Select Committee on Health Memoranda


MEMORANDUM BY THE DEPARTMENT OF HEALTH (CONT.)

(ii)   Could the Department include a commentary explaining the key factors that determined those percentage growth increases shown in the table?

  2.  The initial allocation of resources for 2000-01, announced in December 1999, aimed to balance two objectives:

    (i)  to maintain continuity and stability in the service; and

    (ii)  to move as quickly as practicable to fair shares as represented by weighted capitation targets.

  3.  These two objectives were pursued via the distribution of resources from both the Modernisation Fund and from general funds.

  4.  The first objective was pursued by distributing some additional funds to all health authorities. The second objective was pursued by distributing the remaining funds mainly to bring under target Health Authorities nearer to their weighted capitation target.

  5.  The Modernisation Fund elements of allocations were distributed in two ways:

    (i)  as part of allocations:

    —  £276 million for tackling waiting;

    —  £60 million for primary care;

    —  £21.9 million for adult mental health;

    —  £79 million for information management and technology;

    —  £9 million for cancer (gynaecological).

    (ii)  allocations:

    —  £15 million for adult mental health funding has been targeted to deliver an extra 250 secure places;

    —  £5 million for adult and adolescent mental health services has been distributed to all Health Authorities using the psychiatric needs indices of the weighted capitation formula.

  6.  The distribution of the additional £660 million in March 2000 is covered in question 1.8.

(iii)   Could the Department update the Committee on recent developments in allocations of HCHS resources and provide the timetable for any planned changes?

  7.  There have been no recent developments. The wide ranging review of the formula used to make allocations to Health Authorities and Primary Care Groups/Trusts is still in progress.

  8.  Other than routine data changes, the current freeze to the formula will last until at least 2001-02.

4.6  Capital Charges

Could the Department give an account of the funding system for capital charges, including the basis on which funding is allocated, whether by formula or otherwise? Could the Department explain the reasons for and the significance of the reclassifation of Trust Debt Remuneration as an appropriation in aid in 1999-2000?

  1.  The funding system for capital charges is a circular flow of funds at national level.

  2.  Capital charges are estimated annually by Health Authorities and NHS trusts in advance. The estimated level of capital charges is added to the funds agreed during the Spending Review. Funding for capital charges is then allocated to Health Authorities as part of their general allocations. For NHS trusts the costs they incur on capital charges must be met from the income they earn from service agreements with Health Authorities. The depreciation element is retained by the NHS trust to help fund the capital and the cost of capital element is repaid to the Department as Trust Debt Remuneration (TDR).

  3.  From April 1999 this has been treated as Appropriation in Aid of the Vote. Previously the receipt was accounted for as an Extra Receipt to the Consolidated Fund. This is a technical reclassification. The principal change is to the system of Parliamentary reporting under which the Departmental Expenditure Limit (DEL) replaces the old Control Totals. TDR is included in the DEL both as a provision to Health Authorities and receipt from NHS Trusts. This is because Departmental DELs should contain all the expenditure which they control.

  4.  The reclassification of TDR has no effect on the way the capital charges funding system works for the NHS.

4.7  HCHS Capital Prioritisation

Could the Department explain the process by which the Capital Prioritisation Advisory Group makes decisions, including the basis on which schemes are prioritised for public and private funding, and the criteria used to allocate schemes to private or public funding? Could the Department give examples of schemes which have been turned down, and explain why?

  1.  Ministers make the decision on the prioritisation of major investment schemes. The role of the Capital Prioritisation Advisory Group (CPAG), assisted by a technical sub-committee, is to assess the proposals for major investment and report to Ministers.

  2.  The Schemes are prioritised on the basis of health service need. CPAG is responsible for developing the criteria against which this is assessed, and reporting on each scheme against these criteria.

  3.  CPAG assesses schemes on the basis of information contained in a document known as the Strategic Outline Case (SOC). Regional Offices are responsible for deciding, based on regional priorities, which schemes should prepare a SOC. The SOC document is written jointly by the Regional Office and the relevant health authority and NHS trusts, and is presented to CPAG by the scheme sponsors for clarity. Each site with a proposed development is visited by members of the Technical Sub-Committee who report their findings to CPAG. CPAG then advises Ministers.

  4.  The decision on private or public finance does not form part of the prioritisation process. Once prioritised by Ministers the scheme is subject to the normal business case approval procedures. Although it has been demonstrated that PFI offers the public sector value for money, and it is our expectation that the majority of major projects in the NHS will be funded using PFI, each project is assessed on an individual basis. It will have to be demonstrated in a Full Business Case that the PFI option is affordable to the NHS, meets NHS service needs and offers value for money when compared to the publicly funded alternative. These value for money appraisals are carried out by the NHS trust and the NHS Executive, not the private sector.

  5.  The number of schemes which can be prioritised at one time is limited because of constraints on overall affordability within the NHS. The following are examples of schemes which were not privatised at the time a SOC was put to CPAG.

(i)   Leeds Teaching Hospitals NHS trust

    This scheme was not prioritised on the second wave of major schemes announced in April 1998. The proposal was to create an oncology wing at St James's Hospital to allow relocation of radiotherapy services. Although there was a clear clinical need for this scheme, Ministers felt that the case would be strengthened by expanding its scope to include other aspects of rationalisation of acute services in and around Leeds.

    The scheme was reconsidered and reshaped to complete the rationalisation of acute services, and was given priority in the third wave of major schemes announced July 1999.

(ii)   Portsmouth Hospitals NHS trust

    This scheme was not prioritised in the second wave of major schemes announced in April 1998. The scheme involved the rationalisation of acute services from three sites onto one. There was a strong clinical need for the scheme, but Ministers felt that it would be better considered when local uncertainty surrounding the future of the military hospital at Gosport had been resolved.

    The closure of the military hospital was subsequently announced, and the scheme was given priority in the third wave of major schemes announced in July 1999.

4.8  LONG TERM CAPITAL PROJECTS AND PFI

(i)   Could the Department provide a table showing all publicly funded capital projects with a total cost above £10 million which are under construction during 2000-01? Could this also show the original and current estimated completion dates along with a percentage figure for any additional time overrun/saving? Likewise, the original total cost and current estimated out-turn cost should be provided along with a percentage cost performance figure.

Could the Department provide a commentary on cases where there are significant discrepancies between original estimates of completion dates and/or expenditures and current estimates?

(ii)   Could the Department provide details of PFI projects with a capital value of £10 million or over approved since 1992, including their current status?

(iii)   Could the Department provide tables showing the planned and actual annual contribution to capital from PFI, and the forecast level of investment generated by schemes over £10 million, plus an aggregate of those below £10 million, between 1997-98 and 2002-03? What revenue or transitional support is being given to support the scheme? Could the Department provide further details of locally agreed arrangements to provide revenue or transitional support to schemes?

(iv)   Could the Department provide a table showing the increases to the capital cost of schemes since the last expenditure questionnaire and provide a commentary on changes of more than 10 per cent? In addition, could the Department provide the intitial costs of PFI schemes at outline business case (baseline year) for those schemes reported in last year's questionnaire and comment on increases?

(v)   Could the Department provide data on the revenue consequences of schemes which have reached financial close and represent long term contractual commitment over the next 25 years? Could the Department provide an update on the Departmental Report table showing the source and applications of HCHS capital, giving the outturn position for 1999-2000?

(vi)  For major projects (currently defined as those greater than £25 million in value), could the Department please provide a comparison between the PFI price and the publicly financed option. The publicly financed comparator's costings should be broken down as follows:

    Basic construction contract, broken down between pre-implementation and post implementation costs;

    The value of risk adjustment, again broken down between pre-implementation and post implementation costs, in both pounds and percentage terms, and

    The final total real full life cost of both options.

    Where adjustments have been made to the PFI costs (to bring prices to a like for like basis), these should be broken down on the same basis as the publicly funded option.

    Could the Department also provide a brief commentary on any apparent differences between the reported schemes.

(vii)   Could the Department update the information given in Table 4.8g on donated capital additions by region only?

(viii)  Could the Department list, by scheme, how much has been spent on developing business cases for a sample of schemes worth over £10 million, identifying which schemes are publicly financed and which financed through the PFI? Where schemes have reached completion, could the estimated development costs be compared with actual costs?

(ix)  Could the Department detail for every NHS trust with a hospital development, whether publicly or privately financed, worth over £25 million (a) the number of NHS overnight beds by category currently provided by the trust and (b) the number of NHS overnight beds by category to be provided when the development is completed?

(x)  For each PFI scheme could the Department provide the estimates of the unitary fee and split between the availability and facilities management fee at outline business case (baseline year) and the actual cost of the unitary fee split as above on signing off the FBC? Could the Department comment on how any increases were funded?

(xi)  For each PFI scheme signed or given approval in principle, could the Department provide income and capital charges of Trusts which make up each PFI scheme prior to signing and income, availability fee and capital charges on retained estate for each scheme having signed, or estimates for those schemes which have not yet signed?

(i)   Could the Department provide a table showing all publicly funded capital projects with a total cost above £10 million which are under construction during 2000-01? Could this also show the original and current estimated completion dates along with a percentage figure for any additional time overrun/saving? Likewise, the original total cost and current estimated out-turn cost should be provided along with a percentage cost performance figure.

  1.  Table 4.8.1 provides details of all publicly funded long-term capital projects with a total cost of over £10 million which are forecast to be under construction during 2000-01.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2000
Prepared 27 October 2000