Select Committee on Environment, Transport and Regional Affairs Appendices to the Minutes of Evidence


Memorandum by the Local Government Association (GF 12)

THE IMPLICATIONS OF THE EUROPEAN COMMISSION RULING ON GAP FUNDING SCHEMES FOR URBAN REGENERATION IN ENGLAND


INTRODUCTION

  1.  The Local Government Association (LGA) is the representative body for all local authorities in England and Wales. The LGA is committed to working closely with its member authorities to support reform and improvement in local government. The Association welcomes the announcement by the Environment, Transport and Regional Affairs Committee, that it is to carry out an inquiry into GAP funding schemes for urban regeneration in England. In the short time available, the LGA has invited a group of local authorities with particular expertise in this area, to comment and this response combines the key issues made within all responses received. Individual local authority responses are available on request.

  2.  This short memorandum follows the format of the topics for investigation as outlined in the Committee's press notice 39/1999-2000, dated 15 June 2000.

THE CONTRIBUTION THAT GAP FUNDING HAS MADE IN REGENERATING DERELICT AND OTHER DIFFICULT SITES IN AREAS OF "MARKET FAILURE"

  3.  There would also seem to be important points to be raised in terms of the interpretation of the term "gap funding". The term GAP funding is here taken to mean public sector funding which covers the difference between developer's costs and returns to make a project viable. The UK has a history of utilising GAP funding mechanisms in order to enable the redevelopment and regeneration of "marginal" land and buildings. These are buildings and tracts of land where the private sector would not get a return on their investment.

  4.  If we assume "GAP funding" to include those programmes which are designed to stimulate investment in site reclamation and the improvement of employment premises in areas where adverse site conditions and market factors have impeded/inhibited investment, this would include a substantial proportion of local authority physical regeneration activity.

  5.  Local authorities responded very positively to the principle of GAP funding when it was first introduced as in England as Urban Development Grant (UDG) and subsequently replaced by City Grant (CG). The Partnership Investment Programme (PIP) which continued the principle of GAP funding for regeneration is a vital component of local authorities regeneration strategies, enabling derelict brownfield sites that would otherwise remain undeveloped in disadvantaged areas to be brought forward for successful regeneration. Within a densely populated country such as the UK, there is an exceptional need to ensure that derelict and contaminated urban sites can be brought back into productive use.

THE CONSEQUENCES OF THE EUROPEAN COMMISSION RULING FOR URBAN REGENERATION

  6.    The effect of the EC decision is to allow a far more limited range of instruments available for carrying out physical regeneration. More particularly, outside areas eligible for State Aid within the UK "Assisted Areas" map, to eliminate GAP funding as a mechanism. Even within these "Assisted Areas", use of public funds as GAP funding is limited to the Commission's aid limits applying within these areas. The position is further complicated in that the UK Government and the Commission have yet to reach agreement on the precise boundaries of the areas designated as "Assisted Areas". The LGA would urge that this issue be resolved as quickly as possible.

  7.  There are many areas such as historic town centres, which may be in need of considerable physical regeneration, but which are extremely unlikely to enjoy Assisted Area or ERDF Objective One or Two status. In such areas the prospects for employing GAP funding measures as a result of the Commission's decision are likely to be bleak.

  8.  Some specific schemes in which GAP funding played a key role and which would potentially have been affected by the Commission's decision, are listed in appendix 1. The LGA would be happy to provide the Committee with further information of these if required.

  9.  The scale of the problem can be illustrated by the larger scale example of the city of Birmingham.

CASE STUDY—BIRMINGHAM

  Monitoring of Birmingham's industrial land supply currently indicates a shortfall of at least 25 ha in terms of readily available best urban land when measured against Unitary Development Plan targets.

  The need for intervention is further demonstrated by the fact that there is currently some 74 ha of industrial land (of which the local authority is aware) which cannot be developed due to the need for remediation, infrastructure provision and site preparation works. Without positive action to bring this land forward for employment purposes it will come under pressure from higher value uses such as retail and residential development. To put the situation into perspective, if a developer were to approach the authority tomorrow looking for a readily developable 15 acre site, it would be unlikely to be able to provide it.

  In January 1999 an independent study into Birmingham's Industrial Building Stock was completed by GVA Grimley, International Property Advisors. This found Birmingham's industrial building stock to have "a number of weaknesses, including poor accessibility and local congestion, unattractive image and a legacy of older properties increasingly unsuited to modern needs".

  This finding is borne out by the fact that over 75 per cent of the UK's industrial building stock was constructed before 1970, with this "age problem" likely to be worst in traditional industrial areas such as Birmingham (RICS). There is growing evidence that problems in terms of the provision of sites and premises have resulted in both the loss of existing Birmingham companies to the area and in our failure to attract new investment projects. Whilst some of these may have gone elsewhere in the region (Solihull/Sandwell), it is inevitable that many have been lost.

ALTERNATIVE SCHEMES THAT COULD BE CONSIDERED TO REPLACE GAP FUNDING

  10.  In terms of alternatives, equity, loans and rental guarantee schemes have been used to a very limited degree by local authorities but could be seen as not readily accepted by the private sector. The other option is, of course, direct development, which in terms of the need for acquisitions etc would prove far more expensive. This option would also give rise to issues around private sector leverage public sector ownership, and market realities in situations in which only one agency was involved—ie would those sites with seriously negative values ever get picked up.

THE SCALE OF PUBLIC FUNDING REQUIRED TO ENABLE ALTERNATIVE SCHEMES TO PRODUCE EQUIVALENT RESULTS

  11.  The direct development option as suggested above would be likely to prove anywhere in the region of four to 10 times more expensive that the current GAP funding measures.

  12.  There are serious concerns about the implications of the decision for the cash flows of RDAs. According to the Government's own figures PIP last year alone levered in £567 million of private investment. Although schemes currently underway will not be affected by the decision, the main implication will be that RDAs and local authorities will now be faced with the need to carry out much more direct development requiring them to acquire the land for development first.

WHAT PROVISIONS SHOULD BE CONTAINED IN A NEW REGENERATION FRAMEWORK

  13.  The LGA agrees with the following list of characteristics of a new regeneration framework as outlined by the RICS.[2] Any alternatives to PIP funding for urban regeneration should contain:

    —  a strategic policy framework that is supported at national and regional level and is fully understood by a full range of public and private sector partners;

    —  application to a range of themes and spatial priority areas, including non-Assisted areas;

    —  an outcome-driven approach linked specifically to RDA strategic objectives and outcomes;

    —  co-ordinated funding bringing together, as a minimum, the Single Regeneration Budget and English Partnership programmes into a single scheme; and

    —  competitive procurement processes to enable the public sector to intervene at the level necessary to achieve the required outputs via private sector partners at "best value" and thus be compatible with State Aid restrictions.

June 2000


2   Alternatives to the Partnership Investment Programme, RICS, February 2000. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 September 2000