Select Committee on Environment, Transport and Regional Affairs Appendices to the Minutes of Evidence


Memorandum by the Department of the Environment, Transport and the Regions (GF 13)

IMPLICATIONS OF THE EUROPEAN COMMISSION RULING ON GAP FUNDING SCHEMES FOR URBAN REGENERATION IN ENGLAND


BACKGROUND

  1.  The Partnership Investment Programme (PIP) which was in operation until 22 December 1999, was a programme run by English Partnerships (in England only, similar schemes applied in Scotland and Wales) offering assistance in the forms of grants and loans to private sector developers to undertake projects to bring derelict sites and buildings back into productive use. It was used for projects where the costs of development were greater than the end value of the development would be (because of local property market failure, resulting in depressed project values and abnormal site reclamation costs)—and where no developer would go ahead without assistance, because he would not make a profit.

  2.  PIP was based on the principle of "gap funding", which meant that, following a full appraisal of the developer's application for assistance, the amount awarded would be the minimum necessary to bridge the gap between development costs and forecast end value, and enable the developer to go ahead. PIP could be used for projects promoted by developers on regeneration sites throughout England (ie it was not restricted to the Assisted Areas). PIP was used to support either speculative projects (where the developer was building without a known end-user in mind), or bespoke projects (developed for a known end-user).

  3.  The gap funding approach had been used for regeneration projects involving partnership working with the private sector since the late 1980s—firstly in the Urban Development Grant regime, and then in City Grant, prior to the creation of the Partnership Investment Programme.

  4.  European Commission review of PIP to assess its compliance with the State Aid rules—in May 1995, the European Commission declared (as part of a decision on the Single Regeneration Budget (SRB)), that a number of measures included in the SRB were not caught by the terms of Article 92(1) of the Treaty—English Partnerships' regeneration activities (including PIP) were amongst these measures, (ref Case 31/95, Single Regeneration Budget). However, within a year, the Commission looked at PIP again, because as the Commission said in their 22 December 1999 decision "Following the approval of the SRB, the Commission's attention was drawn to certain cases where the beneficiaries of EP assistance were also enterprises competing in intra-community trade".

  5.  In January 1996, the Commission asked the UK authorities to provide clarification on the actual functioning of PIP. Discussions on the State aid compliance of PIP went on for the next two years, with Ministers and English Partnerships arguing that PIP was not in breach of the rules, because the grant given was the minimum necessary to bridge the cost/value gap, did not confer an unfair competitive advantage on the developer, and that the developers were in any event engaged in an activity (development of derelict land) where there was negligible (if any) trade between European Member States. The Commission also had concerns that the eventual recipient of the support under PIP was the party which had initiated the proposal—rather than the public sector making the proposal and selecting a partner through an open competition.

  6.  The Commission issued an "appropriate measures" letter in July 1998, (ref SG(98)D/061108) under which the Commission formally declared its intention of establishing whether State Aid was involved in the operation of PIP, to identify any such aid, and bring it into line with the requirements of the EC Treaty, and State Aid rules. In July 1999 the UK decided that it would treat bespoke developments within the State aid rules. The UK accepted that there was merit in the Commission's argument that there was a possibility of State aid where firms were developing for a known end user, because the value of the end development to the particular user would be greater than the value of that development on the open market, and the valuation could therefore include an element of benefit to the end user. The UK therefore offered to bring bespoke projects within the Regional aid framework from mid-1999 (in the UK's response to the appropriate measures letter 28 April 1999).

  7.  EU decision on PIP—at a meeting of the Competition Directorate (DGIV) of the European Commission on 22 December 1999, the Commission issued a "partially positive" decision on the PIP. This said that the programme could be made compatible with the Common Market, if the part of the scheme dealing with speculative development was also brought under the relevant State Aid rules. In essence, this would amount to running PIP solely within the Assisted Areas and subjecting it to the Aid Intensity ceilings which apply within these areas. As this would involve the loss of the majority of the type of projects funded under PIP (which occur either outside the Assisted Areas, or receive grant above the aid ceilings), we took the decision to close the PIP as of the decision date. DGIV have allowed transitional arrangements for projects already in the "PIP pipeline". They said that all projects where a formal application had been submitted by the decision date may proceed through the appraisal process to their logical conclusion. This decision will allow several hundred projects to complete the appraisal process.

  8.  No further new applications could be allowed after 22 December 1999. Until that date, PIP operated under the 1995 Commission approval. After 22 December, the scheme in its current form was not approved. Grant payments to developers (other than for projects on the transitional list) would have been illegal State aids, and the Commission could have required that these be paid back (with interest) by developers.

THE CONTRIBUTION THAT GAP FUNDING HAS MADE IN REGENERATING DERELICT AND OTHER DIFFICULT SITES IN AREAS OF "MARKET FAILURE"

  1.  Gap funding served our regeneration policy objectives: bringing derelict sites and buildings into use, generating jobs, reclaiming brownfield land and combating social exclusion. It helped achieve these objectives in a cost effective way, by providing the minimum assistance to persuade a developer to go ahead, and levering in significant private sector contributions.

  2.  One strength of PIP was the flexibility it gave EP to support projects through a range of mechanisms, including joint venture, gap funding grant, loan and rental guarantee, in partnership with the private and public sectors.

  The examples given in Annex A to the memorandum reflect that range of possibilities although all include the gap funding approach.

PIP Outputs

  In the five full years of operation since its introduction a total of £1,100 million PIP investment has been approved in over 1,000 projects.

  By way of illustration, projects approved under PIP in the last three years of operation are expected to give rise to the following outputs once the projects are completed:

    —  50,700 jobs created/safeguarded;

    —  2,060,000 m2 of industrial/commercial floorspace;

    —  1,500 ha land reclaimed/serviced;

    —  7,600 housing units;

    —  £1,490 million private sector investment.

  Many projects involve other public sector investment, particularly ERDF, and the above figures reflect outputs which other public bodies are helping to achieve. However, the PIP appraisal process ensures that its investment is the minimum necessary to allow all projects to go ahead.

  For the last financial year (1999-00) projects for which PIP funding was approved attracted £200 million of other public sector funding of which the ERDF represents £89 million. The outputs attributable to the PIP element of funding amounted to:

    —  11,900 jobs;

    —  445,000 m2 industrial/commercial floorspace;

    —  630 ha land reclaimed;

    —  1,900 housing units;

    —  £353 million private sector investment.

    (Note: these figures are included in the cumulative totals above.)

THE CONSEQUENCES OF THE EUROPEAN COMMISSION RULING FOR URBAN REGENERATION, AND THE ALTERNATIVE SCHEMES WHICH SHOULD BE CONSIDERED TO REPLACE GAP FUNDING

  1.  These two questions are closely linked and are answered together. Following immediately on the Commissions's decision on PIP, the Department put proposals for the short term to the Commission. Shortly afterwards, discussions on the longer term future were set in train.

(i)  PIP has been closed, and no new applications for gap funding are allowed

  The most immediate consequence is that the Commission has decided that the use of gap funding for the private sector is not compatible with the common market except in so far as it falls under a Regional Aid framework. But it is not feasible to run PIP solely as a Regional Aid scheme, as most projects we would wish to target would be ineligible. We informed EP and the RDAs on 22 December that PIP was therefore closed from that date. No new applications for gap funding under PIP could be accepted after 22 December 1999, so unless a former PIP proposal was eligible under the Commission's transitional arrangements (at formal application stage by 22 December) it fell.

(ii)  We need to put in place short term measures to clarify what RDAs may do

  In the short term, in order to establish clearly for the RDAs exactly what the Commission's interpretation of the State Aid rules will allow us to do, we have notified the Commission of a number of new schemes—two are for aid to developers for both bespoke and speculative schemes within Assisted Areas—these would provide gap funding, and would be State Aid, but should hopefully be acceptable under the Regional Aid framework. Further new schemes have also been notified—a revised direct development scheme, environmental and neighbourhood renewal schemes (none of which would be State Aid). We are currently answering questions from the Commission on the first of three notifications and the Commission's decisions on these are awaited. They cannot however be implemented (even if approved) until the Commission also approves a new Assisted areas map for the UK.

(iii)  Direct development and funding consequences for the RDAs of moving to a predominantly direct development approach

  In the meantime, the RDAs have only one avenue to pursue regeneration projects of the type funded under PIP—direct development. Under this route, the RDAs or another public authority would have to purchase the regeneration sites, and then either undertake some or all of the development themselves, (or with public sector partners) or enter into a partnership with a developer (via an open competitive bidding process). Although RDAs already use direct development to a limited extent, it has not been the preferred approach for physical regeneration because of its costs, and the fact that it limits the valuable private sector input.

(iv)  Consequences over the longer term

  On the longer term future of partnership working in regeneration, DGIV recognised that their decision will make joint working with the private sector very difficult in future.

  They therefore invited us to submit information on the regeneration problems we are trying to address and offer ideas on how these might be met within the State Aid rules. We have now presented two papers reviewing the problems, and explaining why the existing State Aid rules do not offer any potential alternatives which would enable us to fund the number and range of projects supported under PIP. We have suggested that a new framework for regeneration within the scope of the State aid rules might provide the answer.

(v)  Possible new regeneration framework

  An agreement with the Commission to issue a new framework for the approval of aid in the regeneration field indicating that they consider appropriate physical regeneration projects to be compatible with the existing State aid rules in the Treaty of Rome would be the preferred solution. If the Commission accepts the concept of a new framework, then any subsequent scheme would have to be within its scope and would have to be made subject to strict conditions to prevent the possibility of abuse of the State aid rules, by any Member State. These conditions are likely to include restrictions such as limits on the levels of grant, a limitation on the development costs which may be considered eligible for the calculation of grant, and strict requirements for clawback. It is within the Commission's power to allow a new framework within the Treaty, if they are convinced of the need.

(vi)  Public procurement exercises

  One of the Commission's objections to PIP was the fact that proposals came forward from the ultimate recipients of the support (the developer/landowner) rather than from the public sector. We have considered whether a full and open procurement exercise involving a set of criteria for development in a certain area, with bids invited from site owners in that area, might offer a partial solution. We are raising this approach with the Commission.

THE SCALE OF PUBLIC FUNDING REQUIRED TO ENABLE ALTERNATIVE SCHEMES TO PRODUCE EQUIVALENT RESULTS

  1.  The immediate available alternative to gap funding is direct development. This has the disadvantage of being considerably more expensive than gap funding in the early years. Once recipients begin to come back to the private sector several years down the line, direct development may compare well to gap funding in cost terms.

  2.  Direct development costs more than the gap funding approach under PIP, as the public sector must acquire the development sites up front and in some cases undertake some or all of the development. This means that the public sector is effectively replacing the valuable private sector contribution in the early stages of the project. The financial consequences of a predominantly direct development approach are currently under consideration in the context of the Spending Review 2000.

WHAT PROVISIONS SHOULD BE CONTAINED IN A NEW REGENERATION FRAMEWORK?

  1.  We are asking the Commission to consider a new regeneration framework. We are in the early stages of discussions on this, and the Commission's deliberations are likely to be measured, taking account of the position in other Member States. Our argument for this framework is based on our view that physical regeneration serves Community objectives of improving both the standard of living and quality of life within the Member States, promoting a high level of protection of the quality of the environment and promoting sustainable development (as set out in Article 2 of the Treaty of Rome). We consider that a new framework would promote these Article 2 objectives.

  2.  We are deploying other arguments in support of the new framework:

    —  that none of the existing frameworks (for example for Regional aid or Environmental aid) serves regeneration goals;

    —  that regeneration is a "horizontal" issue where a framework could apply across the full range of economic sectors (as opposed to the "sectoral" frameworks which exist for State aid to particular industries, such as motor manufacture);

    —  and that all existing (and potential) Member States could benefit from the existence of the framework for furthering regeneration objectives.

  3.  If the Commission is able to accept the idea of a new framework—and it is by no means clear that they will—we will then move on to discuss its content with them. We will wish to discuss conditions which make it possible for us to support a wide range of projects across all areas of England. The Commission will clearly wish to ensure that any new arrangement would not leave open the possibility of abuse of the State aid rules, and would be applicable across the whole EU.

June 2000


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 14 September 2000