Select Committee on Environment, Transport and Regional Affairs Minutes of Evidence


Examination of Witnesses (Questions 120 - 126)

WEDNESDAY 12 APRIL 2000

PROFESSOR STEPHEN GLAISTER, MR DECLAN GAFFNEY AND DR JEAN SHAOUL

Chairman

  120. You are saying neither of those will apply?
  (Professor Glaister) Correct.

  Chairman: Thank you. Dr Ladyman?

Dr Ladyman

  121. Two questions, the first one to Dr Shaoul and Mr Gaffney. In your supplementary evidence to the Committee you seem to indicate that the distorting factor in the public sector comparator is being removed by the fact that it is going to be a comparison against bond issue with the revenue being spread over a period of time. That seems to me a positive statement about the fairness of the public sector comparator, which is later contradicted by pretty much everything else you say. Would you clarify your position on that.
  (Mr Gaffney) I do not think it is contradictory. What we said was "subject to the reservations below", is the phrase we use in the note, that this did remove a distortion from earlier public sector comparators. The technique used in all economic appraisal of PFI schemes is one which is based on discounted cash-flow analysis where expenditure which is scored in later years counts for less than expenditure which is scored in earlier years. By convention public sector procurement capital costs tend to be allocated to years in which the expenditure actually occurs rather than treated as being spread out. Basically you assume that government or the public sector cannot spread its costs through borrowing and when it comes to, for example, NHS hospitals where you might have costs of £100 million in the first two years with the public sector contract which are spread out over 30 years of a PFI contract, those two things together constitute a distorting mechanism. You front load the public sector expenditure and then discount it at a discount rate which is also regarded by many people as being far too high anyway. The reservations to that were, first of all, that there would be a lot of subjective elements in the assessment of the cost and risk, and this has been another major distorting factor in previous PFI economic appraisals. A major reservation, which related to an ambiguous passage in the document issued last week concerned the cost of finance under the bond issue where the authors of the document say that the interest rate on a bond issued by London Underground could be expected to be at a certain level. However, it implied that this did not capture the full cost of capital in that instance and, therefore, that they should use a different rate, which would have been up to 2.5 per cent higher, in order to fully reflect the cost of capital. I cannot see in that document any argument which would support raising the interest rate in this way. It is implied that this is to take account of the cost of government guarantees on any bond issue by a public authority. As far as I can see, there is no extra cost which would justify raising the interest rate in that way, and that is a major reservation.

  122. Professor Glaister, we have just been through a fairly traumatic experience with the Jubilee Line, where the cost was much higher than expected and the project took a lot longer than it was hoped. To what extent is it reasonable to assume that the PPP would eliminate, or have eliminated, that sort of cost over-run and time over-run? Therefore, to what extent can we learn from the Jubilee Line experience what assumptions are appropriate when we do our public sector comparator?
  (Professor Glaister) There are a lot of issues in that question. The first observation I would make is that the Jubilee Line Extension was finally sorted out by the employment of Bechtel as independent management consultants. That is exactly the kind of procurement of service within the public sector which I would see being perfectly available to a Mayor if the whole thing stayed within the public sector. Secondly, there were all sorts of reasons why the Jubilee Line Extension over-ran. One of the difficulties was that that was a big contract where the contractors were not able to deliver what they promised, for all sorts of reasons, and they were in a very strong position to extract more money from the public sector to finish the work. I see that as being precisely the kind of position that the PPP would risk putting the Mayor and the Assembly into with a 30 year contract, with a first review only after seven and a half years. It would be very difficult to enforce these contracts rigorously were the contractor to fail to deliver. So, yes, I think that there are things to learn from the Jubilee Line Extension and I do not think it is all one way, it is a lesson on both sides of the argument.
  (Dr Shaoul) I would like to get you to consider that the finance initiative has had similar problems and yet the contractual relations are very similar for the PPP. You have only to think of the Benefit Agency contract where Andersons Consulting ended up with a fine of £3.9 million, and yet the Government is out of pocket to the tune of hundreds of millions of pounds. It is not at all clear to me—and I have looked at some of the legal contracts and legal issues—that these contracts are going to be enforceable.

Chairman

  123. I do not want to go backwards. I think we have a clear picture now.
  (Dr Shaoul) The answer to the question as well is that the Jubilee Line was concerned with very difficult tunnelling work and most of these tunnelling projects face problems. You have got to remember the PPP. We are talking about a large number of relatively small scale projects which are quite different to manage.

Dr Ladyman

  124. Are you saying that the sort of practical experiences that people like Professor Currie are using in order to back up assumptions for the PPP are not real factors that we ought to be considering and that there is nothing that we can learn in that way in order to build in those assumptions?
  (Mr Gaffney) You referred to what we can learn from the JLE with regard to the public sector comparator. I have a grave concern that when it comes to design the PSC, London Underground will learn far too much from the JLE. We have seen this already in the NHS where assumptions on cost over-runs, which were supposedly based on historical cost over-runs in the NHS, have the effect of bumping up the price of public sector comparators to quite outrageous levels. Trusts were regularly making use of assumptions that all NHS capital projects over-ran by figures between 17 and 25 per cent. These figures were actually imaginary, the real figures were closer to 6 per cent. This then led to over-valued public sector comparators which, therefore, made greater spurious value for money on the PFI side. If the JLE is used as an example to work out the kind of historical cost over-runs which should be used in assessing the risk under the PPP contract, there will be a serious distortion.
  (Professor Glaister) You said, "Should we ignore Lord Currie's evidence?" No, we should not. It is well established, but you must look at the assumptions and look at the circumstances in which those 20 per cent cost savings were got historically. It is repeated competition with open labour markets, it is not a one off thing with protection for the transferring employee, which is a different game.

Mr Donohoe

  125. When you were answering a question earlier, you indicated that there were better options than the PPP. What would you say they were?
  (Professor Glaister) My fundamental difficulty with the PPP is this inflexibility with a 30 year contract, and even with a first review after seven and a half years. I would look for a way of getting cost savings from private sector involvement, which is much quicker and more flexible and which divorces the raising of finance from the commissioning of the work. I think one that would be worth looking at is leaving it in the public sector, a funding trust to do the funding with revenue bonds to raise the finance, but not necessarily government backed, and then letting out the Underground lines on a line by line basis for a period of five or seven years. You keep those as integrated businesses, you have management contracts and you compete for those just as they did with the buses. Basically it is by direct contract managing, and it was a very successful experience on London Buses. I hope that will be used in the comparator.

  126. It is possible that the proposals for the PPP as they are, are going to come up against the buffer because of the fact that they have to do the calculations on the basis of the fares and the increasing number of usage, when in fact, if anybody uses the underground, they will know that it will be almost impossible at peak times to get any more passengers on board. Do you think that is a problem in its own right as well in terms of the basic undertaking that has been taken?
  (Professor Glaister) That is a kind of engineering and economic judgment that one would want to look at. On the face of it, it does seem strange that you can get 40 per cent more passengers onto the existing system. You would certainly get more through it if it worked more reliably. If it is a problem, it faces any of these solutions. The future revenues over 30 years are very, very hard to predict and the shortfall will fall on the Mayor and the London Assembly whichever way we do it.

  Chairman: I am very grateful to you. You have given us a lot to think about. Thank you very much indeed for coming this afternoon.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 17 July 2000