review in summer 1999, conducted in full and open cooperation between the Equipment Central Customer, the DPA and industry, simplified and reduced the requirement further, resulting in what is now known as the 'BOWMAN Lite' requirement. Regrettably, we have nonetheless had to conclude that the original preferred bidder could not achieve the outcome we need.

(Paragraph 50) In Bowman's case, we were glad to have the MoD's assurances that the revised requirement still fully meets the needs of the Army. The MoD must however guard against reducing the capabilities sought for the new communications systems (in order to make its delivery more assured), if the result is a capacity with a functionality little advanced from its predecessor or unable to counter the new and sophisticated communication threats it will have to deal with.

BOWMAN is a complex and involved programme but the requirement is well understood by industry who have been involved with it for several years. In 1999 a major review of BOWMAN was undertaken allowing potential solutions to the requirement to be significantly simplified. In line with SMART procurement, there are areas within the requirement where there is flexibility but this will not be allowed to detract from the overall capability of the system.

(Paragraph 57) In giving itself an option of launching a new competition, the MoD now has a sound strategy for putting Bowman back on track—the disappointment is that the Department had not resorted to this course sooner. The constant changes and delays in the programme so far have had damaging effects not only on the armed forces but on the potential suppliers of equipment, and their employees in turn, for whom the lack of firm future work has resulted in staff being laid off. The prospect of a new competition appears to have been a factor in Archer's improving performance over the last few months. If Archer's proposals do not cut the mustard, the MoD should run a new competition without delay. The consortium has not earned any right to merciful treatment by its performance so far.

The Government accepts the Committee's recommendation. The Ministry of Defence announced on 25 July that it had decided to remove preferred supplier status for BOWMAN from Archer Communications Systems Limited (ACSL) and that a competition would be launched. We had been constructively engaged with ACSL for a considerable time but after careful consideration of ACSL's interim bid for the BOWMAN contract, we were not convinced that they could deliver a communications system that met our requirement in the time required, or that represented value for money. Achieving an early in service date was the key to this decision. We are confident that a new competition now offers the best prospect for delivering the best value for money and lowest risk solution to the BOWMAN requirement. We have taken a difficult decision to bring the BOWMAN project back on track. This is what we mean by Smart Procurement—taking tough decisions to ensure our Armed Forces get the equipment they need when they need it.

(Paragraph 59) We welcome the new approach to the definition of in-service dates being adopted by the MoD, and we recommend that it be universally applied, including to Eurofighter whose in-service threshold is currently defined by the wholly misleading criteria of the delivery of the first aircraft by the manufacturers.

We note that the Committee welcomes the new approach to the definition of in service dates. We will be looking to use this definition in the majority of cases. There may, however, be a small number of projects where it might not be appropriate to do so, including Eurofighter where the definition has long been agreed with our collaborative partners.

OTHER PROGRAMMES

Type 45 Destroyer

(Paragraph 64) We were pleased to be told that [the Type 45 destroyer] is 'being designed from the outset to allow the fitting of a vertical launcher suitable for a variety of weapons (including missiles such as the Tomahawk) to every ship in the class, should a funded requirement be raised for this capability.

We note the Committee's comments about the progress being made on the Type 45 programme. As the Committee recognises, the Type 45 design incorporates margin to allow for a longer Vertical Launch System, capable of supporting a variety of missiles, to be fitted, should a land attack capability be required for the Type 45 class .

The Future Carrier and the Future Carrier Borne Aircraft

(Paragraphs 67-68) The short take-off and vertical landing version of the US-led Joint Strike Fighter (JSF) programme is currently 'a strong contender' for the FCBA. There have been press reports that the US Department of Defense are encountering technical and industrial problems with the JSF programme and may delay their selection between the bids from the Boeing and Lockheed-Martin consortia . . . we were assured that at the moment the US remains committed to the STOVL Joint Strike Fighter'

Although other options are still under consideration the US-led Joint Strike Fighter (JSF) remains a strong contender to meet the UK's Future Carrier Borne Aircraft requirement. While no decision has yet to be taken as to whether the UK should enter Engineering and Manufacturing Development (EMD) phase of JSF development we recognise the Committee's concern over progress on the JSF development programme.

There have also been concerns in the US Congress about the technical risks associated with the Concept Demonstration Aircraft. These have led Congress, for the budget cycle beginning October 2000, to redirect JSF provision to extend the JSF demonstration effort. Congress require that the exit criteria for the current Concept Demonstration Phase be satisfactorily demonstrated, with appropriate analysis and reports to Congress, before approval can be sought to the next phase, Engineering and Manufacturing Development. These requirements have led to the start of the source selection process for the Prime Contractor being delayed from November 2000 to an earliest predicted January 2001, with entry into EMD now being predicted for no earlier than October 2001 (from April 2001). However, this delay is not expected to affect the JSF ISDs which would meet UK requirements.

Ministry of Defence

3 October 2000


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 23 October 2000