Select Committee on Environment, Transport and Regional Affairs Memoranda


Memorandum by the Local Government Association (PI 49)

1.  INTRODUCTION

  1.1  The LGA welcomes the opportunity of submitting evidence to the Committee on the Planning Inspectorate. This response is based on comments collected by the Association from local planning authorities specifically for the Committee's inquiry, and from work the LGA has carried out itself, for example on the impact of the Human Rights Act. The principle representations the LGA would like to make to the Committee are under the following headings: general points; inconsistency of decisions; timing and delays; the Human Rights Act, and other issues.

2.  GENERAL POINTS

  2.1  The efforts made by the Planning Inspectorate to improve their performance—particularly in relation to the programming of S78 (planning application) inquiries is recognised and welcomed by the LGA. It should be noted that a number of planning authorities have written to the LGA to put on record that they are satisfied with the service provided by the Inspectorate in terms of speed and quality. Other authorities have, however, raised problems and it is these problems which this submission to the Environment Sub-committee the LGA will be focusing on.

3.  INCONSISTENCY IN DECISIONS

3.1  Draft government guidance

  Following the publication of draft PPG 3 in March 1999 local authorities have been keen to begin implementing the change in emphasis in government policy away from the development on housing on greenfield sites and towards brownfield development. However authorities do not feel that the Inspectorate gives sufficient weight to draft government guidance and this can be a particular problem when, as in this case, there is a general consensus that policy needs to change, and when there is a significant time lag between draft guidance and the Government's final version. In the case of PPG3 the period between draft and final version was a year, during which important and irreversible planning decisions have been taken. There is a pressing need for the inspectorate to take up draft advice as soon as it is issued and, possibly, a need for Government to issue guidelines which add to the weight Inspectors give to draft guidance.

3.2  Supplementary Planning Guidance

  We are in a period of major policy change in the planning system when both local and central government are seeking to switch development from greenfield sites to more sustainable brownfield locations, both to encourage the urban renaissance and to provide for the projected household growth. To be successful significant shifts in policy are needed at the national and local level. The planning system has been criticised in the past for being inflexible—the LGA would like this criticism to be addressed by Inspectors, who need to take on board the implications of new government guidance as quickly as possible, and by local authorities, who need to keep their development plans up to date. In the latter case the LGA is advocating the use by local authorities of Supplementary Planning Guidance (SPG) which can be drawn up and consulted upon quickly and can keep pace with fast-moving regeneration schemes. Local authorities often complain that the Inspectorate does not give sufficient weight to SPG and the LGA would like the Government to issue stronger guidelines to tackle this issue.

3.3  Specific policy areas

  There are a number of specific areas of planning policy where authorities have identified inconsistencies in decisions by Inspectors. These highlight the need for clearer Government policies and for clearer guidelines for Inspectors. Examples which have been brought to the LGA's attention are: A3 uses in shopping centres—there are very different interpretations between Inspectors about what constitutes an A3 use; mineral working in the Green Belt—what level of working compromises the "openness" of the Green Belt; extensions to dwellings in the green belt—again Inspectors' definitions of how "openness" was defined appear inconsistent, as does the significance placed by Inspectors on the size of the original dwelling.

4.  TIMING AND DELAYS

4.1  S78 Inquiries

  As stated as a general point, the speeding-up of S78 (planning application) inquiries in recent years is welcomed. However there is a danger of the pendulum swinging too far and timetables becoming more important than the wishes of the appellant and/or the local authority. The Inspectorate need to give both parties sufficient time to submit Rule 6 statements covering areas of agreement, and for the authority to arrange a venue.

  4.2  A further point on S78 inquiries is that authorities have noted an inconsistency in the acceptance of late appeals by the Inspectorate. There are examples of appeals being rejected on the day of expiry, and examples of appeals being accepted three weeks after the deadline. If appeals are to be accepted after the expiry date, the Inspectorate should be given clear reasons why this is the case.

4.3  Local Plan Inquiries

  The LGA places a high priority on speeding up the development plan process and recognises that the Local Plan Inquiry (LPI) plays a major role in this. Very recently the LGA has made strong public statements about the need for planning authorities to keep their development plan up to date and to devote sufficient resources to the process. In response to the Committee's call for evidence, the Association has received representations from local planning authorities on how the inspectorate could improve its performance.

  4.4  Generally it is considered that Inspectors could take a more active role when the inquiry is underway. In particular they could: define issues which they need the parties to address, intervene more to rule out irrelevant or repetitive evidence, and curtail the excessive time taken by some advocates. The LGA is promoting the use of much more strategic and less detailed development plans as a way of speeding up the plan process; this approach would allow Inspectors to concentrate on the key issues and would avoid dealing with minor issues in excessive detail. Authorities are also frustrated by the amount of time it takes Inspectors to produce their reports; this could also be tackled by a more strategic approach to development plans and encouraging Inspectors to rule out irrelevant evidence and concentrate on key issues. These points indicate the need for both stronger guidelines for the Inspectorate and a more fundamental review of the development plan process.

  4.5  A final point on local plan inquiries: it is crucial that the Inspectorate keeps authorities fully informed of the progress of the Inspectors report. For example authorities need to be notified of the potential early production of a report so that arrangement can be made for publication and to make appropriate resources available.

4.6  Delays due to Government Regional Offices

  A significant number of authorities referred to the role played by government offices in slowing down the planning process, both in terms of planning appeals and local plan inquiries. Authorities have expressed frustration at the length of time Government Offices hold onto Inspectors' reports before releasing them, and the lack of any definite timetable identifying when decisions will be taken. Examples were given in the south-east and the north-east of what were seen as excessive delays due to Government Offices. The excessive number of objections made to local plans by government offices has also been cited, as has their reluctance to conditionally withdraw objections.

5.  THE HUMAN RIGHTS ACT—IMPACT ON THE INSPECTORATE

  5.1  The LGA has undertaken some work on the implications of the human rights legislation for planning authorities. However, the DETR have stated that they will not be producing guidelines themselves and that disputes will need to be resolved in the courts. The Association recognises that some matters can only be resolved in the courts, but that the absence of any guidance specific to planning from Government is unhelpful. We feel that all those involved in the operation of the planning system would benefit if DETR were to explicitly address and communicate the Human Rights Act, and the European Convention on Human Rights (ECHR) considerations that have informed legislation, policy and guidance. Similarly, although we understand that the Inspectorate is making preparations for the Act, it would be helpful if the detailed advice to Inspectors is widely circulated.

  5.2  Current case law indicates that the planning process is compatible with the Human Rights Act because the totality of the appeal process, including the right to appeal to the High Court, is fair. Difficult issues may remain to be resolved, for example in a case where the actual decision is taken by the Secretary of State disagreeing with the Inspector on a point of fact.

  5.3  The whole area of third party rights of appeal needs to be reviewed by the Government in the light of the European Human Rights Act. At a conference held by the LGA in January a leading planning lawyer expressed his view that the Act meant that the eventual adoption of 3rd party right of appeal by authorities was "inevitable". It has also been suggested that in the shorter term, protecting the Article 6 rights of third parties is likely to lead to a greater use of call-in powers by the Secretary of State. This would have a knock on effect throughout the system, including increased workload for the Planning Inspectorate. The Inspectorate would no doubt need more resources to cope with this increased workload. In the long term it would be reassuring to know that the Government and Inspectorate are at least considering the implications of the extension of the right to appeal to third parties; and for the DETR to make known any revisions to the criteria they will apply when considering call-in.

  5.4  There is little doubt that the scope of relevant Articles of the ECHR will be tested in planning matters. The LGA hopes that procedures and decision-making will not become bogged down by ill-founded claims; it will be important for the Planning Inspectorate to deal robustly and efficiently with Convention points, so that lessons may be taken on board at an early stage by all concerned.

6.  OTHER ISSUES RAISED: COSTS AND COMPLAINTS/FEEDBACK

6.1  Costs

  Authorities sometimes have difficulty in seeing the justification for the award of costs. The process can seem arbitrary and when costs are awarded the local authority and appellant can become involved in a protracted debate as to the appropriate figure. There appears to be a case for clearer guidelines and more detailed justification by Inspectors.

6.2  Complaints/feedback

  There will always be individual decisions which local authorities cannot see the Inspector's rationale or on which they would welcome clarification. Although an authority can complain to the Inspectorate about a specific decision, there is often a feeling that the complaint has not been heard. It is unsatisfactory that the only forum where a dialogue can be entered on a specific decision is the High Court. An alternative process would be welcome.

  7.  The Association would be pleased to appear before the Committee to go into the evidence in more detail and to answer questions if necessary.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 2000
Prepared 23 March 2000