Select Committee on Environment, Transport and Regional Affairs Memoranda


Memorandum by the Planning Group, Denton Wilde Sapte (PI 46)

INTRODUCTION AND SUMMARY

  1.  These comments are intended largely to address practical issues associated with the public inquiry process. We do not wish to comment on the internal organisation and peformance of the Planning Inspectorate, although some of the comments below clearly envisage a different role for Inspectors in the conduct of inquiries.

  2.  The general thrust of our comments addresses the perception that the inquiry process may be becoming too cumbersome, and that the existing procedural arrangements are being exploited by parties wishing to delay or prevent proper consideration of relevant issues. It is crucial that the inquiry process operates, and is perceived to operate, as a fair, impartial and efficient forum for determining appeals and called-in applications. Our suggestion is that public inquiries are likely to be less prone to deliberate and unintentional delay and inefficiency if they are actively "case managed" from the beginning. Some of the practical consequences will be an enhanced importance for pre-inquiry statements, wider use of pre-inquiry meetings and greater third-party involvement in the contents of planning obligations. We also discuss some of the issues involved in ensuring more efficient third party involvement.

  3.  Other issues will require a more holistic assessment of the planning process, for example to see if changes can be made to the rules governing determination of planning applications by local planning authorities to avoid appeals.

THE BACKGROUND

  4.  We welcome the greater use of informal hearings and written appeals, and on the whole there seems to be a deal of satisfaction with them by "users" of the system (i.e. applicants and local planning authorities).

  5.  There will always be some development proposals which will be evaluated by way of a public inquiry, however. Where planning permission has been refused, the technical complexity of proposed development, the force of local planning authority opposition or the weight of public interest may mean that written representations or an informal hearing are inappropriate for determining an appeal. Inquiries held at the direction of the Secretay of State pursuant to Section 77 of the Town and Country Planning Act 1990 ("call-in" inquiries) proceed on a slightly different approach, a decision having been taken that the issues raised by the application should be considered in a forum which allows greater particpation by the applicant and third parties.

  6.  It is not always appreciated that considerable efforts are made to avoid inquiries, by all concerned. The delay and expense associated with inquiries can often prejudice the commercial viability of a proposal. Unfortunately, recent experience has also made us aware of a perception among applicants/appellants that third party objectors will use an inquiry (or even the prospect of an inquiry) as an opportunity to cause problems and delay for the proposed development. In addition, inquiries are also sometimes seen by local planning authorities as a convenient way of avoiding difficult decisions at local level. In our respectful submission, these features are not symptomatic of a system which is efficient or serving the best interests of all its users.

  7.  One issue which we would like to raise is whether, in the case of an application which is not called-in, there is a need to address or re-visit the assumption that planning applications can be determined only by the local planning authority or the Secretary of State. Where there is the possibility that planning permission can be granted following further discussions with, or the provision of additional information to, the local planning authority this possibility should be exploited. At present, only the practice of submitting duplicate applications permits this. This is expensive for the applicant and involves unnecessary use of resources by the local planning authority. It may be fruitful to consider the possibility of concurrent jurisdiction for both planning authority and Secretary of State. This is an issue which may be outside the terms of reference for this Inquiry. In any event, we suggest that one of the principal aims of any further changes to the current system should be sufficient flexibility to allow appeals to be withdrawn if planning permission can be granted (eg following changes to the application).

  8.  Finally, these comments are made against the background of increasing public participation in inquiries, often by objectors who (although not professional) have a good understanding of the process. Regrettably, in some cases objectors to proposals are able to exploit the existing procedures to delay inquiries. What is needed is a more streamlined process, designed to serve objectors as well as applicants and local planning authorities, which will (hopefully) reduce or remove the opportunity to abuse up the inquiry process.

WHAT ISSUES NEED TO BE ADDRESSED

  9.  It is easy to state that the ideal must be efficiency. In general terms, the decision-making process as a whole must be efficient, as must the actual conduct of inquiries. Clearly, it is in no party's interest that inquiries drag on or proceed on an unstructured basis. Quite apart from the cost (which, it must be recognised, is an issue affecting all parties, objectors included), a cumbersome inquiry process prolongs uncertainty about important projects. There is no reason why inquiries cannot be structured in a way which enables all parties to satisfy themselves that relevant points have been made.

  10.  The inquiry system must balance the desire for efficiency with the need to ensure that all relevant issues are identified and properly considered. This aim will be supported by ensuring that potential appellants, local planning authority officers and interested third parties are aware at an early stage of the issues in dispute.[82] "Early stage" here should mean at the time that a committee report is produced. In our experience, they are usually well-drafted. However, reasons for refusal are not always clearly drafted and there is often delay in producing copies of resolutions and decison notices.

  11.  If members decide to refuse an application, the reasons should be produced quickly and should be as full as possible. We welcome the proposed amendment to Article 22 of the General Development Procedure Order 1995 ("the GDPO") which, if implemented, will require decision notices to specify all relevant development plan policies. Where the Secretary of States has called in applications, the letter issued pursuant to Section 77 TCPA 1990 should set out in full the reasons for doing so.

CASE MANAGEMENT

  12.  In our submission, giving the Inspectorate a "Case Management" role will assist in making the inquiry process less cumbersome. The Committee may be aware of the changes to the Civil Procedure Rules introduced under the guidance of Lord Woolf in 1999. One of the changes introduced was to give decision-makers a much more active role in the procedural aspects of cases. In addition, parties are now encouraged to reveal their cases at an early stage so that attention and evidence can be focussed on areas of real dispute. We suggest that something of these changes might usefully be reflected in the planning inquiry process. We would like to suggest three practical areas to address.

Statements of case

  13.  There must be an acceptance by all parties (including the Secretary of State) that statements of case submitted pursuant to Rule 6 of the Town and Country Planning (Inquiries Procedure) Rules 1992 ("the Rules") are an important part of an inquiry. They also present an opportunity to ascertain where the real issues between the parties lie and where there is some measure of agreement. "Rule 6 Statements" (as they are known) are often not taken seriously by applicants and local planning authorities. Indeed, our experience is that statements of case are rarely if ever mentioned during an inquiry or in a decision letter. The Committee will be aware that there is no mandatory provision in the Rules to require that parties other than the local planning authority and the applicant submit such statements.

  14.  In our respectful submission, a considerable amount of time can be saved by effective use of such statements. We note that the definition of such statements in Rule 1 of the Rules refers to a written statement containing "full particulars" of the case which it is proposed to put at the inquiry. Bearing these points in mind, we have some practical suggestions:

    (i)  The issue of addressing a failure to prepare meaningful Rule 6 statement when exercising the discretion to award costs in relation to an inquiry has been addressed elsewhere. A pro-active solution might be for the Secretary of State to direct that a particular Statement fails to comply with the standards expected. We note the proposed change to Article 23 of the GDPO allowing the Secretary of State to refuse to accept an appeal in the absence of sufficient information. Power might be granted to the Secretary of State to prevent appeals from continuing where he considers there to be a failure to provide a proper Rule 6 statement;

    (ii)  We would also advocate an amendment to Rule 6(6) of the Rules to the effect that parties appearing at an inquiry must supply the Secretary of State and other parties with a statement of case;

    (iii)  Consequently, a longer time for preparation of Rule 6 statements may be appropriate, particularly where third parties are involved. It may also be helpful to amend the Rules to provide for simultaneous exchange of statements and to provide that pre-inquiry meetings (see below) are held after exchange. The meeting can then be used as an opportunity to discuss common ground where/if it exists and to identify the principal areas of dispute and how they are to be addressed.

  15.  Where an appeal is lodged against a local planning authority's failure to determine an application within an appropriate time, there is a particular problem to address: the non-determination may result from the fact that the local planning authority does not consider itself to have sufficient information, or sufficient time to evaluate the information submitted. To require it to reach a series of conclusions on the principal issues in order to prepare a statement of case introduces an element of artificiality. Conversely, the appellant cannot be entirely certain of what he is appealing against. The period for submitting a Rule 6 statement may have to be amended.

The role of the Inspector

  16.  Case management means that, once Inspectors are appointed, they stay with the appeal and are not (as frequently occurs) replaced at a relatively late stage. Ideally, much of the case management can be done by the Officers at the Planning Inspectorate, as they do now, rather than the Inspector himself. Such a system is likely to face the criticism that it is not always possible to predict that an Inspector will be in another inquiry which overruns. A more efficient system if imposed will make this less likely, but the fact that an Inspector has another inquiry should focus the efforts of all participants to ensuring that time estimates are realistic and then observed.

Pre-Inquiry meetings

  17.  Another suggestion is the introduction of a pre-inquiry meeting ("PIM") for all inquiries (although there might be a discretion to dispense with PIMs if the relevant parties and the inspectorate can agree that the issues which need to be considered are limited in number). PIMs would be held after Rule 6 statements had been exchanged and would allow the Inspector to focus on the points which can be addressed in evidence and (importantly) draw parties' attention to the issues which ought to be the subject of further discussions.

  18.  "Technical" issues should, where possible, be resolved by the use of written evidence. This does not mean that parties cannot make comments on the evidence. This could be done principally by submission and the Inspector can be invited to direct that witnesses be called. Alternatively, parties (including third parties) can be invited to suggest areas where there is common ground, perhaps by increased use of agreed statements. Failure to respond constructively to these invitations might then be a matter which can be addressed by way of an application for costs.

Notice

  19.  Efficiency is often best served by concentrating responsibility in the hands of the participant best able to ensure a particular outcome. In relation to ensuring adequate publicity for inquiries this means the local planning authority. Increasingly, notification has become an issue. It is crucial that notice of the PIM be given the same prominence as notice of the inquiry itself. We would respectfully suggest an alteration of the permissive language of Rules 10(6) and 10(7) of the Rules to ensure that there is a duty on relevant parties to publish notice of inquiries and to post site notices.

Planning obligations

  20.  We note that the Planning Inspectorate is informing applicants that Section 106 agreements must be completed before the inquiry. This means that local planning authority must negotiate with applicants. Too often there is deliberate delay and prevarication by local planning authorities in relation to section 106 agreements. If legal officers have no instructions then they should communicate this quickly to the applicants and that can be a matter for an application for costs. Failure or refusal by third parties to discuss agreements can waste a great deal of inquiry and other time. Third parties must be given a chance to understand the proposals in full, and this would include any relevant Section 106 ogligations, before the start of the inquiry. Radically, the PIM could even be used as an opportunity to invite suggestions from third parties as to the content of such obligations, although we would resist any move which allowed them to be a party to the detailed negotiations.

THE ROLE OF THIRD PARTIES

  21.  Third parties frequently have an important role in the inquiry process. The efficacy of this role is often undermined by the fact that the procedure rules pay little attention to the role or interests of third parties. Nor can third parties reasonably be expected always to have a grasp of the technical and complex issues. However, a combination of the lack of a real role, their unfamiliarity with the procedures and different focus invariably results in delay to inquiries. The need exists for advice which does not seek to alter the case they wish to make, but which can help them make it in the most effective and efficient way. In particular, it would be helpful to ensure that they understand the difference between evidence and submission, the difference between evidence and cross-examination and the fact that repetition is obstructive.

  22.  There has been a suggestion that mechanisms can be introduced to offer some type of administrative or professional assistance to third parties. In theory this seems admirable; such professionals can ensure that the cases are presented in the most advantageous way and that the administration of the inquiry is not disrupted by unfamiliarity with the procedural rules and failure to understand rules of evidence.

  23.  In practice, the important issue will be ensuring that the cost does not discourage participation. Importantly, there needs to be examination of how this cost is borne. It is unlikely that applicants and/or local planning authorities will be persuaded that they should finance the opposition. One suggested solution has been the introduction of an appeal fee to create a fund out of which third party assistance can be financed. Two potential problems suggest themselves:

    (i)  This has been suggested in the past, but as a way of financing in part the costs of the system (ie the Planning Inspectorate). That principle will have to be abandoned which might not be politically acceptable.

    (ii)  Difficulties exist in determining the level of such a fee. Importantly, care must be taken to ensure that it does not operate as a "fine" to anyone seeking to exercise their right of appeal, the practical consequence being that it must not discourage appeals.

  24.  Even if these objections can be overcome, how will such a fund operate? Whether or not this could be developed as some form of, or modification of, the legal aid system (so that a planning consultant/solicitor/barrister can be instructed to do a prescribed number of hours' work on behalf of each party objecting), it is unlikely to be politically acceptable to a government seeking to reduce the legal aid budget.

  25.  More efficiently, an assistant to the Inspector could be employed to co-ordinate the evidence and cases of third parties. The role would be akin to that of the programme officer. Although the assistant will take no part in the decision-making process, they might be given discretion to suggest that certain evidence is put in writing, and to "project manage" the evidence to be put on behalf of all objectors.

March 2000


82   In practice, potential areas of dispute can be, and often are, signalled by way of preliminary discussions and requests for further information. Regulation 4 of the Town and Country Planning (Applications) Regulations 1988 enables local planning authorities to direct that applicants supply them with further information and evidence and (except in the case of outline applications) plans and drawings. There is often difficulty in obtaining from officers confirmation that they have sufficient information to recommend a decision on the application to members. Back


 