Select Committee on Environment, Transport and Regional Affairs Appendices to the Minutes of Evidence


Supplementary memorandum by the Department of the Environment Transport and the Regions (FLU 12A)

FUNDING OF LONDON UNDERGROUND

  Thank you for the letter of 18 April in which asked some supplementary questions which are reproduced, with the Department's response, below.

At what stage will the National Audit Office scrutinise the public sector comparator and when will its opinion be published?

  This is a matter for the NAO itself. They have already made clear that they cannot get involved in the decision-making process on the PPP; though the Department has asked for, and received, guidance from them on the preparation of the comparator. It will be up to the NAO to set a timetable for any study it wishes to make into the PPP.

Will the results of the comparator tests decide whether the PPP bids are accepted or will equal importance be placed on the satisfaction of other criteria?

  As we have indicated previously, the PPP will only go ahead if the bids are shown to represent best value when tested against the public sector comparator. It is nevertheless conceivable that bids might not be accepted for another reason, for instance, if we were not satisfied that a bidder was financially sound, technically competent or that their proposals would make an active contribution to improved safety.

What estimate has been made of the total amount that will be spent by London Transport on consultants' advice on the PPP? Will all of LT's contracts with its PPP advisers continue to be on the basis that both it and the Department are advised jointly?

  It has never been the practice to answer questions about future costs of advisers while a project is still under way. The Government and LT are doing everything possible to ensure that costs are kept within an appropriate figure. The Government is committed to giving periodic updates of costs and will also give the total costs of advisers working on the project once it has been completed.

  In seeking to obtain best value for money, London Transport and the Government makes decisions on a case-by-case basis about how external advisers should be employed. It seems reasonable at this stage to assume that those advisers who currently provide joint advice will continue to do so.

Is there a case for Government-backed bonds of the type used to help pay for the Channel Tunnel Rail Link being used to raise finance for the Underground?

  Not a good case. The use of private-sector bonds backed by the Government on CTRL was a solution tailored to the circumstances of that transaction. In the case of the Underground PPP, benefits will flow from transferring risk to the private sector, which could not be achieved as effectively with Government backed-bonds. These would consequently not represent best value, and would also count as public spending.

  It remains the case that we expect that the private sector infrastrucure companies taking on the Underground work will issue their own bonds to raise the finance for investment.

Please confirm whether or not it is intended that proposals for the Croxley Link project and the proposed extension of the East London Line (with the first stage to Dalston) will be taken forward as part of the sub-suface lines PPP. If not, please explain the reasons for an apparent change of policy as, in his oral evidence to the Sub-committee on 15 December 1999, LT's Chief Executive expected these proposals to be included in the agreement.

  The shadow Strategic Railway Authority (sSRA) is advising the Government on the best way of implementing north-south integration through the East London line and its proposed extensions. Depending on the conclusions of the sSRA's work and the Government's subsequent decision, bidders for the Sub-surface lines contract may be required to price separately, against a detailed scope of work for construction works to link the East London line to the national rail network.

  In the case of the Croxley link, it would be for the Mayor to consider whether to build an extension and the Major Enhancement Agreement (see below) provides a mechanism for implementing such a decision.

After the PPP contracts have been let, would the incumbent infrastructure companies not be in a strong bargaining position in any negotiations about new lines and extensions which might place the operating company at a disadvantage?

  The PPP contractual arrangements will include provisions for major schemes to increase capacity at stations and provide for line extensions. The scope and timing of such schemes will need to be worked out on a case-by-case basis and they will often require TWA orders or other consents, which may sometimes lead to design changes. London Underground therefore intends to design such schemes jointly with the responsible infrastructure company and to commission the company to deliver the work, provided it can demonstrate value for money.

  We would normally expect the company responsible for the station or line in question to be best placed to offer value for money in implementing major enhancement projects. But London Underground can choose a different contractor if the infrastructure Company's price is not competitive. In such circumstances, the infrastructure company would still have to provide (and would be paid for) any essential works which could not be provided by a third party. These arrangements ensure that the London Underground operating company can benefit from the efficiencies which an incumbent infrastructure company could offer (for example by co-ordinating work on a major enhancement with its routine maintenance and upgrading work on the existing line) while not constraining London Underground's freedom to look elsewhere if the price is uncompetitive.

8 May 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2001
Prepared 17 July 2000