Select Committee on Environment, Transport and Regional Affairs Memoranda


Memorandum by Birmingham City Council (PI 42)

INTRODUCTION

  It is important to stress at the outset the high regard that the City Council has for the Planning Inspectorate and in particular the professionalism and independence that pervade all of its activities. Our perception is that these qualities are widely shared by all those who have involvement in the development process, not least the general public.

  We see the following as the key attributes/requirements of the public inquiry system:

    —  A means of settling disputes on the basis of sound judgement and consideration of all the relevant issues.

    —  Speedy completion of the process is in the interests of all parties.

    —  Must be transparent and comply with the principles of natural justice.

    —  The process should be efficient and not wasteful of resources.

  Our observations on the issues to be examined do not raise many issues about the Inspectorate itself but centre on questions such as:

    —  Does current practice deploy resources to best effect?

    —  Are public inquiries always necessary?

    —  Could the process be altered to make it quicker and cheaper without real detriment to the quality of decision-making?

  The Sub-committee's terms of reference set out a number of issues that will be examined as part of the inquiry. The City Council's observations in respect of each of these are set out in the following sections.

DETAILED OBSERVATIONS

1.  THE RELATIONSHIP BETWEEN THE INSPECTORATE'S INTERNAL TARGETS AND THE QUALITY OF THE DECISIONS MADE

  No comments.

2.  THE CONSISTENCY OF DECISIONS MADE

  In the West Midlands Region there have been concerns raised over the consistency in the approach of Inspectors Reports into development planning issues such as the approach towards the accommodation of long-term development needs in Green Belt and provision of affordable housing. Insofar that these have been challenged the Inspectorate or Government Office have suggested that the differences can be explained by particular local circumstances. We are not entirely convinced and would suggest that a lack of clarity in government policy and apparent lack of briefing to Inspectors may also be contributory reasons. If our assertions are correct then we would suggest that some changes to the operation of the development plan inquiry process might be in order (see observations under 3 below).

  One possible course of action might be to establish a well-publicised complaints procedure.

3.  THE RELATIONSHIP BETWEEN THE INSPECTORATE AND GOVERNMENT OFFICES

  In respect of development plan inquiries we consider that there may be some benefit in the preparation and publication of briefs to Inspectors prior to the commencement of public inquiries. This could have two principle benefits:

    —  Significant amounts of inquiry time could be saved. For example, if the Government Office prepared a brief which stated that the development plan should conform to the overall level of new housing provision set out in Regional Planning Guidance then long and tedious inquiry sessions questioning the Secretary of State's Regional Guidance could be avoided. That would not stifle a debate taking place at all but displace it to the next review of the RPG. If a situation arose where the local planning authority proposed a level of housing at odds with both the RPG and Government Office brief then at the very least the parameters of the debate would have been more tightly focussed.

    —  The brief to the Inspector could also clarify government policy within a regional context. It could, for example, define the extent to which long-term development needs could be taken into account thus ensuring consistency of approach within each region.

  If such a proposal were adopted it would be very important that any brief should be published well in advance of the public inquiry. Strong reservations to its content could be raised publicly at the pre-inquiry meeting.

  A second major issue in relation to development planning concerns the entire "scrutiny" process operated by government offices. This often leads to a situation where the Government Office submits objections to a development plan. Our experience suggests that this activity is not only time consuming (and arguably duplicating the role of the local planning authority) but it also leads to a type of objection that appears to be given a greater degree of status in the inquiry process. We consider that this issue could be very easily addressed by requiring that the Government Office should present its objections orally at the public inquiry and thereby place itself open to cross-examination. We consider the effect would be to reduce the level of Government Office involvement, lead to greater subsidiarity and above all help remove a degree of haziness that surrounds government intervention in the development planning process.

  Following the recent Warwickshire Structure Plan Examination-in-Public the Government Office for the West Midlands intervened in a most unusual way. The Warwickshire Panel Report recommended that the County Council should revise its affordable housing policy. GO-WM did not agree with the revised policy and suggested to the County Council that the Panel's conclusions did not accord with national policy and that the Panel had misunderstood the issue. The Warwickshire Panel Chairman subsequently refuted these claims! While we accept there are circumstances where the Secretary of State might wish to take issue with the outcome of an inquiry we consider that this should not be a matter that is within the domain of the Government Office. It was fortunate that in the Warwickshire case the papers were in the public domain and that representations were able to follow. We wonder if there might be other circumstances where papers or correspondence that relate to inquiry proceedings and thereby planning decisions have/are not made publicly available. It is clearly very important for the integrity of the whole public inquiry system that all papers are within the public domain.

  Moving from development plan to planning control issues we have further concerns about the role of the Government Office. In our view there have been instances in the recent past when GO-WM has acted to call-in planning applications unnecessarily leading to excessive delays, higher costs and Government intervention in matters that should rightly have been dealt with locally. Three examples spring to mind. Top of the list is the proposed Arena Central development in the City Centre.

  This major mixed use City Centre project is very much in line with national, regional and local policy principles of urban concentration and regeneration and has a close fit with Birmingham's nationally acclaimed City Centre Design Strategy. It was submitted mainly in outline, and although a large proposal (including a tall tower) it is widely accepted as appropriate and non-controversial in Birmingham—not just by the City Council. There is also strong support from resident and business representative groups. The call-in focused to a considerable extent on design issues. It was never clear what national policy issues were at stake. The City Council saw Arena Central as a potentially positive regeneration project and the scheme was put through extensive and open public and expert consultation, technical analysis and negotiated amendments—a process which took five months—before being "minded to approve". In contrast the call-in process has taken almost two years thereafter. Both the developer and local authority remain unclear as to what issues are being addressed and frustrated by a "distant" process that is essentially dealing with matters of detail that should be decided locally.

  The second case relates to a proposed Tesco foodstore in an out-of-centre site upon which the City Council was minded to grant consent. In this case all the evidence suggested that there were no alternative sites available either within or adjacent to existing centres and that the retail impact assessment showed no over-riding adverse impact on existing centres. While there were local objections to the proposal these had been taken into full account by the City Council's Planning Committee in arriving at its "minded to approve" decision. It appears to the City Council that the call-in decision related to the out-of-centre retail proposal. What seemed to have been forgotten is that a consequence of the sequential test is that in certain circumstances out-of-centre retailing is permissible. If this is not the case then the action that should be taken by Government is clear—Planning Policy Guidance Note 6 should be revised to insist that all retail development takes place in-centre.

  The third example is, perhaps, the strangest of the three. This concerned a proposal to develop a retail warehouse park adjacent to the Ring Road in Birmingham—in accordance with the policy set out in the Birmingham Unitary Development Plan and Supplementary Planning Guidance. This proposal was called-in even though no objections had been submitted, apparently on the grounds that the Government Office considered the proposal to be in conflict with Government policy.

  In cases where applications are referred to the Government Office, either under the Shopping Direction, or for other reasons, we have noted an increasing tendency for interested parties to submit representations either in favour of, or opposing call-in. At present there are no procedures governing this process. It seems to us that in the interests of fairness and openness some protocols should be put in place, for example that matters of factual accuracy are dealt with appropriately and that any submissions be made known to all interested parties. However, it is also important that this stage does not become an inquiry process in its own right and so our view is that interested parties should be discouraged from making lengthy submissions, which inevitably encourage further submissions from the other parties. The principle should be that the Secretary of State will reach his view on the basis of the same material submitted to the local planning authority when it considered the application.

  The City Council would conclude that a review of the role of Government Offices in both the planning control and development plan areas is called for. We would strongly argue that intervention should be used far more sparingly and that the principles of subsidiarity should be vigorously applied.

4.  THE ABILITY OF THE INSPECTORATE TO ADJUST TO CHANGING WORKLOADS, INCLUDING THE USE OF NEW TECHNOLOGY AND THE VOLUME OF LOCAL PLAN INQUIRIES

  The volume of paperwork in local plan inquiries can be frightening and it makes sense that every effort should be made to apply the benefits of new technology.

  The Draft Alterations to the Birmingham Unitary Development Plan will shortly be published for public consultation and we are working to maximise the use of computer technology, for example by scanning consultation responses directly into a database and publication of material via the internet. We expect the initial time and investment in developing these systems will pay dividends later in the process.

  Nevertheless, we feel that the overall management of plan preparation, consultation and the inquiry process is very important and that poor decisions at the outset could lead to potentially crippling delays later on. For example, a badly prepared plan—perhaps one that contains too much detail—could prompt an avalanche of objections and paperwork. On the other hand, however, we would be equally concerned if the desire to limit the number of objections and length of the inquiry process led to the preparation of a plan which failed to address the real and difficult issues.

  On a more detailed note we recall that our dealings with the Inspectorate were complicated during the preparation of the original plan through their use of effectively non-standard and out-of-date computer equipment. Even now requests for electronic documents from DETR are not in the most common and widely used formats!

5.  THE TREATMENT OF COMPLAINTS TO THE INSPECTORATE

  Please see comments under 2 above.

6.  THE IMPACT OF HUMAN RIGHTS LEGISLATION

  The City Council is highly committed to extensive and effective public consultation. Ethnic minorities make up in excess of 20 per cent of the City's population and therefore production of documentation in a variety of formats has been a feature of public consultation for some time.

  The summary material for the forthcoming UDP consultation will include the preparation of audio tapes in five ethnic minority languages. We will also make the provision for face-to-face meetings with interpreters should this prove necessary. In addition an English version will also be prepared for the visually impaired. There are financial implications arising from these commitments but these are matters that have to be addressed.

7.  RECRUITMENT, TRAINING AND EQUAL OPPORTUNITIES

  No comments.

8.  PUBLICISING PUBLIC INQUIRIES

  It is a fact that attendance at most public inquiries are high on day one but then quickly tail off. By definition the hearings must be in public and there is a strong case to allow some sessions to be held outside of normal working hours.

  We have no strong concerns about this issue because public awareness and involvement in the planning process depends to a much greater degree on the quality of the public consultation carried out during either plan preparation or prior to the determination of a planning application.

9.  ASSISTANCE FOR PARTIES TO INQUIRIES

  The format of most public inquiries is of a quasi-judicial hearing with legal representation and expert witnesses. There is no doubt that such a format can add significantly to the length and cost of the inquiries. Whether the quality of decision-making is improved as a consequence is a moot point! A key effect of the style of most public inquiries is that they become very adversarial, very detailed and very difficult for the non-professional to become involved.

  Our experience is that more informal hearings—such as a round-table session at a development plan inquiry—greatly assist the decision-making process and generally lead to a better quality of discussion. We consider there to be a strong case to extend the use of this type of hearing and would, for example, envisage using this approach for large sections of the public inquiry into the UDP Alterations. At our first UDP inquiry the adversarial format was used throughout.

  A big issue for the City Council is the resources that are tied up in public inquiries. There is no doubt that the whole process is very time-consuming and the effect is to divert attention from—arguably—much higher priority work. In circumstances where the inquiry seems unnecessary—see 3 above—this is of particular concern.

  Another matter we would wish to raise is in relation to the length of some public inquiries and to query whether this really leads to a better quality of decision. We wonder if there were some sort of time limit placed on time available to present a case might help focus minds and provide inspectors with a far clearer basis for making a speedy decision. We doubt there are many developments where the case in support, or against, could not be effectively expressed in one inquiry day. There are many instances where it takes far longer and we doubt that the decision-making process is effectively improved. Cross-examination might also require curtailing. One way might be for advocates to make a statement on the scope of their intended questioning to the inspector and if this cannot be achieved within the prescribed time—perhaps as a result of an obstructive witness—then the issues could be directly addressed by the inspector in his/her questions.

  There may also be some scope for greater use of pre-inquiry meetings to seek agreement over the key issues in advance.

10.  COMPLIANCE WITH TIMETABLES

  Failure to produce evidence to a pre-determined timescale without doubt hinders the smooth running of the inquiry process. In our experience, however, most parties make the effort to comply. We support the usual practice that failure to comply might either remove the right of appearance or lead to the loss of a participant's place in the inquiry timetable.

  We strongly consider that agreed timescales should apply to other participants in the process and in this respect our experience is that decision-making can be subject to extraordinary delays with there apparently being a pretty good correlation between length of delay with seniority of the decision-maker! The worst example we are familiar with is the four years it took for the Secretary of State to issue his decisions in relation to the M42 Premium Industrial Site applications.

  Our suggestions for trying to shorten the length of inquiries are important as the longer the hearing the more paper that is generated and the longer the report writing time. It is interesting to note that there is no limit to the length of evidence presented at public inquiries unlike the six A4 sides requested by this Sub-Committee. Again we would make the point—would the City Council's evidence be any more instructive if it were two, three or four times the length? The opposite is likely to be the case.

  If it were possible to shorten and simplify proceedings it might also be possible for inspectors to issue their decision at the conclusion of many simpler proceedings, effectively reintroducing the old-style system of red and green forms. This could dramatically speed up the whole decision-making process to the benefit of all participants.

11.  THE AVAILABILITY OF ASSESSORS FOR SPECIALIST INQUIRIES

  It is clear that many inquiries deal with evidence of a highly specialised nature. It makes good sense, therefore, that independent specialist advice is available to assist inspectors in appropriate circumstances.

February 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 23 March 2000