Select Committee on Environment, Transport and Regional Affairs Minutes of Evidence



Memorandum submitted by London Transport (LU 1)

LONDON UNDERGROUND: AN UPDATE ON PROGRESS

INTRODUCTION

  London Underground last appeared before the Transport Sub-Committee in April 1998. At that time it outlined issues relating to its finances and investment programme.

  Since then London Underground has been able to do much to improve its provision of transport for London and to meet record levels of passenger demand.

  In this memorandum London Underground is seeking to update the Sub-Committee on:

    1.  Performance trends

    2.  Funding and investment issues

    3.  Public-Private Partnership (PPP)

    4.  Extended Jubilee line.

1.  PERFORMANCE TRENDS

  In recent years London Underground performance in terms of passengers carried, customer satisfaction and the volume of train services operated has steadily improved. Financial performance has also improved substantially enabling an increasing element of the investment programme to be self funded. Performance trends since 1990-91 are detailed in the charts in Annex 1.

  Forcasts for 1999-2000 demonstrate significant improvements since 1990-91, particularly in the following:
Passenger journeys Up 18 per cent from 775 million to 912 million
Train kilometres operatedUp 23 per cent from 52.4 million to 64.5 million
Customer satisfactionUp 15 per cent and being maintained
Gross operating marginFrom breakeven to +£288 million

  More recent trends between 1997-98 and the forecasts for 1999-2000 show a 9.5 per cent increase in passenger journeys, a 4 per cent improvement in train kilometres operated, customer satisfaction being maintained and a 8.5 per cent increase in gross operating margin. Customer service improvements have been delivered despite a large investment backlog, which adversely impacts on the reliability and availability of assets.

2.  FUNDING AND INVESTMENT

2.1  Investment backlog—current position

  There has been a long history of under-investment in London Underground, as illustrated in Annex 2.

  Despite a higher level of core investment in recent years, a substantial investment backlog remains. The investment backlog is currently assessed at £1.2 billion, which represents no change on the position reported to the Sub-Committee in February 1997 and April 1998. The additional funding announced by Government in July 1999 will allow core investment of £377 million in 1999-2000 and £398 million in 2000-01. This is broadly in line with "steady state" investment needs of some £400 million per annum. Therefore, there should be no further increase in the investment backlog prior to the start of the Public-Private Partnership (see Section 3). From 2001-02 onwards investment to recover the backlog and modernise the network will take place through the PPP.

2.2  Investment backlog—when will it be recovered

  A Long Term Investment Programme has been prepared to assist in the development and specification of the PPP. The programme anticipates that most of the backlog will be eliminated by the first periodic review at 7.5 years from the start of the PPP. How long it will actually take depends on the phasing of the investment programme agreed in due course with the incoming infrastructure contractors. The PPP structure is inviting the successful InfraCos to optimise the investment-maintenance expenditure mix and to commit to a whole life approach to asset management. This may result in different combinations and phasing of backlog recovery, steady state and improvement related expenditure. Initially InfraCos will be expected to focus on improving asset availability.

  Overall, the majority (in expenditure and volume terms) of backlog recovery is expected to take 7 to 8 years. However, for certain asset areas (for example civil infrastracture and track) recovery is anticipated to take up to 15 years, mainly due to the practicality of carrying out the required volume of work, given resource availability and the need to minimise disruption to customers.

2.3  Investment programme-recent progress

  Much of the core investment in London Underground during the last 18 months concentrated on upgrading and renewing basic infrastructure. In 1998-99, for example, some £95 million was spent on track, £28 million on signalling and communications, and £26 million on lifts and escalators. There was also significant investment in stations and in new and refurbished trains. Main investment-related examples include:

    —  introduction into service of the new fleet of Jubilee line trains

    —  opening of the Jubilee Line Extension

    —  Circle line tunnel strengthening between High St Kensington and Gloucester Road

    —  removal of speed restrictions on the Northern line between Moorgate and Kennington

    —  reopening of Mornington Crescent station after a £10 million refurbishment

    —  modernisation of Oval and Clapham Common stations at a cost of £16 million

    —  continuation of the refurbishment of Piccadilly line stock.

  In addition to expenditure under the core investment programme, customers wil benefit from private sector investment under the Private Finance Initiative:

  Northern line Train Service—the contract involves the provision and maintenance of 106 new trains. All the new trains have now been delivered, with acceptance of the final train into passenger service planned by early 2000.

  Prestige—the contract gives London Underground and bus services in London a new integrated ticketing and revenue collection system. This includes gating nearly every station by mid-2000 and the introduction of Smartcard ticket products by 2002.

  Power Services—under this contract, a private sector consortium has taken responsibility for operation and modernisation of the Underground's power distribution system. This will include a transfer to the use of supplies directly from the National Grid, enabling closure of the Underground's Lots Road generating station.

  Connect—this contract will result in the introduction of a modern communications network on the Underground, including provision of a new integrated train and station radio system. Ageing and unreliable systems that did not allow direct communication between train and station staff will be replaced. The new communications network will also provide the basis for allowing mobile telephone use on the Underground.

  British Transport Police Facilities—the contract has delivered a new police station at West Ham and will provide a new police station at Tottenham Court Road. It will also involve the upgrade of existing police station facilities to modern standards.

2.4  Improvements programme—plans to December 2001

  The additional funds provided by Government in July 1999 will allow continued investment in essential infrastructure works and service enhancement. As well as investment in track, bridges, embankments, lifts and escalators and other basic infrastructure, the improvements programme includes:

Train Services

    —  Train service levels to improve further to a planned 68.6m kms by March 2001—6 per cent above 1999-2000 levels

    —  A 10 per cent increase in peak train service capacity on the Central line by Autumn 2000

    —  A 10 per cent increase in peak train service capacity on the southern section of the Northern line by Autumn 2000

Station services

    —  Station capacity increases (with a total cost of some £29 million) at: Vauxhall, Brixton, Russell Square and Knightsbridge

    —  Station modernisation works (with total cost of some £60 million) at: Hyde Park Corner, Euston Square, Warren Street, Great Portland Street, East Ham, Earl's Court, Colliers Wood, South Wimbledon, Marble Arch and Upton Park

Security and information improvements

    —  CCTV improvements at nine Northern line stations and three District line stations.

    —  Installation of Train Arrival Indicators on the Hammersmith branch of the Metropolitan line

    —  Completion of the programme to introduce Customer Care Assistants at key stations

    —  LT website upgrade to include an on-line journey planner

    —  Public transport guides to be delivered to every home in London

3.  PUBLIC PRIVATE PARTNERSHIP PROGRESS

3.1  Background

  In March 1998 the Deputy Prime Minister announced the intention to create a Public-Private Partnership (PPP) to maintain, renew and upgrade the Underground infrastructure under long-term contracts with private companies. Since then London Underground has done a great deal towards making such partnerships a reality.

3.2  Deep-tube PPPs

  The consortia selected to bid for the two deep-tube PPPs were announced on 15 June 1999. Invitations to Tender (ITTs) were ssent to the bidders on 19 October 1999. The ITT gives an overview of the main terms of the PPP contracts, sets out the information to be submitted by bidders, and outlines the way in which bids will be evaluated. A full draft of the PPP Contract was sent to bidders with the ITT, together with certain supporting information. At the same time, London Underground opened the Data Rooms, which contain the financial, engineering and other information which bidders will need. Bids are due to be returned on 31 March 2000.

3.3  Sub-surface Railway PPP

  Since June 1999 London Underground and Railtrack have been exploring whether there would be a way of linking the national rail network to the sub-surface lines in a Public-Private Partnership that would create better integration of overground and Underground services. The main opportunities were seen to be:

    —  a link between the national rail network in South London and the East London line (the North-South scheme);

    —  a link between Railtrack's Great Western main line and the north side of the Circle line, to create opportunities for through trips from west of London and Heathrow and to the City (the East-West scheme).

  On 30 November 1999 the Government, London Transport and Railtrack together agreed not to proceed with further discussions about the possibility of Railtrack acquiring the Sub-surface Infraco under the PPP and building new links between the sub-surface lines and the national rail network. London Underground is now due to commence the formal process of inviting bidders for the Sub-surface PPP in early December.

  Discussions between London Underground and Railtrack were detailed and constructive. Good progress was made on the North-South scheme, but evaluation of possible East-West schemes highlighted a range of capacity issues relating to the national network west of Paddington which require further detailed study. This study will be undertaken by the shadow Strategic Rail Authority—and will include a review of various proposals for improved access from Heathrow to Central London, CrossRail and other similar schemes.

3.4  Alternative funding methods

  The question about whether London Underground should be retained in the public sector and raise its own finance was considered at length during the initial evaluation of options for the PPP (see DETR's paper "Public Private Partnership for London Underground: Facts and Analysis", dated 20 March 1998). Government opted for the current structure of the PPP for the reasons set out in the paper—and since then London Underground has focused its efforts on developing the PPP.

4.  EXTENDED JUBILEE LINE

4.1  Progress update

  The extended Jubilee line is open—with a through service operating from Stanmore to Stratford via central London, Docklands and North Greenwich. A peak 20 train per hour service now operates each weekday. The extended line represents the largest extension to the network in more than 30 years. It provides links to every other Underground line, connects to the national rail network at six stations and provides access to International Eurostar services at Waterloo.

  The extended Jubilee line provides significant journey time savings. Platform to platform journey time from Waterloo to Canary Wharf is 12 minutes, compared to 30 minutes by Docklands Light Railway and the Waterloo and City line. From London Bridge to Canary Wharf, a journey that took 27 minutes now takes eight minutes.

  Westminster is the one remaining station to open for Jubilee line services. Its construction has presented huge technical difficulties and involved a number of industrial relations issues. These are now being resolved, system testing is proceeding and the Westminster Jubilee line link is expected to enter passenger service in the first quarter of 2000.

  To provide the most frequent service over the whole route, as agreed when Parliamentary approval to build the new line was given, the Jubilee line has ceased to serve Charing Cross. Customers who previously changed from mainline services onto the Jubilee Line at Charing Cross now find it easier to get off at London Bridge or Waterloo East and join the Jubilee Line from there. An extensive advance publicity campaign was undertaken to ensure Charing Cross customers were aware of the available alternative routes.

  Since through running started it is estimated that more than 90 per cent of the schedule has operated. Usage of the extended line has already exceeded expectations—with some 225,000 journeys being made on the extension each day.

4.2  Cost update

  The current estimated final outturn cost for the extension is around £3.5 billion. The principal cost risks remaining on the project are associated with completion of Westminster station and settling of contractors claims on work done and to be completed.

  The project has involved the integration of different technologies and skills with many contract interfaces. Project costs were affected by its complexity, and its construction around interchanges and an operating railway. The work has been substantially executed below ground in a city and urban environment with exposure to unforeseen ground conditions and ageing assets. Additional design, architectural and construction costs were incurred to overecome the delays, disruptions and difficulties posed by these risks—and to address some original design problems.

4.3  Post-project work

  Apart from works at Westminster station, some additional completion work is required at other stations. Settlement of the major contracts will continue well into 2000 and the Project team will need to be demobilised in a structured way. Consideration is being given to the business case for system improvements which will lead to operating cost reductions during 2000 and onwards.

  London Underground's immediate priority is to support a reliable 24 train per hour service, moving to 27 trains per hour by 2004. Introduction of higher train frequencies and the technology to support them will be dependent on the results of updated 10 year passenger forecasts and the suitability of signalling technology. Given the need to minimise any disruption to the Jubilee line during the millennium year, London Underground does not expect to be in a position to make modifications to the existing signalling system before 2001.

December 1999



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 1 March 2000