Select Committee on Environment, Transport and Regional Affairs Minutes of Evidence



Examination of witness (Questions 20 - 39)

WEDNESDAY 15 DECEMBER 1999

MR DENIS TUNNICLIFFE

  20. I am sorry to have interrupted you in that way. Why did Deputy Prime Minister terminate?
  (Mr Tunnicliffe) The Deputy Prime Minister's view was that the position of Railtrack as single bidder was only justified—and this has been his consistent view all the way through since June and maybe May; I cannot remember when the debate started, but all the way through the Railtrack period—because it was thought that the case for a single bidder was that there was something exceptional that could be done with Railtrack that could not be done with anybody else, and particularly some exceptional integration between the national railway system and London Underground. Two schemes were explored. One scheme which relates to the development of the East London line was found by both parties to be really quite attractive, was developable in a number of different scenarios, and did not require anything like the same sense of common ownership to achieve it, and I am very hopeful that that scheme will go ahead one way or another in the relatively near future. The other scheme was a scheme which connected the national railway to the London Underground at a junction at Paddington. When we first looked at it and came to the understanding to try and develop this scheme with Railtrack it looked quite attractive. As we got into it both sides started to understand the sheer complexity of the task, not putting a junction at Paddington but of actually managing the two railways together, creating enough capacity on the Great Western Railway, so as to use any slots that were used on the north side of the Circle and to look at other BAA aspirations for services around that, what other aspirations there might be as a result of more capacity becoming available from Great Western, for instance, and some general re-appraisal of the capacity into Paddington that developed out of the concerns over Ladbroke Grove. When one saw the size of that it was not a debate really between ourselves and Railtrack which was the sort of debate that one might have had quite quickly. It suddenly became a very complex study which concentrated and centred on the Strategic Rail Authority, because the Strategic Rail Authority would have to make long term commitments about investment on the national railway to enable it to happen, and long term commitments as to how that piece of railway was used. The Strategic Rail Authority said to the Deputy Prime Minister that to understand all that complexity would take a long time and under no circumstances could the Strategic Rail Authority give him an agreement and guidance early next year, which is what the programming was. On that basis the Deputy Prime Minister took the view, and we all agreed, that it would not be sensible to continue with the single bidder basis.

  21. So had there merely been a negotiation between yourselves and Railtrack about what was best for British Railways as it were, probably a deal would have been do-able?
  (Mr Tunnicliffe) If that were possible, but it simply is not possible because the moment you start to connect the railway in and you start to look at the capacity that then lies to the west, what you think is a simple idea suddenly becomes very complicated.

Chairman

  22. What you are saying is that the idea seemed like a bright one until you looked at it in detail, and then you both decided that neither of you had got it right in the first place.
  (Mr Tunnicliffe) I think that is probably fair.

Mr Gray

  23. Presumably Railtrack now will be able to take part in the bidding process for the infracos. Will they also be able to bid for the upgrading and maintenance of the rest of the track?
  (Mr Tunnicliffe) They will be able to bid for the SSL, or they will be able to seek to pre-qualify for the SSL, to be absolutely correct. They are out of time to bid for the deep tube.

Miss McIntosh

  24. During an 18-month period approximately between January 1998 and November 1999 there were 5,544 incidents of delays to services lasting 15 minutes or more. How does this figure compare with previous periods?
  (Mr Tunnicliffe) The rate of delays of 15 minutes or more has been pretty constant over recent years.

  25. Does it not concern you therefore that of these delays 550 were due to track circuit failure, 519 were due to the fact that staff were either absent or not in position, and what can be described as miscellaneous train defects accounted for 481? Does that concern you and, if it does, what measures are you proposing to take to prevent such delays in the future?
  (Mr Tunnicliffe) The delays, as I say, have been fairly constant over recent years. The level of delays we have is not something we are comfortable about and that is why we are looking to the future with the focus of the new organisation to actually start working the number of delays down. A significant number of the delays are train related.

Chairman

  26. You mean rolling stock related?
  (Mr Tunnicliffe) Sorry, rolling stock related.

  27. I am sorry, but if we create words like "infraco" we must expect people to question our English. Forgive me.
  (Mr Tunnicliffe) I apologise, Chairman.

  28. Those of us who went to council schools have problems like that.
  (Mr Tunnicliffe) Both of us. The rolling stock related ones have been very much related to major programmes like the Northern Line PFI which has brought new trains on to the Northern Line. It brought them on rather more slowly than we had hoped and therefore we had old trains for longer and they were a problem. The new trains had teething problems. We are round that curve.

  29. You mean that is getting better?
  (Mr Tunnicliffe) That is getting better. The refurbishment of the Piccadilly Line trains, for instance, created, because of the depth of the refurbishment, some quality problems. That created some delays. The quality is now improved and the performance is getting and will get better. There were Central Line problems; there still are. Most of those we would expect to get better. The delays relating to our workforce have to an extent related to having people in the wrong place as the timing of various physical changes like new trains coming along, like the Jubilee Line opening, have shifted.

  30. You mean it was a surprise to you?
  (Mr Tunnicliffe) It was a surprise, yes. We expected our Northern Line trains to be introduced more rapidly. We expected the Jubilee Line, as you know from previous evidence, to become available more quickly.

  31. Is that not a reason to have people in place before they come along?
  (Mr Tunnicliffe) Yes indeed, but you get a ripple effect through the system so if you are expecting, for instance, Northern Line guards to fund expansion elsewhere of train drivers, and then you find you cannot release them because you are still using 59 stock, you have those sorts of problems.

Miss McIntosh

  32. For the Circle Line closure while the Gloucester Road and High Street Kensington Line was being attended to, extensive preparations were planned which then had to be abandoned. Can you first of all explain why the preparations failed to work and secondly put our minds at rest that similar difficulties will not be encountered on a future occasion?
  (Mr Tunnicliffe) Yes. We have what we believe to be quite good modelling techniques for simulating what happens on the railway so you simulate a line and you put some sort of perturbation in it and you see what happens and so on.

Chairman

  33. You must be quite good at perturbations by now, I should think.
  (Mr Tunnicliffe) Yes, Chairman. We use these sorts of things, together with the teams working together, to try very hard to take that particular link out and still deliver almost as much of a train service to our customers as we had before, and we invented a solution which really was a Circle Line but because it could not go round the Circle it went down to Wimbledon basically. In practice it was too fragile and it failed relatively easily. Frankly, it took us longer to realise that than I think we would like in retrospect. I think it took us about four days to fully come to the conclusion that that was not going to work; it was too fragile. Then we went away from that, and I think it probably took us about five or six days to do the whole thing, to basically taking the Circle Line out completely, ie those trains that go all the way round, and reinforcing the Hammersmith and City and the Metropolitan Line where we could. We achieved, if I recall, on most sections of it 70, 80, 90 per cent of the frequencies and because it was running to patterns which were much more robust then the second week onwards it was not as good a service as we were providing before we had taken the Circle Line corner out, but then it never could be, but it was quite a reasonable service. Our first mistake was to try too hard to push this capacity back in a way that in the end did not work and our second mistake was not to react to it quickly enough. At the time we apologised to our customers for both those mistakes. We have generally been quite good at closing lines in the sense that—

  34. That may be an unfortunate quote, Mr Tunnicliffe!
  (Mr Tunnicliffe) Yes, Chairman. We have closed parts of the railway before and by extensive consultation with local authorities, user groups and so on, we have minimised the impact by putting in buses and different routings. The Circle Line was one we got badly wrong and we are taking a lot of learning from that.

  35. You are not ever going to do it again, are you?
  (Mr Tunnicliffe) We will close parts of the Circle Line either next summer or the summer thereafter because there is no other way of taking very fragile structures and reinforcing them. We will have extensive planning for those closures and they will go, we believe, much better than the one this summer.

Mr Stevenson

  36. One of the points which was made to argue in favour of the PPP proposal was the Jubilee Line, but is it not true that the PPP proposals are restricted to cover the maintenance and enhancement of existing Underground constructions and have got nothing at all to do with new line construction?
  (Mr Tunnicliffe) They envisage some modest extensions but they certainly have nothing to do with new line construction of that magnitude.

  37. Could I then quickly go on to the point you made about delays and the efficiencies of the private sector which Pricewaterhouse said could be 20 per cent? We tend to agree with that. Is it not the case that Alstom were four years behind schedule in delivering the new Northern Line trains, which you say has been experiencing difficulties? Central Line trains provided by Adtranz have also experienced delays, which have been due to platforms having to be rebuilt because Adtranz failed to gauge the size of their trains, which seems to me to be quite an inefficiency if it is true. Problems have been experienced due to Adtranz not ensuring that the trains were compatible with the Central Line's ATP system, and continuing problems have been experienced in the signalling installed by Westinghouse Signals on the Central Line. All these are private companies. Do you concur with that information and, if so, do you share the concerns some of us have about how this demonstrates that the private sector cannot necessarily deliver all the efficiencies that are being suggested?
  (Mr Tunnicliffe) The Alstom trains were late, I am not sure whether it is four years; I do not think it is four years but it certainly was significantly late.

  38. Could you check on that?
  (Mr Tunnicliffe) Yes, certainly, and we will send a note. The Adtranz trains I think you are mixing up with some of the problems on the main line railway. We did not suffer a gauging problem with the Adtranz trains. They were gauged as we expected them. We had planned to do some civil work as part of the project because there were not tunnel collapses but tunnels had been squozen (sic) over the years and that was put right as part of the total project. We certainly had something of a gauging problem with the Northern Line trains but I do not think you can blame Alstom for that. It was because our tunnels were twistier than we thought they were. The signalling on the Central Line has been a long sage and you are quite right, it is by a private sector company, Westinghouse. At the end of the day it will be anyway. We have no capability to either manufacture trains or to install major signalling projects. they will always come from the private sector. The thing that is different about the PPP is that they will be commissioned by a private sector firm whose rewards will be very closely tied with the performance in delivery of upgrades and delivery of reliability, and it is that direct relationship between performance and reward that we and our advisers believe will give better performance.

  39. Is that the reason Taylor Woodrow have withdrawn, and is it the reason the Government have now decided to accept the principle of public subsidy which was never in the Pricewaterhouse document?
  (Mr Tunnicliffe) Taylor Woodrow have withdrawn as I understand it because they have been re-assessing their portfolio. They have got a new management team and the new management team, looking at the shape of the company in the future, did not feel as enthusiastic of this project as the previous management team did. The Government had an aspiration for there not to be any subsidy when spec-ed up this thing, but Gavin Strang, who made the statement, made it very clear that whilst that was an aspiration that was all it was. It was not a condition. The key test of the success of the PPP is, is it best value for money and will it produce a sustained quality investment programme? Our working with the PPP so far leads us to the view very firmly that the answer is yes to both of those questions.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 1 March 2000