Select Committee on Environmental Audit Minutes of Evidence


Annex 3

ENVIRONMENTAL PROGRAMME OUTPUTS EXPECTED FROM COMPANIES FOR THE PERIOD 2000-05

Specific improvements Enhancements planned before December 2005 Assumed
capital
expenditure
(£m)
2000-05
[2000-06]
Assumed
additional
operating
expenditure
(£m/year)
2004-05
[2000-06]
Works required to reduce over-abstraction        
  (a)  at designated sites under Habitats and Birds Directives
Improvements to treatment works with a design flow of 210Ml/day sufficient to serve <1 million consumers24 projects 50
[50]
1.0
[1.0]
  (b)  affecting other SSSIs Improvements to treatment works with a design flow of 70Ml/day sufficient to serve <1 million consumers20 projects 10
[10]
<1.0
[<1.0]
  (c)  other priority sites (low flow rivers)

Improvements to treatment works with a design flow of 880Ml/day sufficient to serve 3 million consumers37 projects 60
[60]
<1.0
[<1.0]
Installing high quality sewage treatment infrastructure to comply with the Urban Waste Water Treatment Directive Improvements to works with a capacity of 18.6 million population equivalent902 sites 1,310
[1,310]
72
[82]
Works to comply with mandatory standards under the Bathing Waters Directive and further improvements to assist achieving Blue Flag status at key holiday resorts Improvements to works with a capacity of 8.0 million population equivalent75 sites 230
[230]
6
[6]
Improvements to comply with imperative standards and endeavour to observe guideline standards for:        
  (a)  Freshwater Fish Directive Improvements to works with a capacity of 4.4 million population equivalent245 sites 250
[250]
4
[4]
  (b)  Shellfish Waters Directive Improvements to works with a capacity of 1.8 million population equivalent48 sites 50
[50]
1
[1]
Other improvements to effluent discharges        
  (a)  at designated sites under the Habitats and Birds Directives

Improvements to works with a capacity of 0.8 million population equivalent33 sites 20
[20]
1
[1]
  (b)  affecting other SSSIs Improvements to works with a capacity of 0.1 million population equivalent34 sites 20
[20]
1
[1]
  (c)  for compliance with Surface Water Abstraction Directive

Improvements to works with a capacity of 0.1 million population equivalent4 sites 10
[10]
<1
[<1]
Improvements to unsatisfactory intermittent discharges (including combined sewer overflows) Improvements to 4.682 unsatisfactory overflows 1,700
[1,760]
6
[8]
Improvements in the disposal of sewage sludge        
  (i)

  Phasing out of raw sludge to land by end of 2001
       
  (ii)

  Restrictions on treated sewage sludge to land
       
  (iii)  Disposal of additional sewage sludge

A total of 1,380 thousand tonnes dry solids sludge disposed of satisfactorily 800
[800]
46
[46]
Improvements to reduce current shortfall on River Quality Objectives 2,947km river protected from deterioration, 1,004km river improved487 schemes 490
[500]
6
[12]
To meet demands for First Time Sewerage and other requirements Provision of sewerage to a population equivalent of 0.8 million315 schemes 240
[240]
11
[11]
Totals  5,240
[5,310]
155
[173]


  1.  Enhancement categories are based on the first-listed cost driver in the EA's March 1999 National Environment Programme spreadsheets. This may not correlate with the individual company's allocation of expenditure between the various categories.

  2.  Tabulated figures reflect assumptions made in Final Determinations and may be subject to minor, cost-neutral changes following recent discussions between companies and Environment Agency to finalise programmes.

  3.  Totals may not add due to rounding.

  4.  Price base: May 1999.


 