Select Committee on Environment, Transport and Regional Affairs Sixteenth Report


ANNEX 1

Notes of a meeting of the ETRA Committee and European Commission Officials,

Mr Wouter Pieke (Head of Unit "Regional Aid)and Mrs Cristina Calabro on Thursday 11 May 2000 (Mr Pieke answered most of the Committee's questions)

Through the Partnership Investment Programme (PIP), English Partnerships provides gap funding, ie. additional funds to private developers for schemes which they would not otherwise undertake. This is usually where there is high risk and/or low demand. The scheme involves a claw back mechanism.

Under European regulations all programmes of assistance offered by Member Countries are required to be notified to the Competition Directorate General of the European Commission. The PIP was notified to the Commission in January 1995 and in May 1995 the Commission determined that the scheme was not subject to state aid restrictions. However, the Commission subsequently reviewed this decision and on 22 December 1999 the Commission decided that the whole amount of the gap funding, including the elements allowed for "site abnormals" and developer's profit, constitutes an economic advantage offered to the developer. This is because the whole of this amount is needed in order to enable it to engage in what the Commission defines as a "commercially non-viable investment" which would not have been carried out in the normal course of business. The EC is concerned that PIP might give an appreciable advantage to recipients in relation to their competitors and is likely to benefit undertakings engaged in trade between Member states

The Committee was told that the anti-competitive elements of the scheme had not been perceived in 1995, but were subsequently brought to the Commission's attention and had led to its decision in 1999. The Commission did not aim to hinder the development of derelict sites, but did not want competition to be distorted. In the Commission's view gap funding could lead to a distortion in the following ways:

  • It could provide a windfall to the owner of land (which might, for example, be a car or chemical manufacturer), hence giving it an unfair advantage over other companies in the same sector;
  • It could provide a subsidy to a developer, and hence might (for example if it were a property developer which was active internationally) give it an unfair advantage;
  • It could provide a subsidy to the organisation which rented the new premises, and hence give it an unfair advantage.

We were told that the Commission's ruling affected the UK particularly badly, because in other countries -

  • Planning permission was more difficult to get on greenfield sites, so there was more incentive to develop brownfield sites;
  • Local Authorities were more likely to use compulsory purchase orders.
  • Local Authorities were more likely to be the owner of the land - it was far less common as in the UK for the owner to be the developer.

The situation was now that:

  • The Competition Directorate's decision has made a distinction between speculative development with a developer as the beneficiary and bespoke development;
  • Speculative development could not go on as it had and a new draft scheme was needed to take its place;
  • The Commission saw no problem with bespoke development taking place within assisted areas; and within the aid limits allowed there
  • Any development outside assisted areas would require a new draft scheme which will need to be approved by the Commission; and
  • Schemes where the Local Authority was the owner and developer were unlikely to cause any problems.

Various possibilities were being explored to enable the development of derelict sites to be funded without distorting competition. Commission officials had had discussions with Mrs Armstrong and her officials about a new scheme*. As a result of the Commission's decision, where there was speculative development in the UK it needed to take account of the Commission's state aid policy. The way forward appeared to be to split up regeneration projects. Decontamination, providing infrastructure on contaminated sites and building dwellings would not be a problem. It should be possible to say that part of the financing covering these areas was compatible aid or not state aid at all and would hence not fall foul of the Competition Directorate General. However any windfall gain should not be state aided.

Mr Pieke was optimistic that a solution could be found. The Commission takes a positive approach to regeneration as such and hopes to be able to approve a new aid scheme.* The Competition Directorate General had had a meeting on 15 March with the UK authorities. After this the latter were carrying out simulation exercises and had agreed to provide additional information. The information requested from the UK had not been provided yet, but once the proposals had arrived the EC was keen to find a way forward. At the same time the EC was waiting for the new assisted areas maps proposals from the UK.

A final possibility was to look at the public service exemptions from competition policy under Article 86, if regeneration were to be presented as a public service..

*A Regeneration Framework


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 September 2000