Select Committee on Environmental Audit Appendices to the Minutes of Evidence



APPENDIX 3

Memorandum from Dr Dieter Helm, New College, Oxford and Director, OXERA Environmental Ltd

INTRODUCTION

  1.  This memorandum focuses on: the institutional context of the water periodic review, the quadripartite process, the role and incentives of the water companies, and the ways in which the final determination incorporated environmental considerations in general and the precautionary principle in particular.

  2.  It will be argued that there is a lack of clarity in the roles of the Environment Agency and Ofwat; that the quadripartite process failed to provide an open process or to take full account of the sustainable development policies of the government; that economic regulation creates incentives for the companies to "game" the environmental process; and that the final determination failed to incorporate fully and reflect the ministerial decisions and the spirit (if not the letter) of the outcomes of the quadripartite process. A series of recommendations are presented to improve the periodic-review process in the future.

THE INSTITUTIONAL CONTEXT

  3.  The privatisation of the water industry required a separation between the private provision of water and sewerage services, including the maintenance and renewals of assets; the environmental regulatory functions; and economic regulation. The solution adopted was to create the National Rivers Authority (NRA) to take the lead on environmental functions, while Ofwat would ensure that companies could finance these and other functions, and be incentivised to be efficient. Government, in the form then of the Department of the Environment, would set the standards, in sympathy with the European framework.

  4.  This division of responsibility has been eroded over time. The main causes have been:

    —  the inability for the NRA (and then the Environment Agency) to focus on its environmental regulatory functions, because of the distracting and overlapping responsibilities deriving from its river-management and flood-defence functions. The NRA never had the institutional structure to provide the necessary attention to the periodic review. The Environment Agency continues in this mode, as the recent DETR Select Committee report indicates;

    —  Ofwat has encroached into the NRA's and then the Environment Agency's territory by enunciating the principle of customer affordability, claiming that, only if the costs can be properly demonstrated to be less than the measured benefits, should environmentally driven projects be financed by the price-cap mechanism (contrary to the precautionary principle);

    —  the desire of ministers to lower prices for political reasons, independent of the setting of environmental standards and the financing of functions.

  5.  This blurring of the roles of the three main institutions has been detrimental, in that it has tended to produce an answer which reflects the relative ability of the key individuals in each body to influence the outcome, rather than one which properly reflects the environmental and economic objectives. (A clarification of roles may also entail significant changes in the organisation and performance of the Environment Agency.)

THE QUADRIPARTITE PROCESS

  6.  The quadripartite process has the advantage of creating a framework within which the main parties can debate and discuss the core environmental issues. In the 1999 review, its role became one which provided an input into the minister's decision-making process, rather than the more powerful role it played in 1994. It moved away from the concept of four parties involved in making decisions, towards a tripartite advisory input.

  7.  The companies were included. They clearly have an important input in providing operational expertise and costs. However, the private and public interests are separate. The private companies are essentially stakeholders, interested in maximising profits. Their role is therefore different in kind from the other three players.

  8.  The quadripartite process is, essentially, a closed one. Other interested parties (environmentalists, academics, customers, anglers, surfers) are all external players. It is far from clear why companies should be included, while other stakeholders are excluded.

  9.  The quadripartite process did not strive to solicit advice and opinions from "outsiders", relying on these parties acting directly with Ofwat, the Environment Agency and ministers.

  10.  It is hard to reconcile the outcome of the quadripartite process as consistent with the government's sustainable development policy. Rather, there was a process which sought to reach a largely pre-set answer. This was given by the ministerial statement indicating that both environmental improvements and a 10 per cent price cut might be the outcome. This statement came well before the detailed work had been completed.

INCENTIVES ON COMPANIES TO "GAME" THE ENVIRONMENTAL PROCESS

  11.  The role of the companies in the periodic review is not neutral. As long as the rate of return exceeds the cost of capital, profits increase with the level of capital expenditure. Therefore, the companies have an incentive to encourage environmental standards to be raised. However, once the total is set, profits can be further increased if companies manage to spend less than their total set, while delivering the output. Hence, it is in their interests not only to have a large total, but also to have higher cost estimates for each project.

  12.  This "gaming" opportunity influences the advice they give in the quadripartite process. Ofwat has attempted to moderate these incentives, but with limited success. This core problem lies with the five-year, fixed-period contract approach. It is far from ideal to have the environmental (and other) capital investments fixed once every five years. A more flexible approach to the determination of both the environmental outputs and the economic regulation is desirable.

INCORPORATION OF MINISTERIAL DECISIONS IN THE PRICE CAPS

  13.  The outcome of the periodic review was presented as price cuts and stable prices thereafter. This is not a completely accurate picture of the position for customers. It was achieved by the incomplete financing of all the requirements flowing from the ministerial decisions.

  14.  A number of environmental obligations were not financed, on the grounds that the costs were either not known or agreed. The absence of a proper provision enabled the regulator to announce a price profile broadly in line with the pre-indicated political outcome. However, these obligations will not go away, and, hence, customers are likely to face higher prices towards the end of the period than they currently expect. Given the "surprise" element, there is bound to be resistance to the environmental spend, and pressure for delay.

  15.  The failure to finance fully the programme might, in normal circumstances, be regarded as sensible in view of the uncertainties ahead. However, it arises in the context in which the Director General of Water Services has been perceived to be somewhat hostile to the environmental policy agenda, and it is widely noted that the Chief Executive of the Environment Agency and the Director General of Water Services have been in considerable conflict. While the challenge to environmental objectives is often helpful and productive, in this context it has created a sense of conflict between environmental and economic objectives.

RECOMMENDATIONS

  16.  It is recommended that:

    (i)  the roles of the Environment Agency and Ofwat are clarified, with Ofwat's role being confined to the efficient financing of functions, given the environmental policy and standards set by the minister, supported by the Environment Agency;

    (ii)  the Environment Agency's performance would be greatly enhanced if its multiplicity of functions were clarified. Its operational activities and sheer size reduces its effectiveness in policy and standard-setting roles;

    (iii)  the roles of the Environment Agency and Ofwat in the quadripartite process should be clarified, with the DETR adopting the lead role;

    (iv)  the role of the companies in the quadripartite process should not be on a par with those of Ofwat or the Environment Agency. There is a good case for either confining the process to the public institutions (the DETR, Environment Agency and Ofwat), or including other stakeholders. There is no case for including the water companies and excluding other stakeholders;

    (v)  the incentives for the companies to "game" the process would be much diminished by moving away from five-year fixed-period, fixed-price contracts;

    (vi)  the full environmental impact on prices should have been made clear in the final determination announcements, and in future better information should be provided to customers and stakeholders;

    (vii)  the conflicts between Ofwat and the Environment Agency are partly the consequence of the highly personalised nature of British utility regulation. Further steps towards replacing a single Director General with a board or authority (as was proposed in the Utilities Bill when water was included) would help to diffuse such clashes in future.

May 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 November 2000