Select Committee on Environmental Audit Minutes of Evidence


Examination of Witnesses (Questions 120 - 139)

TUESDAY 27 JUNE 2000

DR GEOFF MANCE, DR GILES PHILLIPS AND DR MARTIN GRIFFITHS

  120. Can I go back to the previous answer you gave on the Tyne. You mentioned the Tyne had been cleaned up. How far was that actually a result of work that was done to get rid of sewage discharges, and how far was it just that industry that had been along the Tyne just died and was not there any more?
  (Dr Mance) The major polluting load and the major consumer of oxygen was actually sewage. If you go back 20 years the sewage from Newcastle went into the Tyne, effectively, untreated. So you have got a population of about 1.5 million pouring crude sewage into an estuary where the material washes up and down the estuary with each tide and takes several tidal cycles to move out of the estuary. So most of the oxygen consumption was from sewage as it decomposed in the estuary. It is actually killing plaice in the estuary.

Joan Walley

  121. If I could come back to a couple of points arising out of Mr Chaytor's and Mr Gerrard's questions, it does not quite add up to me. On the one hand, I am being told that there was the environment programme which is going to really deal with the major outstanding work and investment that was needed. Yet, by the same token, there is a residual of combined sewer outfalls which is going to be carried forward into the next review. Speaking from a constituency point of view, and seeing how urgently that kind of work is needed, I cannot accept that all the work that needs to be done is being done when the kind of priorities that matter to my constituents are not going to feature until the next programme. When I look at that, combined with the whole issue about assets and serviceability of assets and the alarming concerns that, maybe, we are only looking at replacement works of one in 1,000 or one in 100 years, I really want to press you about the advice that you are giving to ministers in the first instance as to the principles that should underpin what should actually be in this programme. It still seems to me that however more is being done this time, for the first time ever, there still is not enough being done, particularly when it comes to the existing infrastructure of sewers and drains, and the concerns that there are there. Can you, perhaps, just reassure me on that—or not, as the case may be?
  (Dr Mance) Clearly, in our published advice to ministers in May 1998 we advised that all the problems should be dealt with.

  122. When you say "all", which is "all"?
  (Dr Mance) I mean all. So all the identified problem sites could be dealt with.

  123. So there is a list other than that list?
  (Dr Mance) We have had a running spreadsheet which has been available to the companies, it has been put in the public domain at several points in the process and culminates in the publication, this week, of the programme as approved by ministers. In A Price Worth Paying in May 1998 we laid out an action list which we attach as an appendix to the evidence, which identifies that we were putting forward the view then that given the Director General's statements and the initial cost estimates, we felt the whole programme could be funded.

  124. The whole programme was not funded?
  (Dr Mance) No.

  125. What is not funded?
  (Dr Mance) Ministers took a view of the balance they thought advisable between price reduction and the environment programme and gave us public guidance on the programme they wished to see; initially, in Raising the Quality, which is a DETR document, which was put in the public domain in the autumn of 1998 and, subsequently, this last autumn, in more detail, just prior to the final price determination, where they fine-tuned their advice to us and actually increased the scale of the programme. However, they did not go for 100 per cent of the programme we recommended. There is a residual. The residual falls into three parts. In one or two companies there are a number of sites where if the sewage-works loading from the population increase actually came to fruition, it might cause a failure of the river standards. I repeat "if" and "might", because that is a low probability, in our view. Therefore, there is not a large risk because these are not areas where there has been large population growth over the last 20 years. Under some of the EC Directives we need to make further progress on compliance with the guide values in the Directives, as opposed to the imperative or mandatory standards. There is no timetable for that in the Directives as such, we just need to demonstrate progress. The final category was the low-priority combined sewer overflows, which is about a third of the total number of overflows, where there is only a low aesthetic impact—

  126. Are they not the most important to people who have to live alongside them?
  (Dr Mance) I believe that the medium and high priority storm overflows would be more urgent for those people, because they will have widespread aesthetic impact and be causing damage to the water course itself. So we have picked up, if you like, the worst-offending storm overflows in every part of the country. It is the ones which are giving widespread aesthetic impact—and are really pronounced and, in some cases, actually discharging continuously rather than intermittently—which are being addressed by the programme.

Chairman

  127. Why did the DETR exclude some of the programmes?
  (Dr Mance) It was a judgment by ministers on the balance they wished to see between the scale of the programmes and the scale of price reduction.

Joan Walley

  128. So it was not necessarily environmentally imperative in those residual cases?
  (Dr Mance) It was a political judgment which the process set out. That is why in our evidence we laid out the roles—the Agency put forward the environment programme, ministers took a view on the scale of that and the advisability of supporting that in whole or in part on the basis of estimates of the likely impact of prices given by Ofwat. Ministers gave clear guidance in public to us on the scale of the programme they were prepared to support, and it was a very substantial programme. In one or two parts of the country, I think the company would be unable to go beyond the existing programme. So, for instance, our view in Preston in the North West is that, had the whole system over-flow problems been funded, effectively Preston would not have been able to function over the next five years; there would have been so much excavation of the roads, it would have brought Preston to a halt. So we took a view there, in discussion with the company and an assessment of the manageability and scale of rebuilding the sewers of Preston, that it needed to be spread over a long period of time.

Chairman

  129. What about the treatment schemes on the Mersey, for example? There were about five schemes there.
  (Dr Mance) There is an issue about the cost estimate and the actual justification of cost as opposed to whether they should proceed, but my colleague can comment.
  (Dr Griffiths) At the final phases of the determination there were 62 schemes where the advice the minister took from Ofwat was that there were insufficient cost and relative benefits in the case made. We were asked to complete a further appraisal of costs and relative benefits and resubmit those to the minister during this five year period, and if he was satisfied, he would have powers to introduce those into the programme. Certainly some of those schemes—and I think there was Wigan and Fazakerley and one or two of these fairly major urban regeneration/redevelopment schemes—were exceedingly expensive, tens of millions of pounds, and it was quite difficult to do a cost and relative benefit debate at that stage. We therefore will be submitting those cases as quickly as we can because we believe in many respects these decisions have already been taken in the South but the scale of the engineering in the North is extreme.

Mr Chaytor

  130. Could I ask a bit more about the cost benefit issue and ask if you have well-developed systems for cost benefit analysis? I think we understand how it is fairly straightforward to do a cost benefit analysis in terms of ending sewage discharges near a coastal town and do a calculation about the benefits of additional tourism, but not so easy to do a cost benefit analysis of the impact of increased abstraction of water and the impact on biodiversity in a particular river area. Could you tell us how you do these cost benefit analyses?
  (Dr Mance) I think you have summarised the dilemma quite well. There are no generally available accepted methodologies for costing environmental benefit or pricing environment benefit. Therefore weighing costs versus benefit is difficult when you are trying to take into account the environmental benefits as opposed to some of the more tangible things like potential impact on tourism or regeneration. I would like to put in context the fact we are not actually required by statute to undertake a cost benefit analysis.

  131. Do you think you should be?
  (Dr Mance) No. There was a long debate during the passage of the Environment Bill 1995, which created the Agency, about the duty being imposed upon the Agency to take account of an assessment of the likely costs and benefits, and ministers during the passage of the Bill in the House made clear it was not a duty to undertake a full cost benefit assessment, nor were we expected to generate our own information but only to be able to use such information as was available. That does not mean we do not take account of the possible benefits, we do, and part of the iteration of building up the spreadsheets is looking at each site at the suggested solutions and whether they made sense or whether they were being gold-plated. There is an iteration of trying to get to what appears to be the most cost effective solution. Equally, where EU Directive standards are involved, there is no requirement under the statute for us to actually assess possible benefits. It is a given and we are not exercising discretion, we are actually implementing an international Government agreement, and therefore have to proceed. All that said, the Agency for a long time, and its predecessor bodies, has been actively carrying out cost benefit assessment in flood defence capital works, for instance, so we have a lot of experience of doing cost benefit analysis, the difficulty in all cases is how to take account of and how to value environmental benefit and at times the social benefit. So the trauma of living next to a river which smells, is dead, is black, has objectionable solids—as we tend to refer to them and you know what I mean—actually flowing past the end of your garden or outside your front door, actually has an impact upon your quality of life, but how you put a price on that is very difficult. We therefore went in this process for a multi-attribute technique, which is where you give a number of weightings to different characteristics, and then you come up with a total score which enables you then to compare sites on a reasonably quasi-objective basis. We developed the weighting factors and the scores using focus groups, and using our statutory advisory committees, to actually get advice on relative weighting in an open way, and then we published all that information so that it was accessible. It gave us a way of prioritising the relative need. It was not intended to indicate what should or should not proceed but enable us to prioritise. We then had to meld together the outcome of that where we had discretion with the sites where we also had requirements under EC Directives and trying to make sure in an integrated way we were promoting all the action on these sites within this programme. Every time there is a construction on a sewage works, for instance, there is a risk of disruption of performance, and an environmental risk of unacceptable discharge, so it is sensible to keep the number of construction phases on a sewage works to a minimum, and it hopefully also means the company can come up with more cost effective solutions. We have not tried to scrutinise in detail the cost site by site of the companies's proposals, because it is clearly the role of Ofwat to do so.

  132. In terms of the formulation of the programme, you say there is not a strict and precise method of prioritising the different components of the programme. It is a combination of the focus groups' responses to the characteristics you have identified, the weightings they give and the impact of the EU Directives. It all sounds very subjective. Where is the balance between what you perceive of as the customers' preferences and what is necessary under the EU Directives and your own judgments about the science and the environmental quality of it? How do you pull it altogether?
  (Dr Mance) I am not sure it is completely subjective but there is an element of subjectivity in it. What we are faced with in this process is a number of reasons for investment, so there is a Bathing Waters Directive requirement for investment, there is a Shell Fisheries Directive requirement for investment, there is an Urban Waste Water Treatment Directive requirement for investment, there is potentially a genuine environment problem as well in terms of absence of wildlife in an area because of the impact, there may also be the aesthetic problems caused by the stranding of sewage solids. What we have done for each of those is identify the obligations. The EU ones are driven by hard timetables in the Directives and clear commitments on timing. We have then sought where we have some discretion to prioritise using the multi-attribute technique, to give us a priority sequence. We then used both sets of information to look across for each site to make sure we had picked up the non-discretionary elements first, where we were already going to have investment because there is an EU driver, a European Directive requirement, because it is clearly more sensible to try and make sure that while that site is being disturbed by one tranche of investment all the other reasons for investment are dealt with. That should open up the options for more cost effective solutions—better design or integrated design. That then leaves you with a residue of, if you like, the apparent discretionary things which you then have in a prioritised sequence. It inevitably involves bringing together in a reasonably structured way the different priorities for investment and it does give you a cascading sequence, with the first priority which is absolute because of the EU Directive requirements and ending up with the ones where there is true discretion available to ministers as to whether to proceed or not. That is the sequencing. It may sound slightly subjective but when you work it through on paper it is far from that, it is a rather mechanical process almost once you have actually done the digest.

  133. As we move on through time to the next periodic review, do you think there will be more precise methods of cost benefit analysis? Is anyone outside the Agency doing any work or research on this?
  (Dr Mance) There is a lot of activity outside the Agency, I am not so sure that will lead to a lot of progress. We ourselves are promoting a number of R&D projects aimed at focusing on particular operational needs such as this. What we are currently exploring is how we capture the outcomes of this investment programme in economic terms so we can actually see the economic benefit in given areas of the investment which will be made under this programme. We actually have a chance to use this almost as a real world experiment to give us a chance to quantify the economic benefits which do appear on the ground. That still will not give us a clear costing of the environmental benefits, say getting the fish back into the river; that is the more difficult one.

  134. Can I ask you something else about the programme? Is there still some dispute as to exactly what is in the programme and what is not in the programme? This was a point which came out in our hearing last week and there was some criticism from the companies that they claim not to be absolutely sure as to what the total programme involved. Will publication of this document this week resolve that or are there still some grey areas?
  (Dr Mance) Throughout the process there have been claims of confusion and lack of clarity. I have to say I find it very hard to accept. We have from the start maintained a quality control led spreadsheet, which has been available to the companies and to Ofwat. We have had confusion in one or two instances but that is where the company has deliberately in its strategic business plan chosen not to use the standard spreadsheet but to re-present it a different way, changing headings, changing groups and investment needs. In one or two instances that has led to confusion between the company and Ofwat as to whether there is adequate funding, but from the Agency's point of view the obligation is clear. It has been throughout in the spreadsheet which has been issued formally by my chief executive to each company on two occasions, the third occasion being this week. So I find it hard to accept they are under any illusions at all about the investment programme which has been approved by ministers from the point of view of improving the environment.

  135. One more question about the situation beyond 2005. If 2005 is the point at which work on sewage will have been completed, do you envisage an increase in work as a result of further EU Directives, or an extension of the scale of existing EU Directives beyond 2005? Will that be a major issue in the next period?
  (Dr Mance) That is difficult to judge. On the Habitats and Birds Directives the Government is currently reviewing the potential designations for nature conservation purposes. That looks likely to increase the number of areas designated and the scale of the areas we have previously been aware of, but we do not know the scope of that yet and that could well cause further impact. The implementation date for that is actually April 2004, so it is going to have impact within this period potentially. There is the draft Water Framework Directive, which looks like being agreed this summer, which at first sight should not necessarily drive extra investment but, unfortunately, over about three decades now of personal experience every time a Directive is implemented we work on the basis it will not drive very much in the way of investment and it always seems to unexpectedly have a few bear traps in it which cause substantial investment. So I would be surprised if in 2005 to 2010 there is not a need for additional investment because of change of standards or interpretation in relation to EU Directives.

  136. Will that be significant or will it be something the companies can easily absorb? Is it something the companies ought to be planning for now? Are they aware of this and have you advised them of this?
  (Dr Mance) Given it is all subject to Government agreement and decision, and we all face an uncertainty in relation to 2005 to 2010, neither we nor the companies are able to adequately plan for it, but that is the nature of the business. What we will do is make sure that as soon as it is clarified, it is converted into detailed spreadsheets again, so the companies when they come to plan for 2005-2010 and the next periodic review have no doubts at all about the obligations they face.

Chairman

  137. Are you always happy with the European Directives or are there occasions when you would rather do something else?
  (Dr Mance) I think my hesitation says it all, does it not?

  138. Yes, is the answer.
  (Dr Mance) I think the Directives which do not start with the environment but start actually with standards for discharge, do not necessarily give us the best return for the environment and the scale of investment which goes in. If we actually started with genuine environmental need and worked back, we would undoubtedly get a far better benefit for the cost involved.

Mr Loughton

  139. Can we move on to implementation and monitoring now. The quadripartite group, do you think there is any merit in continuing that with a sort of monitoring and reviewing role for the implementation of the Environmental Programme and other programmes that come out of the Review?
  (Dr Mance) No is the simple answer. The danger is it would confuse the responsibilities of the respective bodies. We are publishing the environmental obligations the companies face. It is clearly our responsibility to Government to make sure that programme is implemented through changes in abstraction licences and discharge consents, and that those changes actually appear on the ground and are effective. It is quite appropriate, therefore, that the responsibility rests with us for making sure that is put in place, that we should openly publish progress on that basis and be held accountable, if you like, for our effectiveness or otherwise. In doing so it would expose the effectiveness or otherwise of each individual water company in delivering their approved and funded programmes which, again, I think puts the accountability firmly with them. If they fail to deliver then the role for enforcement in relation to their management performance and economic performance or financial performance rests with the Director-General which, again, is clear. I think the risk of having a formalised quadripartite monitoring group is it becomes a forum for negotiating variation from what is currently a very clear, firm agreement and programme. I do not think it would help at all.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 November 2000