Select Committee on Environment, Transport and Regional Affairs Appendices to the Minutes of Evidence


Memorandum by The Royal Academy of Engineering (FLU 08)

INQUIRY INTO THE FUNDING OF LONDON UNDERGROUND

  GENERAL COMMENTS

1.  Fellows recognise the importance of London Underground to the capital city. For example, 90 per cent of London commuters use the Underground for part or all of their daily journeys, and a similar percentage of tourists also use the system as the principal means of transit in and around the capital. With over 110 miles of route in tunnels mainly beneath the streets of inner London, the Underground is a large complex system, with long lived structures and equipment . However, it is also recognised that there is still some way to go in the provision of what has been described as a "decently modern metro" partly reflecting, it is believed, the inadequacy and variability of funding over many years.

THE LEVEL OF FUNDING REQUIRED BY LONDON UNDERGROUND

  2.  The backlog of investment referred to above, whilst substantially reduced over the last few years, still amounts to the £1 to £2 billion calculation produced by London Underground Estimating the scale of this backlog is complicated however by the difficulty in accessing and evaluating the Underground's assets, compounded by their intensive use and the disruption caused by taking them out of service. Consequently, and in the interest of prudence, this figure may need to be higher although the magnitude is not known.

  3.  In addition to the cash requirement to eliminate the investment "backlog", Fellows believe that an estimate of £400 million plus annually to replace existing assets which have come to the end of their useful life is realistic, and would provide a "steady state" situation. However, this does not make any significant provision for the enhancement of the system and the more rapid introduction of new technology, for example, new motive systems which allow the cross sectional area of carriage saloons to be significantly increased, and the introduction of air conditioning. Such improvements are believed to be measured in hundreds of millions of pounds.

  4.  There are other measures required to improve the system in addition to those indicated above. These include enlargements of some busier stations, better and more direct links to improve interchanges, the lengthening of some station platforms, and addressing some of the severe limitations which exist in the older parts of the system including narrow tunnels, short and narrow platforms, cramped ticket halls etc. The funding of such activity is likely to be very substantial, although impossible at this stage to quantify.

  5.  The continued growth in the use of the Underground—some 900 million journeys this year compared to 500 million in 1982—raises important questions about the extension of the system's capacity if continuing congestion is to be avoided. Figures available to Fellows indicate that over the next 20 years the capital expenditure requirements will be in the region of £16 to £17 billion. This includes the recovery of the backlog (£1 to £2 billion), ongoing renewals (£8.0 billion), modernisation and system enhancement (£2 billion) and system extension (£5 billion).

THE DEVELOPMENT OF PUBLIC-PRIVATE PARTNERSHIPS (PPP)

  6.  Based on the limited information available, Fellows consider that there are some key issues which bear on the proposal's efficacy. It is assumed that the Underground will remain in the public sector but that private groups (Infracos) will have responsibility, under contract to the Underground, to finance, maintain and modernise its infrastructure. It is also assumed that the intention is to employ private capital to "catch up" the investment backlog unconstrained by short-term public expenditure restrictions, and to allow the Infracos the freedom to achieve efficiency gains in carrying out this work.

  7.  The merits and de-merits of such a PPP arrangement are complicated, but may best be expressed as the following:

    (1)  Private sector efficiencies through innovation and competence in the delivery of pre-determined investment packages may be achieved, but will the cost savings more than outweigh the extra cost of private sector financing?

    (2)  whilst PPP opens up the possibility of considered long-term planning of the improvement and maintenance of the existing system and more efficient procurement of major capital activities, it may also introduce substantial constraints on the future shape of the maintenance and improvement programme and additional costs and complexities that could otherwise be avoided;

    (3)  with PPP there exists the danger that the relationship between the Infracos and London Underground could become adversarial, and it is not clear to whom the Infracos will report. If Transport for London sets the output specifications, will London Underground be responsible for the delivery through its own operation, and through Development Agreements entered into with each PPP? There may be a serious role here for a regulator to ensure fair play!

  8.  The principles underlying PPP are generally regarded as acceptable by Fellows, but many doubts remain over the practical operation of the scheme. It can be regarded as a "hybrid" solution to a complex problem, which will require constant vigilance by all parties to ensure the maintenance of excellent communications in the interests of the efficiency of the train operators, and a well defined and understood command and control structure which assumes especial importance in times of emergencies.

ALTERNATIVE PROPOSALS TO MEET THE UNDERGROUND'S FINANCIAL NEEDS

  9.  It has been suggested that it may be erroneous to divorce the problems of the Underground from the issue of transport in London as a whole, and that a holistic approach which looks at London's transport and land use as an entirety is needed. For example, the Crossrail scheme, in conjunction with the national railways, could relieve congestion on the Underground but as a consequence could result in falling revenues.

  10.  Some of the disadvantages of the PPP arrangement outlined in paragraphs seven and eight above, could be overcome by an alternative method which allowed the Underground to borrow through conventional loans or bonds with the significant proviso that the costs of such borrowing are not significantly higher than that enjoyed by the Government. Bonds could be issued against the security of road charging revenues. In New York, the Metropolitan Transport Authority issues bonds secured at attractive rates against future revenue streams, to fund its capital programme for the New York Subway. Additionally, thought might be given to raising revenues for the Underground by levying charges on businesses which benefit from the services provided by the Underground, as would appear to be the case in Paris.

11.  CONCLUSIONS

  In general, there is realisation that the current system and level of funding of the Underground is inadequate to meet the full financing requirements of a network which not only has to "catch up" on a funding backlog, but needs further additional investment to enhance the system. The proposed PPP is regarded as a way forward which may address these issues, but there are reservations concerning the costs of private financing, and on the need for clear lines of responsibility with the partners concerned. The possibility of issuing bonds coupled with a system of Government grants, presents an attractive alternative which warrants serious consideration.

March 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2001
Prepared 17 July 2000