Select Committee on Environment, Transport and Regional Affairs Minutes of Evidence



Supplementary memorandum by London Transport (LU 01C)

  Further to my letter of 23 December 1999, I am now able to provide a response to the balance of the points raised by Members at the Transport Sub-committee meeting on 15 December 1999.

PROCEDURE FOR SETTLING CONTRACTORS' CLAIMS FOR WORK ON THE JUBILEE LINE PROJECT

  Details of the Claims Management procedure are outlined in Annex 1.

EFFECTS OF JUBILEE LINE EXTENSION BUDGET OVERSPEND

  The cost pressures faced by LT as a whole during 1999-2000 and 2000-01 were not confined to the funding needs of the JLE, but included also:

    —  Higher than expected bus tender prices.

    —  The assumption in the 1998 Settlement that there would be no grant for LUL from 2000-01 onwards; without additional funding this would have meant lower levels of investment than steady state.

    —  Costs for planning the transition into the PPP for the Underground, and into TfL, being higher than the sums originally advised by Government.

  All of these cost pressures were addressed by the Government in allocating additional funding to LT for 1999-2000 and 2000-01, including in particular the announcement in July 1999 of an additional £517 million of resources for investment. As a result of this additional funding, LUL is now able to invest over the three years 1998-99 to 2000-01 at a rate averaging £400 million pa, which is broadly in line with "steady state" levels of investment. After allowing also for investment through PFI contracts, the total amount invested on the core Underground system this year and next will be more than £1 billion.

  During the period when discussions on funding were taking place with Government, some projects were delayed, but not abandoned. This was to ensure the then existing cash limits were not exceeded, bearing in mind that LT was having to manage its businesses within the sums of money made available in the 1998 settlement. These delays were principally in areas such as Stations, Lifts and Escalators and Track where there is more flexibility to vary the timing of projects. The funding now available has allowed investment generally to return to previously planned levels, although for practical reasons some longer term projects are now being timed to be implemented through PPP contracts. In the meantime, planning and design work on these longer term projects is being funded from the resources now available to LUL.

COST OF USING BECHTEL ON THE JUBILEE LINE EXTENSION PROJECT

  We are in the process of negotiating an extension to the Bechtel Contract. To protect our commercial position we ask that we defer response to this question until March 2000, when we envisage that discussions will be complete.

COST IMPLICATIONS OF THE PROBLEMS THAT HAVE BEEN EXPERIENCED WITH THE JUBILEE LINE EXTENSION'S SIGNALLING SYSTEM

  The original contract was based on deliverey of a "moving block" signalling system as offered by Westinghouse Signals in their tender. This would have had a capability of supporting a train seervice frequency of 36 trains per hour, the ultimate service level forecast when the Extension was being planned. Various circumstances led to the implementation of the moving block system being deferred and a "fixed block" traditional signalling system being installed instead. The fixed block system is capable of supporting 24 trains per hour initially, which provides ample capacity to meet the short-medium term passenger usage forecasts.

  Again we are in the process of negotiating the way forward with Westinghouse so as to protect our network wide signalling requirements and would ask that we defer our response to the cost implications until March 2000, so as to protect our commercial position.

TRANSITION CONSULTANCY COSTS

  From 20 March 1998 (the date of the Government's announcement re PPP) to 13 November 1999, £48.06 million has been spent on consultancy work for the PPP and restructuring of London Underground. London Transport will not know the final costs for external advice until the PPP transaction has been completed, but we are working with the Government to ensure that we receive the best advice while minimising the overall costs of implementing the PPP.

EFFICIENCY IMPROVEMENTS

  When I gave evidence to the Sub-committee on 29 April 1998 it was based on my experience up until that point. During the summer and autumn of 1998 we assembled a team of experts to deliver the PPP. They consisted of, amongst others, our own people, PriceWaterhouseCoopers and Ove Arup. We tested a number of scenarios and, of course, a necessary input was the assumption of improved efficiency by the Infracos. Ove Arup worked with my own engineers and produced estimates of at least the level that was used in the recent PriceWaterhouseCoopers paper. My colleagues and I probed these assumptions in-depth and became convinced that they were indeed probably valid. They were in our view certainly valid enough to justify proceeding to the stage of getting real bids from the market. Based on this information, Government agreed to continue with the PPP and the Deputy Prime Minister made a statement to that effect in the House last December.

Denis Tunnicliffe

13 January 2000



Annex 1

CLAIMS MANAGEMENT ON THE JUBILEE LINE EXTENSION PROJECT

1.   Background

  In considering claims management on the Jubilee Line Extension Project (JLEP), it is essential to understand that little new cost is now arising. That is, the relevant costs have been incurred already, in some cases over a period of several years.

  Contracts for the project followed a form which has been used for many years in the civil engineering industry, but adapted to some extent to reflect experience on underground railway projects in Hong Kong and Singapore. JLE is a huge and complex project requiring the integration of different technologies and skills with many contract interfaces. In these "measurement" type contracts, the contractor is paid for the work actually undertaken and the contractor is legitimately able to claim for unforeseen conditions, delays caused by other parties and variations. In addition, the contract conditions require the contractor to notify only the intent to make a claim when the event occurs. Substantiation of the claim can follow on later and in some cases this may not be finalised until the Final Account is prepared. It was essential, due to the interdependency of each contract to the overall project programme, that the contract terms and conditions avoided the risk of work being halted whilst commercial issues were resolved.

  It should be noted also that many of the contracts were bid for and placed when the construction industry was short of work.

2.  Claims Management

  (a)  The "Engineer"

  The JLE contracts are similar in form to the ICE 5th edition contract forms for civil engineering works. The role of the Engineer under the contracts is also similar.

  Three parties are involved in the JLEP contracts, the EMPLOYER, the CONTRACTOR and the ENGINEER.

  The Employer is defined as London Underground Limited. In the case of JLEP the Project Contracts Manager is designated the Employer's representative.

  The Contractor is defined as the person whose tender has been accepted by the Employer and includes the Contractor's successors and permitted assigns (ie sub-contracting may be allowed).

  The Engineer is defined as the person appointed by the Employer to act as Engineer for the purposes of the Contract. In other words, the Engineer is required to administer the contract on behalf of the Employer and in accordance with the conditions of contract. The Contractor may only take instructions or directions from the Engineer (or persons with power delegated by the Engineer) within the bounds of the contract. The Engineer has the conditional authority to order variations to the works and to value those variations (after consultation with the contractor). The Engineer also has the authority to grant extensions of time where the contractor is delayed or impeded. He may not instruct the contractor to accelerate the works unless required to do so by the Employer.

The impartial role of the Engineer

  The contract places on the Engineer in many circumstances the job of deciding on the rights of the parties (the Employer and the Contractor) according to his own opinion of what is fair and reasonable under the contract and acting accordingly—for example deciding whether the contractor is entitled to payment or an extension of time. In this capacity, the engineer must act independently of both parties in deciding fairly the application of the contract.

  In addition, the Employer may empower the Engineer to pass on the Employers wishes—for example, if the Employer wishes to make advance payments outside the contract.

  In practice powers are delegated widely so that most of the day-to-day administration of the contract is undertaken at "site" level. Certain matters can only be dealt with the Engineer, as laid down in the letters of delegation issued to the contractors.

  Apart from payments and awarding extensions of time as mentioned above, the Engineer's powers also extend to matters such as variations, handover, completion and maintenance certificates.

  Generally, on payments due under the contract, the contractor applies for payment and the engineer certifies what is due. This then has to be paid by the Employer, subject to any bona fide set-off or counterclaim of the Employer or any right to make deductions from sums due under the contract.

  If a dispute arises between the Employer and the Contractor, including those arising from a decision by the Engineer, it is first referred to the Engineer to rule on. If either the Employer or the Contractor is dissatisfied with any such decision of the Engineer, the dispute may be considered under the LU Conciliation Procedure. If conciliation does not resolve the issue it may be referred to arbitration.

  (b)  The "Employer"

  At the present time the Employer's representative dealing with all commercial matters beyond those dealt with by "the Engineer" is the Project Commercial Manager who reports to the Project Chief Executive, both of whom are Bechtel staff.

  The authority process for all claims settlements rests with the Project Financial Control Group (PFCG) chaired by the LT Chief Executive and including a LT Non Executive director, the LT Director of Finance, the LT Legal Director, the JNP Infraco MD, the Project Chief Executive, the Project Commercial Manager and other JLE Project team members.

  A contract management group comprising members of the PFCG agree and oversee the close out of major contracts, including settlement of claims, having determined the structure of approach and negotiating strategy for all the major contracts. To ensure the approaches are appropriate and viable there is a close working with LT Solicitors and external legal advice including leading Counsel where appropriate.

  (c)  Claims Management Strategy

  The general commercial strategy is as follows:

    Concentrate on critical areas

    Focus on least contentious issues first

    Co-ordinate Variation/Claim substantiation

    Utilise expert external consultants if needed

    Identify legitimate interim payments

    Formal Commercial Settlement process

    Approval mechanisms for substantiation and recoveries

    Consolidate commercial teams

  London Underground faces a number of risks in dealing with claims, as follows:

    Difficulty in obtaining adequate substantiation from contractors

    Adequacy of "historical" documentation

    Continuing availability of key personnel

    Contractors' willingness to settle amicably

    Cash availability

    Residual issues such as "moving block signalling"

    Sustaining contractor commitment and pereformance

  Faced with these risks, for the past 18 months or so LU's approach has been, where necessary, to encourage a climate with contractors of "teaching commercial settlement" rather than venturing or defaulting into long and expensive litigation. Obviously, the settlements reached have to represent value for money, with an auditable outcome or business case for London Underground.

  (d)  Contract Close Out Strategy

  There exists for each contract a well documented close out strategy which clearly is highly confidential. This is supported with a financial summary and contract status summary, all of which are updated each four weekly accounting period.

  There also exists a time based schedule of activities to achieve "Final Account" status for each contract, as follows:

  Works completion

  Maintenance Period

  Notional Final Account

  Contractor Negotiations

  Contractor Final Submittal

  Employer Final Settlement

  It should also be mentioned that the contract itself gives up to 18 months after completion to agree Final Accounts. We are aiming to have "notional" final accounts settled for many of the contracts by March 2000.

10 January 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 1 March 2000